State Transportation
/
Improvement Program

.;
~. ~ "-~


...

~ ~

.



t !!'
,.
...
':.r

State Transportation Improvement Program

Introduction



Statewide Transportation Planning Process Certification

STIP Funds by Category

Glossary of Terms



Understanding STIP Entries

Map ofGeorgia



Highway and Bridge Projects



Transit Projects

STIP Financial Plan

I
I ')1of
~

~I
..
.":1
I
I ,. I '.j I\:

m ...
I'e"~~.c

i'c'. ;
I~ .
; :--

li ~.~

.:
.;.:

,.1'~ :-,.

:lIi.

11':.'
\ ':,.

[.....
.
~ ::

1- ""

State Transportation Improvement Program

.Introduction

We are pleased to present the State Transportation Improvement Program (STIP). Projects listed in this document were identified through the planning process and are important to the state's transportation program for rural areas.
I
The srn- includes Highway and Bridge, Bicycle, Pedestrian, Transportation Enhancement
Activities and Public Transportation (transit) projects. Project related cost, such as Preliminary Engineering (PE), Right of Way (ROW), and Construction are given for highways and Capital and Operating cost for public transit. The projects are organized in alphabetical order by county with the same information categories listed for each of them.
.
The STIP was developed under guidelines provided by the Transportation Equity Act for the 21st Century (TEA-21), passed by Congress in 1998. TEA-21 continues the initiatives started under the Intermodal Surface Transportation Efficiency Act of 1991 (ISTEA). Projects in the STIP emphasize the maintenance, safety, and improvement of existing transportation facilities, and public transportation systems.
The STIP is fiscally balanced, including only those projects with funding available or having a reasonable expectation of obtaining funds. Federal funds for fiscal years 2000, 2001 and 2002 are program estimates and will not be final until after the federal budget is implemented on October 1 of each year.
Georgia continues to grow in population at more than double the national average. Georgia's economy is also growing, leading to increased demands on the transportation system. The STIP process insures that we receive maximum benefits from available funding and that Georgia's transportation system will continue to support and promote Georgia's growth and economy.
The Department of Transportation wishes to thank all of the citizens and local officials for taking the time to provide input on the development of this program.

I I
...
z- n1
'~I
I I I
11
~w

I
" T,' _ . '- ~ "
I

I

I

Appendix D-I

I

I

STATEWIDE TRANSPORTATION PLANNING PROCESS CERTIFICATION

I

(To be submitted with each Statewide Transportation Improvement Program)
I

In accordance with 23 CFR 450.220, the Georgia Department of Transportation hereby

certifies that its statewide transportation planning process is addressing major issues

I

facing the State and its non-urbanized areas, and is being carried out in accordance with

the following requirements:

I

L 49 U.S. Section 5323(k), 23 U.S.C. 135, and 23 CPR part 450.220;

I

Il. Title VI of the Civil Rights Act of 1964 and the Title VI Assurance executed by

I

each State under 23 U.S.c. 324 and 29 U.S.c. 794;

.

I

ID. Section 1101 of the Transportation Equity Act for the 21st Century (Pub. L. 105178) regarding the involvement of disadvantaged business enterprises in the

I

.4.

FHWA and the FfA funded project (Sec. 105(f), Pub. L. 97-424, 96 Stat. 2100, 49 CFR part 23);

I

I. ..
IV. The provisions of the Americans With Disabilities Act of 1990 (Pub. L. 101-336,

I

104 Stat 327, as amended) and the U.S. DOT implementing regulation;

I

V. The provision of 49 CPR part 20 regarding restrictions on influencing certain

I

activities; and

I
VI. (for states with non-attainment and/or maintenance areas outside metropolitan

planning area boundaries) Sections 174 and 176 (c) and (d) of the Clean Air Act
as amended (42 U.S.C. 75 ,7506 (c) and ( a.

I

I

I

I

Title

I

I

I

I

I

I

I

.. . ~ .. '.: ..:

'.-.' .- , :.-_ --c-. -_ -. -_ ~ - . ~ .

.?
'-
a

STIP FUNDS BY CATEGORY Fiscal Years 2000-01-02 $4.38 Billion

ReconstlRehab . $1,501

Other . $115

Public Transit $414

Safety $438 Maintenance $241
Dollars shown in Millions


Enhancement. $112
L New Construction $693 Bridge $869
..

-. ,"

;;.

GLOSSARY OF TERMS

.ft

J

:l

ATMS

Advanced Transportation Management System; a computerized system that integrates video, voice, and

:n

data management functions to collect information about the transportation infrastructure and performance

~i

analysis as well as support traffic management decisions based on real-time information.



CMAQ

Congestion Mitigation and Air Quality Improvement Program; directs funds primarily to areas that have

failedto reach certain air quality standards. Projects allowed under this program include mass transit

improvements and high-occupancy vehicle facilities.

CST Construction; phase of a project that includes the actual construction of the project.

DONOR STATE BONUS Donor State bonus: Donor states are states that contribute more to the Highway Trust Fund than they receive back in federal-aid highway programs. These states receive a predetermined amount based on a
a comparison of projection of all payments into the Highway Trust Fund and the amount received in
federal-aid apportionments. Starting with the state with the lowest return, states are brought up to the level of return for states with the next higher level of return until ayailable funds are depleted.

FED Share Federal Share; portion of funding to be paid for with federal money.

GAShare

Georgia Share; portion of funding to be paid for with state money.

r

GF Grandfathered; projects in the non-attainment area that are included in the STIP. These projects are included because they have environmental clearance (NEPA), an approved conformity determination and are consistent with the design concept modeled in the last approved conformity analysis in 1995.

HPP High Priority Project; list of 1,850 high priority projects specified by Congress in TEA-21. Funding for these projects totals $9.4 billion over the six years of TEA-21. Georgia will receive $283.87 million for 40 projects.

mGHWAY TRUST FUND Federal account established by law to hold receipts collected by the government, earmarked for highway programs and a portion of the mass transit program; supported by the federal gasoline tax and other user taxes.

INTERMODAL SURFACE TRANSPORTATION EFFICIENCY ACT of 1991 (lSTEA) Transportation bill approved by Congress in 1991.

1

METROPOLITAN PLANNING ORGANIZATION (MPO) Required by federal regulations in urbanized areas to develop transportation plans and programs; responsible for developing the Transportation Improvement Program (TIP).

NEPA National Environmental Policy Act of 1969; requires federal government to use all practical means and measures to protect environmental values; makes environmental protection a part of the mandate of every federal agency and department.

NHS National Highway System; consists primarily of the Interstates and other major routes. Includes a large percentage of urban and rural principal arterials.

NONATTAINMENT. The 13 county area around Atlanta that fails to meet federal air-quality standards. Projects in the non-
attainment area are not allowed to proceed if there is an increase in capacity of a roadway unless they
were identified in the 1995 TIP for Atlanta.

OBLIGAnON CEILING . The maximum amount that a state is expected to receive from the Highway Trust Fund.

OTH Share

Other Share; portion of funding to be paid for with money other than federal or state funds; generally

provided by local governments.

.

PE Preliminary Engineering; phase of a project that includes the development of the concept, survey, environmental documentation and design plans.

ROW Right of Way; phase of a project that includes the acquisition of any necessary property for the construction of the project.

STATE AID LET Projects that are. funded with state money.

STATE IDGHWAY SYSTEM Network of roads maintained by the state including road and bridge construction, maintenance, rehabilitation and restoration. There are approximately 17,947 miles of state highways in Georgia which .make up 16% of the total public road system in the state.

-,

STP Surface Transportation Program; federal funding category that provides funding for projects on any

federal-aid highway, including the NHS, bridge projects on any public road, transit capital projects, 'and

public bus terminals and facilities.

.~
TRANSPORTATION EQUITY ACT FOR THE 21ST CENTURY (TEA.21)

Six year transportation bill approved by Congress in 1998.

2'

TRANSPORTATION IMPROVEMENT PROGRAM (TIP) In metropolitan areas over 50,000 in population, a program of federally funded transportation projects proposed to be carried out in the first three years of adoption by the MPO. There are 11 urbanized areas in Georgia - Chattanooga, Rome, Athens, Augusta, Savannah, Brunswick, Macon, Columbus, Albany, Atlanta, and Warner Robins. The TIPS's are incorporated into the STIP as adopted by the respective governments and approved by the Governor, with no .changes.

TYPE WORK- category of project and source of funding

RECSTIREHAB

ReconstructionlRehabilitation; work, such as widening, to be performed on an existing roadway

or structure.

NEWCONST.

New Construction; a new roadway or structure that is to be built on new location.

BRIDGE PROGRAM

Bridge Program; work that is to be performed on existing bridges or the construction of new

bridges. Iricludes construction and maintenance.

SAFETY

Safety; projects that serve the purpose of improving the safe operation of state and local

transportation facilities. Generally do not add capacity to a roadway.

ENHANCEMENT

Transportation Enhancement Activities (TEA); non-traditional transportation projects, sponsored

by local governments and administered by DOT.

PUBLIC TRANSIT '

Public Transportation; funding identified to assist local governments in operating their existing

.

public transportation systems and to purchase necessary new equipment.

I

MAINTENANCE

Maintenance; improvements, such as resurfacing, performed on existing roadways or structures.



3

'1,'
.,

i . ~ . u \
Understanding STlp Entries
Typical project

This is the PI or Project Identification number used throughout the life of the project for tracking purposes.

Preliminary Engineering Year that funding became available for this phase.

DRAFT STATE TRANSPORTATION IMPROVEMENT PROGRAM

Friday, March 12, 1999 Page 20 of 221

Type of work, replacement of an existing bridge. See Glossary of Terms for further definitions.
Funding type: third item on top line. May be Bridge, STP, NHS, etc. & refers to specific type of federal funds to be used.
Project description: State route 90 at Little House Creek approximately 1.7 miles south of Fitzgerald. Passing lane projects may only indicate milepost numbers.
.

Federal share of construction.. Georgia share of construction.
Construction. The DOT is scheduled to let to construction after 2002.
Right of Way to be purchased after 2002. If dollar amount is shown, that is the federal funding; if LOCL is shown, right of way to be purchased by local government.

.~



~ I,;


,-,
c
1


HIGHWAYS AND BRIDGES . SAFETY
MAINTENANCE BICYCLE AND PEDESTRIAN
ENHANCEMENTS
..

.x
.~.

f' '
't
County

~

Appling

Atkinson

I

Baker Baldwin

Banks

I

Barrow Bartow

Ben Hill

I

Berrien Bibb

Bleckley

I-

Brantley Brooks

Bryan

I

Bulloch Burke

Butts

I

Calhoun Camden

Candler

I

Carroll Catoosa

Charlton

I

Chatham Chattahoochee

Chattooga

I

Cherokee Clarke

Clay

I

Clayton Clinch

Cobb

I

Coffee Colquitt

I

Columbia Cook Coweta

I

Crawford Crisp

Dade

I

Dawson Dekalb

Dodge

I

Dooly Dougherty

Douglas

I

I

Page
13 14 15 16 17 .18 20 23
24
25 30 31 32 33 34 36 37 38 39 41 42 44 46 47 51 52 53 57 60 61 64 65 71 73 75 77 78 81 82 83 84 85 90 91 92 94

County
Early Echols Effingham Elbert Emanuel Evans Fannin Fayette Floyd Forsyth Franklin Fulton Gilmer Glascock Glynn Gordon Grady Greene Gwinnett Habersham Hall Hancock Haralson Harris Hart Henry Houston Jackson .Jasper Jeff Davis Jefferson Jenkins Johnson Jones Lamar Laurens Lee Liberty Lincoln Lowndes Lumpkin Macon Madison Marion McDuffie McIntosh

Page

98

99

100

101

102

,.

104

105

106

108

111

112 113,

139

140

141

143

145

146

. 148

153

154

157

158

161

163

164

168

170

172

173

174

i76 177 .

178

179

180

182

183

184

185

187

188

189

191

.:"

192

1, 93

..
'.

..... ,'s

~1
County

r'lI .:t

Meriwether

Miller

,~

Mitchell

.:l:lr

Monroe

Montgomery

I: 1"-

Morgan Murray

Muscogee

I

Newton Oconee

Oglethorpe

I

Paulding Peach

Pickens

I

Pierce Pike

Polk

I

Pulaski Putnam

Quitman

I

Rabun . Randolph

Richmond

~

Rockdale Schley

Screven

fi

. Seminole Spalding

Stephens

I

Stewart Sumter

I",

Talbot Taliaferro

Tattnall

~

Taylor Telfair

Terrell

I

Thomas Tift

Toombs

Towns

G

.Treutlen

Troup

I

Turner Twiggs

Union

I

I

Page
194 196 197 198 199 200 201 202 205 207 208 209 210 212 213 214 215 217 218 219 220 221 222 225 227 228 229 230 233 234 235 237 238 239. 240 241 243 244 246 248 250 251 252 254 255 256

County
Upson Walker Walton Ware Warren Washington Wayne Webster Wheeler White Whitfield Wilcox WilkeS Wilkinson Worth

Page

257

258

259

261

262



263

265

266

267

268

269

271

272

273

275


;,

STATE TRANSPORTATION IMPROVEMENT PROGRAM

ALL COUNTY

PROJECT: 0000045 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: ARCHAEOLOGICAL AND HISTORIC GIS

PE:LOCL ROW: LOCL CST: 2000 FED Share:

9/16/99 Page 1 of275
$462,000 $369,600

OTH Share:

$92,400

PROJECT: 0000064 TYPE WORK: ENHANCEMENT'

FUND: STP

PE:LOCL

LENGTH (miles / km) 0 /0.00

ROW: LOCL

I

DESCRPT: INTERSTATE WILDFLOWER PROGRAM

CST: 2000 FED Share:

$500,000 $400,000

'~...

PROJECT: 0000065 TYPE WORK: ENHANCEMENT

FUND: STP .

GAShare: PE:LOCL

$100,000

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: INTERSTATE GATEWAY LANDSCAPING FY 2000
I

CST: 2000 FED Share:
GA Share:

$1,250,000 $1,000,000
$250,000

I:

PROJECT: 0000066

TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

PE:LOCL ROW: LOCL

DESCRPT: INTERSTATE GATEWAY LANDSCAPING FY 2001

CST: 2001

$1,250,000

I

FED Share: GAShare:

$1,000,000 $250,000

I.

PROJECT: 0000205

TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: TEA PROJECT MANAGEMENT 2000-2003

PE:LOCL ROW: LOCL CST: 2000

$2;000,000

I,

FED Share:

$2,000,000

PROJECT: 0000206 TYPE WORK: PLANNING

FUND: OTHER

PE:2000

$1,875,000 _

~

LENGTH(miles/km) 0/0.00 DESCRPT: NATIONAL CORRIDOR PLANNING STUDY - COLUMBUS TO SAVANNAH

ROW: NONE CST: NONE

I

PROJECT: 0000207 TYPE WORK: OTHER .

. FUND: OTHER

I

LENGTH(miles/km) 0/0.00 DESCRPT: ITS: EXPENSES OF THE CVlSN TEAM IN DEPLOYMENT WORKSHOPS

PE:2000 ROW: NONE CST: NONE

$40,000

I

PROJECT: 04MOOO- TYPE WORK: MAINTENANCE

FUND: 1M

PE:NONE

LENGTH (miles / km) 0/0.00

ROW: NONE

I

DESCRPT: LUMP SUM FOR INTERSTATE MAINTENANCE FOR FY 2000

CST: 2000 FED Share:

$5,390,000 $4,851,000

GAShare:

$539,000

I

PROJECT: 04MOOI- TYPE WORK: MAINTENANCE

FUND: 1M

PE:NONE

LENGTH (miles / km) 0 /0.00

ROW: NONE

I

DESCRPT: LUMP SUMFOR INTERSTATE MAINTENANCE FOR FY 2001

CST: 2001 FED Share:

$13,000,000 $11,700,000

GA Share:

$1,300,000

-----------------_._----.....;-------_._.__.._.._--------

STATE-TRANSPORTATION IMPROVEMENTPROGRAM

9116l9!

Page2of275

ALL COUNTY

PROJECT: 04M002- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles I km) 0/0.00

DESCRPT: LUMP SUM FOR INTERSTATE MAINTENANCE FOR FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$13,000,000 $11,700,000
$1,300,000

PROJECT: 04MBOO- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles I km) 0/0.00

DESCRPT: LUMP SUM INTERSTATE BRIDGE PAINTINGIMAINTENANCE FOR FY 2000 I

PE:NONE' ROW: NONE CST: 2000 FED Share: GA Share:

$4,735,000 $4,261,500
$473,SOO

PROJECT: 04MBOI- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles I km) 0/0.00

DESCRPT: LUMP SUM INTERSTATE BRIDGE PAINTINGIMAINTENANCE FOR FY 2001

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

$744,000 $669,600
$74,400

PROJECT: 04MB02 TYPE WORK: MAINTENANCE

FUND: 1M

.

LENGTH (mileslkm) 0/0.00

DESCRPT:LUMP SUM INTERSTATE BRIDGE PAINTINGIMAINTENANCE FOR FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$S,OOO,OOO $4,500,000
$500,000

PROJECT: 171S40- TYPE WORK: MAINTENANCE

FUND: STP .

PE:NONE

LENGTH (miles / km) 0 10.00

ROW: NONE

DESCRPT: BRIDGE PAINT IN CLARKE-FRANKLIN-JACKSON-STEPHENS-WALTONIYS40

CST: 2001

LUMP SUM PROJECT

FED Share:

ASSOCIATED PROJECTS: 17YS40-

GAShare:

$303,000 $242,400
$60,600

PROJECT: 17YS40- TYPE WORK: MAINTENANCE'

. FUND: 1M

LENGTH (miles I km) 0 10.00

DESCRPT: BRIDGE PAINT IN CLARKE-FRANKLN-JACKSON-STEPHNS-WALTONII71S40

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 171S40-

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$104,000 $93,600 $10,400

PROJECT: 210880- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles Ikm) 1/1.61

DESCRPT: 1-20 SAFETY UPGRADES @ 4 LOCINEWTON & 1 LOCIMORGAN

ASSOCIATED PROJECTS: 21088X-

PE: 1997 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$8,663,000 $7,796,700
$866,300

PROJECT: 271175- . TYPE WORK: MAINTENANCE

FUND: STP

PE:NONE

LENGTH (mileslkm) 0/0.00

ROW: NONE

DESCRPT: "BR"PAINT IN BALDWNIBLCKLY/GRENIHANCKlJASPRlMORGINEWTNIRCHMD CST: 2001

LUMP SUM PROJECT

FED Share:

. ASSOCIATED PROJECTS: 27Y17S-

GA Share:

$185,000 $148,000
$37,000

PROJECT: 27Y175- TYPE WORK: MAINTENANCE

FUND: 1M

. PE: NONE

. LENGTH (miles I km) 0/0.00

ROW: NONE

DESCRPT: "BR"PAINT IN BALDWNIBLCKLY/GRENIHANCKlJASPRlMORGINEWTNIRCHMD CST: 2001

LUMP SUM PROJECT

FED Share:

ASSOCIATED PROJECTS: 271175-

GA Shiue:

$SO,OOO , $45,000
$5,000

I..;......

STATE TRANSPORTATION IMPROVEMENTPROGRAM

ALL COUNTY

PROJECT: 312180- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km) 0/0.00

DESCRPT: BRIDGE PAINTING IN BIBB-HOUSTON-MACON-PEACH COUNTIES/31 Y180

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 31Y180-

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

9/16199 Page30f275
$270,000 $243,000
$27,000

. PROJECT: 312185- TYPE WORK: MAINTENANCE

FUND: 1M

, LENGTH (miles / km) 0/0.00

DESCRPT: BRIDGE PAINTING IN HENRY-PEACH-TALBOT-TROUP COUNTIES/31Y185

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 31Y185-

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

$403,000 $362,700
$40,300

PROJECT: 315000- TYPE WORK: MAINTENANCE

FUND: NHS

PE: NONE

LENGTH (miles / km) 0 /0.00

ROW: NONE

DESCRPT: LUMP SUM MAINTENANCE ON NATIONAL HIGHWAY SYSTEM FOR FY 2000

CST: 2000

FED Share:

GAShare:

$28,915,000 $23,132,000
$5,783,000

'PROJECT: 315001- TYPE WORK: MAINTENANCE

FUND: NHS

PE:NONE

LENGTH (miles/km) 0/0.00

ROW: NONE

DESCRPT: LUMP SUM MAINTENANCE ON NATIONAL HIGHWAY SYSTEM FOR FY 2001

CST: 2001

FED Share:

GAShare:

$32,500,000 $26,000,000
$6,500,000

PROJECT: 315002- TYPE WORK: MAINTENANCE

FUND: NHS

PE:NONE'

LENGTH (miles / km) 0/0.00

ROW: NONE

DESCRPT: LUMP SUM MAINTENANCE ON NATIONAL HIGHWAY SYSTEM FOR FY 2002

CST: 2002

FED Share:

GAShare:

$15,500,000
$12,400,000 $3,100,000 '-

PROJECT: 315UOO- TYPE WORK: MAINTENANCE

FUND: NHS

LENGTH (miles / km) 0 /0.00

DESCRPT: LUMP SUM INTERCHANGEIROADWAY LIGHTING FOR FY 2000

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$960,000 $768,000 $192,000

PROJECT: 315UOI- TYPE WORK: MAINTENANCE

FUND: NHS

LENGTH (miles/km) 0/0.00

DESCRPT: LUMP SUM INTERCHANGEIROADWAY LIGHTING FOR FY 2001

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

$1,000,000 $800,000 $200,000

PROJECT: 315U02- TYPE WORK: MAINTENANCE

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM INTERCHANGEIROADWAY LIGHTING FOR FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: GA Share:

$1,000,000 $800,000 $200,000

PROJECT: 31Y180- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles'; km) 0 /0.00

DESCRPT: BRIDGE PAINTING IN BIBB-HOUSTON-MACON-PEACH COUNTIES/312180

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 312180-

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$35,000 $28,000 $7,000

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

ALLCOUNIT

PROJECT: 31Y185- TYPE WORK: MAINTENANCE

FUND: STP

'LENGTH (miles / k;") 0 /0.00 DESCRPT: BRIDGE PAINTING IN HENRY-PEACH-TALBOT-TROUP COUNTIES/312185

. LUMP SUM PROJECT

ASSOCIATED PROJECTS: 312185-

PE:'NONE ROW: NONE CST: 2001 FED Share: GA Share:

9/1619! Page 4 of275
$272,000 $217,600 $54,400

PROJECT: 33AOOO- TYPE WORK: RECSTIREHAa

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM ALL SAFETY FUNDS FOR FY 2000 . '

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$20;000 $18,000 $2,000

PROJECT: 33AOOl- TYPE WORK: RECSTIREHAB

FUND: STP

. LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM ALL SAFETY FUNDS FOR FY 2001

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$1,598,000 $1,438,200
$159,800

PROJECT: 33A002- TYPE WORK:' RECSTIREHAB

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM ALL SAFETY FUNDS FOR FY 2002

. PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$1,500,000 $1,350,000
$150,000

PROJECT: 33COOO- TYPE WORK: MAINTENANCE

FUND: STP

. 'PE:NONE

LENGTH (miles / km) 0/0.00

ROW: NONE

DESCRPT: LUMP SUM MAINTENANCE FOR ANY AREA GT 200K FY 2000 .

CST:2000

$8,350,000



FED Share: / GA Share:

$6,680,000 . $1,670,000

PROJECT: 33COOI- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM MAINTENANCE FOR ANY AREA GT 200K FY 2001

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

. $8,350,000 $6,680,000 $1,670,000

PROJECT: 33C002- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM MAINTENANCE FOR ANY AREA GT 200K FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: qA Share:

$7,500,000 $6,000,000 $1,500,000

PROJECT: 330000- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM MAINTENANCE FOR AN AREA FY 2000

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$11,534,000 $9,227,200 $2,306,800

PROJECT: 33DOO 1- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles /km) 0/0.00 .

DESCRPT: LUMP SUM MAINTENANCE FOR AN AREA FY 2001

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$16,500,000 $13,200,000
$3,300,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

ALL COUNTY

PROJECT: 33D002- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles/km) 0/0.00

DESCRPT: LUMP SUM MAINTENANCE FOR AN AREA FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: GA Share:

9/16/99 PageS of27S
$16,500,000 $13,200,000 $3,300,000

PROJECT: 33OBOO- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: LUMP SUM BRIDGE MAINTENANCEIPAINTING FOR FY 2000

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$3,496,000 $2,796,800
$699,200

PROJECT: 33DBOl- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles/km) 0/0.00

DESCRPT: LUMP SUM BRIDGE MAINTENANCElPAINTlNG FOR FY 2001

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

$1,000,000 $800,000 $200,000

PROJECT: 33DB02- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH(miles/km) 0/0.00

DESCRPT: LUMP SUM BRIDGE MAINTENANCElPAINTING FOR FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$4,000,000 $3,200,000
$800,000

PROJECT: 33DMOO- TYPE WORK: PLANNING

FUND: STP

LENGTH (miles / km) . 0/0.00

DESCRPT: LUMP SUM TRANSPORTATION PLANNING & MANAGEMENT SYSTEMS -2000

PE:2000 ROW: NONE CST: NONE

$2,000,000

PROJECT: 33DMOl- TYPE WORK: PLANNING

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: LUMP SUM TRANSPORTATION PLANNING & MANAGEMENT SYSTEMS

PE:2001 ROW: NONE CST: NONE

$2,000,000

PROJECT: 33DM02- TYPE WORK: PLANNING

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: LUMP SUM TRANSPORTATION PLANNING & MANAGEMENT SYSTEMS

PE:2002 ROW: NONE CST: NONE

$2,000,000

PROJECT: 33DWOO- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: LUMP SUM WETLAND MITIGATION SITE PURCHASEIRESTORATION

PROJECT: 33DWOl- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: LUMP SUM WETLAND MITIGATION SITE PURCHASEIRESTORATION

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:
PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$2,000,000 $1,600,000
$400,000
$2,000,000 $1,600,000
$400,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

ALLCOUNIT

PROJECT: 33DW02- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0/0.00

DESCRPT: LUMP SUM WETLAND MITIGATION SITE PURCHASEIRESTORATION

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

911619S Page6of275
$2,000,000 $1,600,000
$400,000

.PROJECT: 33MSOO- TYPE WORK: RAILROAD CROSSING FUND: STP LENGTH (miles/km) 0/0.00
DESCRPT: LUMP SUM RRX PROTECTION DEVICES 33MS FOR FY 2000

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$1,500,000 $1,350,000
$150,000

PROJECT: 33MSOI- TYPE WORK: RAILROAD CROSSING FUND: STP LENGTH (miles / km) 0/0.00
DESCRPT: LUMP SUM RRX PROTECTION DEVICES 33MS FOR FY 200f

PE:NONE ROW: NONE CST: 200 1 FED Share: GAShare:

$2,600,000 $2,340,000
$260,000

PROJECT: 33MS02- TYPE WORK: RAILROAD CROSSING FUND: STP LENGTH (miles / km) 0/0.00
DESCRPT: LUMP SUM RRX PROTECTION DEVICES 33MS FOR FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$2,600,000 $2,340,000
$260,000

. PROJECT: 33NSO()- TYPE WORK: RAILROAD CROSSING FUND: STP . LENGTH(miles/km) 0/0.00
DESCRPT: LUMP SUM RAILROAD CROSSING HAZARD ELIMINATION FY 2000

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$1,600,000 $1,440,000
$160,000

PROJECT: 33NS01- TYPE WORK: RAILROAD CROSSING FUND: STP LENGTH (miles / km) 0 10.00
DESCRPT: LUMP SUM RAILROAD CROSSING HAZARD ELIMINATION FY 2001

. PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$2,600,000 $2,340,000
$260,000

PROJECT: 33NS02- TYPE WORK: RAILROAD CROSSING . FUND: STP LENGTH (miles / km) 0/0.00
DESCRPT: LUMP SUM RAILROAD CROSSING HAZARD ELIMINATION FY 2002

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$2,600,000 $2,340,000
$260,000

PROJECT: -371720- TYPE WORK: MAINTENANCE

FUND: STP

. PE:NONE

,..

LENGTH (miles / km) 0/0.00 DESCRPT: BRIDGE PAINTING IN MUSCOGEE-SUMTER-TALBOT-TAYLOR COUNTIES

ROW: NONE CST: 2001

$210,000

LUMP SUM PROJECT

FED Share:

$168,000

. ASSOCIATED PROJECTS: 37Y720-

GA Share:

$42,000

PROJECT: 37Y720- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km) 0 10.00

DESCRPT: BRIDGE PAINTING IN MUSCOGEE-SuMTER-TALBOT-TAYLOR COUNTIES

, LUMP SUM PROJECT

PE:NONE ROW: NONE . CST: 2001 FED Share: GAShare:

$70,000 $63,000
$7,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 70f275

ALL COUNTY

L

PROJECT: 410715- TYPE WORK: MAINTENANCE

FUND: 1M

PE:NONE

LENGTH (miles / km) 0 /0.00

ROW: NONE

DESCRPT: BRIDGE PAINTING IN COFFEE-COOK-ECHOLS-TIFT COUNTIES/41Y715

CST: 2001

$649,000

LUMP SUM PROJECT

FED Share:

$584,100

ASSOCIATED PROJECTS: 41Y715-

GAShare:

$64,900

PROJECT: 41Y715- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles! km) 0/0.00

DESCRPT: BRIDGE PAINTING IN COFFEE-COOK-ECHOLS-TIFT COUNTIES/410715

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 410715-

PE:NONE ROW: NONE CST:2001 . FED Share: GAShare:

$65,000 $52,000 $13,000

I.~j.
v ~.

PROJECT: 471410- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 0/0.00

PE:NONE ROW: NONE

DESCRPT: BRIDGE PAINTING IN CRISP-DECATUR-DOUGHERTY COUNTIES/47Y41O

CST: 2001

$334,000

I

LUMPSUM PROJECT ASSOCIATED PROJECTS: 47Y410-

FED Share: GAShare:

$267,200 $66,800

I

PROJECT: 471415-

TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 0 /0.00

PE:NONE ROW: NONE

DESCRPT: PAINT BRIDGES IN CLINCHICOFFEIDOUGHTYIGRADYISEMINOLE

CST: 2000

$391,000

I.

LUMP SUM PROJECT

FED Share: GAShare:

$312,800 $78,200

I

PROJECT: 47Y41O-

TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km) 0/0.00

PE:NONE ROW: NONE

DESCRPT: BRIDGE PAINTING IN CRISP-DECATUR-DOUGHERTY COUNTIES/47141O

CST: 2001

$219,000

I

LUMP SUM PROJECT ASSOCIATED PROJECTS: 471410-

FED Share: GAShare:

$197,100 $21,900

PROJECT:511395- TYPE WORK: MAINTENANCE

FUND: 1M

PE:NONE

I

LENGTH (miles / km) 0/0.00 DESCRPT: BRIDGE PAINTING IN APPLING-CHARLTON-CHATHAM-GLYNN COl5IY395

ROW: NONE CST: 2001

$180,000

LUMP SUM PROJECT

FED Share:

$162,000

I

ASSOCIATED PROJECTS: 51Y395-

GA Share:

$18,000 .

PROJECT: 511440- TYPE WORK: MAINTENANCE

FUND:. 1M

PE:NONE

I

LENGTH (miles / km) 0/0.00 DESCRPT: JOINT REHABILITATION PROJECT ON 12 BRIDGES IN DIST 5151 Y440

ROW: NONE CST: 2000

$105,000

LUMPSUM PROJECT

FED Share:

$94,500

ASSOCIATED PROJECTS: 51Y440-

I

PROJECT: 51Y395- TYPE WORK: MAINTENANCE

FUND: STP

GA Share: PE:NONE

$10,500

LENGTH (miles / km) 0 /0.00

ROW: NONE

I

DESCRPT: BRIDGE PAINTING IN APPLING-CHARLTON-CHATHAM-GLYNN COI5l1395

tST:2001

LUMP SUM PROJECT

FED Share:

$101,000 $80,800

ASSOCIATED PROJECTS: 511395-

GA Share:

$20,200

I

PROJECT: SlY440- TYPE WORK: MAINTENANCE

FUND: STP

PE:NONE

LENGTH (miles / km) 0/0.00

ROW: NONE

I

DESCRPT: JOINT REHABILITATION PROJECT ON 12 BRIDGES IN DIST 51511440 LUMP SUM PROJECT

CST: 2000 FED Share:

$75,000 $60,000

. ASSOCIATED PROJECTS: 511440-

GAShare:

$15,000

I

,STATE i'RANSPORTATIONIMPROVEMENTPROGRAM

ALL COUNTY

PROJECT: 571445- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles I km) 0/0.00

DESCRPT: PILE REHAB PROJECT IN GLYNIMONTGITATNLITOOMBIWAYNIWHELERI PE

LUMP SUM PROJECT

PE: 1999' ROW: NONE CST: NONE

911619S Page 8 of275
UNDERWAY

PROJECT: 611285- TYPE WORK: MAINTENANCE

FliND: 1M

PE:NONE

LENGTH (mileslkm)

0/0.00

.

DESCRPT: BRIDGE PAINTING IN BARTOW~CHEROKEE-GORDON COUNTIES/61Y285 .

ROW: NONE CST: 2001

LUMPSUM PROJECT

FED Share: .

" ASSOCIATED PROJECTS: 61Y285-

GA'Share:

PROJECT: 61Y285- TYPE WORK: MAINTENANCE

:, FUND: STP

LENGTH (miies I km) , 0/0.00

. DESCRPT: BRIDGE PAINTING IN BARTOW-CHEROKEE-GORD0N COuNTIES/611285 '

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 611285-

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share: ,

PROJECT: 671190- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles I km) 0/0.00

-DESCRPT: 'BRIDGE PAINT IN CATOOSA-DADE-FANNIN-MURRAY COUNTIES/67YI90

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 67Y190-

PE:NONE ROW: NONE , CST/2001 '
FED Share: GAShare:

PROJECT: 671195- TYPE WORK: MAINTENANCE

' FUND: STP

LENGTH (miles I kin) 0/0.00

,DESCRPT: BRIDGE PAINT IN CARROLL-FLOYD-PAULDING-POLK COUNTIES/67YI95

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 67Y195-

, PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

PROJECT: 67Y190- TYPE WORK: MAINTENANCE

'FUND: 1M

LENGTH (miles / km) 0/0.00
DESCRPT: BRIDGE PAINT IN CATOOSA-DADE-FANNIN-MURRAY COUNTIES/671190 '

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 671190-

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

PROJECT: 67Y195- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km) 0/0.00

'DESCRPT: BRIDGE PAINT IN CARROLL-FLOYD-PAULDING-POLK COuNTIES/671195 ,

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 671195-

-'PE:NONE ROW: NONE CST: 2001 FED Share: 'GAShare:

PROJECT: 821070- TYPE, WORK: SAFETY,

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: ATMSI ROADWAY WEATHER INFORMATION SYSTEM

PE:NONE ROW: NONE CST: 2000 FED Share:' GA Share:

PROJECT: 860110- TYPE WORK: PLANNING

FUND: HPP

PE: 2000

LENGTH (mileslkm) 0/0.00

,ROW:NONE

, DESCRPT: TRANSPORTATION ALTERNATE STUDY-ATLANTA TO CHATIANOOGA(RURAL)' CST:NONE

ASSOCIATED PROJECTS: 86YI10-

$815,.000 $733,500
$81,500
$163,000 $130,400 $32,600
$233,000 $186,400
$46,600
$354,000 $283,200
$70,800
$143,000 $128,700
$14,300
$318,000 $286,200
$31,800
$4,597,000 $3,677,600
$919,400 $6,250,000

II!.,
E I I I I
E
I I I I I I I I I I

STATE TRANSPORTATION IMPROVEMENTPROGRAM

'AlL COUNTY

PROJECT: 870152- TYPE WORK: MAINTENANCE

FUND: BRIDGE

LENGTH (miles I km) 0/0.00 DESCRPT: STATEWIDE BRIDGE INVENTORY & INSPECTION FOR 2001 - PE ONLY

PE:2001 ROW: NONE CST: NONE

9116199 Page 9 of275
$1,800,000

PROJECT: 870153- TYPE WORK: MAINTENANCE

FUND: BRIDGE

LENGTH (mileslkm) 0/0.00

DESCRPT: STATEWIDE BRIDGE INVENTORY & INSPECTION FOR 2002 - PE ONLY

PE:2002 ROW: NONE CST: NONE

$2,000,000

PROJECT: 870331- TYPE WORK: OTHER

FUND: MIN. GUARANTEE PE:2000

LENGTH (miles 1 km) 0 10.00

ROW: NONE

DESCRPT: ENVIRONMENTAL ANALYSIS ON FED-AID PROJECTS BY CONSULTANT

CST: NONE

$2,000,000

PROJECT: 870335- TYPE WORK: OTHER

FUND: MIN. GUARANTEE PE: 1999

LENGTH (mileslkm) 0/0.00

ROW: NONE

DESCRPT: ENVIRONMENTAL ANALYSIS ON FED-AID PROJ ON STP BY CONSULTANT

CST: NONE

UNDERWAY

PROJECT: 870'338- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 0/0.00

DESCRPT: DEVELOP STATE AGENCY WIDE COMMERCIAL VEHICLE PERMIT SYSTEM

PE:2000 ROW: NONE CST: NONE

$1,000,000

PROJECT: 870340- TYPE WORK: SAFETY

FUND: STP

LENGTH (miles 1 km) 0 10.00

DESCRPT: CONSULTANT EVALUATION OF SIGNAL SOFTWARE NEEDS-PE ONLY

PE:2000 ROW: NONE CST: NONE

$300,000

PROJECT: 870345- TYPE WORK: SAFETY

FUND: STP

LENGTH (miles 1 km) 0 10.00

DESCRPT: SIGNAL SOFTWARE PROCUREMENT

PROJECT: 870350- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0 10.00

DESCRPT: ATMS/ CONSULTANT DESIGN OF ITS PROJECTS STATEWIDE- PE ONLY

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:
PE:2000 ROW: NONE CST: NONE

$500,000 $450,000
$50,000
$1,497,000

PROJECT: 870351- TYPE WORK: SIGNING

FUND: STP .

PE: 1999

LENGTH (iniles 1 km) 0 10.00

ROW: NONE

DESCRPT: NON-INTERSTATE LIMITED ACCESS HIGHWAY SIGN UPGRADE STATEWIDE

CST: 2001

FEDShare: .

UNDERWAY.
$4,000,000 $4,000,000

STATE TRANSP(f)RTATION IMPROVEMENT PROGRAM

ALL COUNTY END OFALL'COUNTY

...

9//61991 Page /1 of175

:I

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99
Page 13 of275

APPLING COUNTY

PROJECT: 0000119 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles I km) 0/0.00

ROW: LOCL

DESCRPT: BAXLEY STREETSCAPE AND WELCOME CENTER

CST: 2000

$700,000

J._

FED Share:

$560,000

PROJECT: 522580- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 8/12.88

DESCRPT: SR 27IUS 341 FM CL OF SURRENCY TO W CL OF ODUMI WAYNE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 52258X-

OTH Share:
PE: 1994 ROW: 2002 CST:

$140,000
UNDERWAY $922,000
AFTER 1002

PROJECT: 522590- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 10/16.10

DESCRPT: SR 27IUS 341 FM 4-LN IN BAXLEY TO W CL OF SURRENCY

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1994 ROW: 2002 CST:

UNDERWAY $323,000
AFTER 2002

PROJECT: 532460- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) 2.86/4.60

DESCRPT: SR 15 FM CR 531/MP 16.73 TO CR202/4 171MP 19.59 S OF BAXLEY

EXIST. LANES: 02 PROPOSED LANES: 05

PE:2000 ROW: 2002 CST:

$28,000 $180,000
AFTER~002

PROJECT: 533165- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.24/0.39

DESCRPT: SR 15 @ BIG SATILLA CREEK OIF .21 MI N OF PIERCE CO LN

PE:2000 ROW: 2002 CST:

$20,000 $10,000 AFTER 2002

END OF APPLING COUNTY

: '. \

STATE TRANSPORTATION IMPROVEMENTPROGRAM

ATKINSON COUNTY

PROJECT: 432105- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26/0.42

DESCRPT: SR 135 @ ALAPAHA RIVER OVERFLOW APP 3 MI S OF JCT SR 520

PROJECT: 432106- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

. LENGTH (miles / km) 0.26/0.42

DESCRPT: SR 135 @ALAPAHA RIVER OVERFLOW APP 2 MI S OF JCTSR 520 .

PROJECT: 432107- TYPE WORK: REPLACE BRIDGE

. FUND:' BRIDGE

LENGTH (miles / km) 0.21/0.34

. DESCRPT: SR 135 @ PUDDING CREEK APP 1.5 MI N JCT SR 520

END OFATKINSONCOUNTY

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:
PE:2000 ROW: 2001 CST: 2002 FED Share: . GAShare:
PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

9/16/99 PageUof275
$30,000 $10,000 $1,283,000 $1,026,400 $256,600
$30,000 $10,000 $1,283,000 $1,026,400 $256,600
$20,000 $10,000 $723,000 $578,400 $144,600

.,

STATE TRANSPORTATION IMPROVEMENTPROGRAM

BAKER COUNTY

PROJECT: 431710- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1km) 0.8 1 1.29

DESCRPT: SR 91IPETER ZACK GEER HWY @ ICHA WAYNOCHA WAY CK N OF SR 253

PE: 1997 ROW: 2001 CST:

9116/99 Page 15ofP5
UNDERWAY $35,000
AFTER 2002

I
I:
~.
I)
".
I
I I
I I
I
I I
I
m
mm.1

PROJECT: 442850- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.18 10.29

DESCRPT: CR 124/FAS 1630 @ BIG CYPRESS CREEK APP 12 MI SW OF NEWTON

PE: 1999 ROW: LOCL CST: 2002 FED Share: GAShare:

UNDERWAY
$371,000 $296,800 $74,200

PROJECT: 442860- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.12/0.19

DESCRPT: CR 67/10NES ROAD @ MILL CREEK APP 16 MI NW OF NEWTON

PE: 1999 ROW: LOCL CST: 2002 FED Share: GA Share:

UNDERWAY
, $371,000 $296,800'
$74,200

PROJECT: 471420- TYPE WORK: REPLACE BRIDGE

'FUND: BRIDGE

LENGTH(mileslkm) 0.12/0.19

DESCRPT: CR 121/CLEAR LAKE ROAD @ CHICKASAWHATCHEE CREEK E OF SR 37

PE: 1998 ROW: LOCL CST: 2002 FED Share: GAShare:

, UNDERWAY
$621,000 $496,800 $124,200

END OFBAKER COUNTY

-------------------------------------_._..-

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99

Page 16 0/275

BALDWIN COUNTY

PROJECT: 0000148 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: MILLEDGEVILLE RR DEPOT RESTORATION & LANDSCAPING

. PE:LOCL ROW: LOCL CST: 2000 FEDShare: .

$1,000,000 $800,000

PROJECT: 222280- TYPE WORK: RECSTIREHAB

FUND: HPP

LENGTH (miles / km) 7.5 /12.08

DESCRPT: SR 24/SR 540 FM SOUTH OF CR 186 TO CR 10 IN WASHINGTON CO

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22228X- .

OTHShare:
PE: 1993 ROW: 2000 CST: 2001 FED Share: GAShare:

$200,000
UNDERWAY $1,768,000 . $18,395,000 $14,716,000 $3,679,000

PROJECT: 231450- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 2.2 /3.54

. DESCRPT: SR 49 FM JUST W. OF ALLEN MEMORIAL RD TO MILLEDGEVILLE BYP

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1997 ROW: 2002 CST: .

UNDERWAY' $105,000
AFTER 2002

PROJECT: 232240- TYPE WORK: .IMPROVE INTERSECTION FUND: STP . LENGTH (miles / km) 0.45 / O.72
DESCRPT: SR 22/SR 24 AT LAKE LAUREL RD/CR 472 EAST OF MILLEDGEVILLE LUMPSUM PROJECT

PROJECT: 232260- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: SR 22 @ CS 558 TATINALL STREET IN WEST MILLEDGEVILLE

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:
'PE:2000 ROW: 2002 CST:

UNDERWAY
. $232,000 $208,800 $23,200
$20,000 $10,000 . AFTER 2002

PROJECT: 245405- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles/ km) 0.24 /0.39

DESCRPT: SR 243IUS 441 BUS. @FISHING CREEK SOUTH MILLEDGEVILLE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

. PROJECT: 26247X- TYPE WORK: NEW CONSTRUCTION FUND: STATE LENGTH (miles / km) 0/0.00
DESCRPT: FALL LINE FWY-NEW LOC FM N GORDON BYP TO SR 24/SEE WILKINSON
ASSOCIATED PROJECTS: 262470-

PE:NONE ROW: NONE CST: NONE

PROJECT: 271287- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: BlKElPED TRAIL FM MILLEDGEVILLE TO GC&SU CAMPUS & H.S.

END OF BALDWIN COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$400,000 $320,000
$80,000

s.

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99

Page 17 of275

"

BANKS COUNTY

:i

PROJECT: 0000158 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles I km) 0/0,00

ROW: LOCL

DESCRPT: HOMER-BANKS CROSSING CORRIDOR BEAUTIFICATION & SIDEWALKS

CST: 2000

$600,000

FED Share:

$480,000

OTHShare:

$120,000

PROJECT: 121190- TYPE WORK: NEW CONSTRUCTION FUND: NHS

PE: 1992

UNDERWAY

',

LENGTH (mileslkm) 6.04/9.72 DESCRPT: SR 15IUS 441IHOMER BYP FM NEAR CR 7 NW TO CR 105

ROW: 1990 CST: 2000

UNDERWAY $50,000,000

If:-~I1

EXIST. LANES: 00 PROPOSED LANES: 04

FED Share:

$40,000,000

GA Share:

$10,000,000

i'

PROJECT: 142265- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles I km) 0.2 I 10.34

ROW: 2001

$10,000

I,."'.

, DESCRPT: SR 51 @ GROVE CREEK 7 MI WEST OF HOMER

CST: 2002 FED Share:
GAShare:

$348,000 $278,400
$69,600

f

PROJECT: 142266-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.22/0.35

PE:2000 ROW: 2001

$20,000 $10,000

DESCRPT: SR 105 @ MIDDLE FORK BROAD RIVER 9.6 MI NORTH OF HOMER

CST: 2002

$201,000

I

FED Share: , GAShare:

$160,800 $40,200

I

PROJECT: 171564-

TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 1.5 12.42

PE: 1999 ROW: LOCL

UNDERWAY

DESCRPT: PLANNING DESIGN FOR BlKEIPED FAC./LANDSCAPING CITY OF HOMER

CST: 2000 FED Share:

. $50,000
$40,000

I

OTHShare:

$10,000

I

END OF BANKS COUNTY

I

I

I

I
I
I

STATE TRANSPORTATION IMPROVEMENTPROGRAM

BARROW co-ilNTY
PROJECT: 121730- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles I km) 2.6 14.19
DESCRPT: WINDER BYP FM SR 8 @ SR II NEAR S CL NE TO SR 53 @ SR 11 EXIST. LANES: 00 PROPOSED LANES: 04

PE: 1998 ROW: 2000 CST: 2001 FED Share: GAShare:

9116/99 Page 18 of275
UNDERWAY $2,218,000 $11,222,000 $8,977,600 $2,244,400

PROJECT: 12R870- TYPE WORK:. NEW CONSTRUCTION FUND: NHS LENGTH (miles I km) 0/0.00
DESCRPT: SR 316 IN BARROW AND OCONEE COS-26INTCHG FOR ADDL RW/122870 '
ASSOCIATED PROJECTS: 122870- 122870-

. PE: 1996 ROW: 2002 CST: NONE

UNDERWAY $12,500,000

PROJECT: 132570- TYPE WORK: REPLACE BRIDGE

FUND: .BRIDGE .

LENGTH (miles I km) 0.21 10.34

DESCRPT: SR 53/GAlNESVILLE HWY. @ CEDAR CREEK 2.7 MI NORTH OF WINDER

ASSOCIATED PROJECTS: 132670-

PEt 1995 ROW: 2000 CST: 2000 FED Share: GAShare:

UNDERWAY $83,000
$662,000 $529,600 $132,400

. PROJECT: 132670- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles I km) 0.2 10.32
DESCRPT: SR 53 AT ROCKWELL CHURCH RD/CR 4 NORTH OF WINDER
ASSOCIATED PROJECTS: 132570-

. PEt 1996 ROW: 1997 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$315,000 $252,000 $63,000

PROJECT: 132970- TYPE WORK: REPLACE BRIDGE

FUND: . BRIDGE

. LENGTH (miles Ikm) 0.22/0.35

DESCRPT: .SR lliW'INDER-MONROE HWY. @ MARBURY CREEK SO OF WINDER

. PE:2000 . ROW:
CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 132971- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.22/0.35

DESCRPT: SR lIIWINDER-MONROE HWY. @ SCOTI CREEK SOUTH OF BETHLEHEM

PE:2000 ROW: 2002 CST:

$20,000 $10,000 AfTER 2002

PROJECT: 142130- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles I km) 0.66 11.06
DESCRPT: SR 211 AT ROCKWELL CHURCH RD/CR 4/CEDAR HILL RD/CR 327 LUMPSUM PROJECT

PEt 19~5 ROW: LOCL CST: 2000 FED Share: GAShare:

PROJECT: 142150- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles I km) 0.45/0.72
DESCRPT: SR SlICHARLES FLOYD ROAD AT CR 325lMATTHEWS SCHOOL ROAD LUMP SUM PROJECT

PEt 1998 ROW: LOCL CST: 2001 FED Share: GAShare:

PROJECT: 171415-' TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PEt 1997

LENGTH (mileSI km.) 0.2/0.32

ROW: LOCL

DESCRPT: CR 125IMCELHANNON ROAD OVER APALACHEE RIVER @ WALTON CO LINE

CST: 2000

FED Share:

ASSOCIATED PROJECTS: 17141X-

GA Share:

UNDERWAY
$340,000 $306,000
$34,000
UNDERWAY
$232,000 $20S,800
$23,200
UNDERWAY
$321,000 $256,800
$64,200

STATE TRANSPORTATION IMPROVEMENTPROGRAM

BARROW COUNTY

PRQJECT: 171566- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (mileslkm) 0/0.00

DESCRPT: CITY OF WINDER RAILROAD DEPOT

PE:LOCL ROW: LOCL CST: 2000 FED Share:

9116199 Page 19 of275
$52,000 $41,600

OTH Share:

$10,400

PROJECT: 171600-. TYPE WORK: NEW CONSTRUCTION FUND: NHS

PE:NONE

ATHENS TIP #

LENGTH (miles I km) 0/0.00

ROW: NONE

.<

DESCRPT: COMMUTER RAIL DACULA 'TO ATHENS/CLARKE - PHASE 4

,~

PROPOSED TCM

I

CST: 2002 FED Share:
GAShare:

$5,000,000 $4,000,000 $1,000,000

I

END OFBARROW COUNTY

I
I,

STATE TRANSPORTATION IMPROVEMENTPROGRAM

BARTOW COUNTY

PROJECT: 611290- TYPE WORK: SAFETY

FUND: 1M

.

LENGTH (miles 1 km)

2 13.22

DESCRPT: 1-75 SAFETY UPGRADES@8 LOC FM GLADE TO SRI40ISR3/136/GORDON

ASSOCIATED PROJECTS: 61129X

PE: 1998 . ROW: NONE CST: 2000 FED Share: GAShare:

9116/99 Page 20 0/275
UNDERWAY
$9,669,000 $8,702,100
$966,900

PROJECT: 620832 TYPE WORK: REPLACE BRIDGE

.FUND: BRIDGE

LENGTH (miles 1 km) 0.63/1.01

DESCRPT: SR 61 @ ETOWAH RIVER & APPROACHES

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 621255-

PE: 1994 ROW: 1987 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $4,262,000 $3,409,600
$852,400

PROJECT: 621130- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.3 10.48

DESCRPT: SR 113 BRIDGE & APPROACHES OVER HILLS CREEK

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1988 ROW: 2000 CST: 2000 FED Share: GAShare:

UNDERWAY $50,000
$462,000 $369,600
$92,400

PROJECT: 621250- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 2.4/3.86

DESCRPT: SR61/CARTERSVILLE FM GILMER STTO SR20lINCL I-WAY PAIR

EXIST. LANES: 03 PROPOSED LANES: 05

PE: 1992 ROW: 2002
CST:

UNDERWAY $1,198,000 AFTER 2002

PROJECT: 621255- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 2.61 14.20

DESCRPT: SR 6l1SR 113 FM CR 533 NO TO PLYMOUTH DRICARTERSVILLEIEXC BR

EXIST. LANES: 02,PROPOSED LANES: 04

ASSOCIATED PROJECTS: 620832-

PROJECT: 621350- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 2.47/3.98

DESCRPT: SR 20 FM SR 61 TO 1-75 (INCL INTCH W/SR 61 & US 41)

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 621430- TYPE WORK:RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 4.717.57

DESCRPT: SR 113 FM SffAYLORSVILLE CL NE TO CR 3l1STILESBOROIPOLK

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 62143X- 621435~

PROJECT: 621435- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.16/0.26

DESCRPT: SR 113 @ DRY CREEK

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 621430-

PROJECT: 621710- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 2.9/4.67

DESCRPT: SR 201 EBIMP 19.05-20.75/WB MP 20.75-21.95 INCL 2 BRID CLvi'

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 631510-

PE: 1992 ROW: 1997 CST: 2000 FED Share: GAShare:
PE: 1992 ROW: 2000 CST: 2001 FED Share: GAShare:
PE: 1993 'ROW: 2000
CST:
PE: 1993 ROW: 2000 CST:
PE: 1998 ROW: 2002 CST:

UNDERWAY UNDERWAY
$4,144,000 $3,315,200
$828,800
UNDERWAY $2,533,000 $5,755,000 $4,604,000 $1,151,000
UNDERWAY $2,345,000 AFTER 2002
UNDERWAY $50,000
AFTER 2002 .
UNDERWAY $170,000
AFTER 2002

STATE TRANSPORTATION IMPROVEMENTPROGRAM

BARTOW COUNTY

PROJECT: 621880- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.25/0.40

DESCRPT: SR 20lUS 411 EBL & WBL @ SR 293- CSX RR NW OF CARTERSVILLE

PE: 1996 ROW: NONE CST:2000 FED Share: GAShare:

9/16/99 Page 21 of275
UNDERWAY
$1;472,000 $1,177,600
$294,400 ..

PROJECT: 622150- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.22/0.35
DESCRPT: SR 61 AT OLD ALABAMA RD/CARNES RD/CR 636 LUMPSUM PROJECT

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$266,000 $239,400 $26,600

PROJECT: 62Y135- TYPE WORK: TURN LANES

FUND: NHS

LENGTH (miles 1 km) 0/0.00

DESCRPT: SR 20 FM SR I IN FLOYD TO SR 3 FOR RURAL $ SEE 622135

ASSOCIATED PROJECTS: 622135-

PE:NONE ROW: NONE . CST:2000 FED Share: GAShare:

$4,725,000 $3,780,000
$945,000

PROJECT: 631510- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 20 AT STAMP CREEK 5.8 Ml SE OF WHITE

ASSOCIATED PROJECTS: 621710-

PE: 1996 ROW: 2002 CST:

UNDERWAY $34,000
AFTER 2002

PROJECT: 631515- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 20 @ BOSTON CREEK 6.2 MILES SE OF WHITE

ASSOCIATED PROJECTS: 621710-

PE: 1996 ROJv." 2002 CST:

UNDERWAY . $24,000 AFTER 2002

PROJECT: 632925- TYPE WORK: MAINTENANCE

FUND: STP

- LENGTH (miles 1 km) 0/0.00

DESCRPT: DECK HYDRODEMOLITION ON 2 BRIDGES IN BARTOW COUNTY

LUMPSUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$38,000 $30,400 $7,600

PROJECT: 632935- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 13.6/21.96

DESCRPT: SR 61IUS 411 FM S OF 1-75 OVERPASS TO GORDON COUNTY LINE

LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$1,239,000 $991,200 $247,800

PROJECT: 641870- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles 1 km) 0.26/0.42
DESCRPT: SR 293 @ GRASSDALE RD/CR 155

PE:2000 ROW: LOCL CST: 2002 FED Share: GA Share:

$5,000
$297,000 $237,600 $59,400

PROJECT: 642035- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 2.4/3.86

DESCRPT: SR 140 WB MP 20.5 TO 21.51 EB MP 21.3 TO MP 22.7

EXIST. LANES: 02 PROPOSED LANES: 03

PE:2000 ROW: 2002 CST:

$35,000 $35,000 AFTER 2002

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

BARTOW COUNTY

PROJECT: 642100-

TYPE WORK: REHAB. BRIDGE '~

FUND: STP

"LENGTH(miles/km) 0.45/0.72

DESCRPT: CSX RAILROAD UNDERPASS RELOC AT SR 293 NORTH OF CARTERSVILLE

. PE:2000 ROW: 2002 CST:, :

9/161Y9' Page 22 of275
$200,000 $847,000 AFTER 2002

PROJECT: 671204- TYPE WORK: ENHANCEMENT

FUND: STP

, ,LENGTH (miles / km) 0/0.00

DESCRPT: MULTI-USE TRAIL IN EUHARLEE

, PE:LOCL' ROW: LOCL CST: 2000 FED Share:

$100,000 $80,000

PROJECT: 671206- TYPE WORK: ENHANCEMENT

FUND: STP

, LENGTH(miles/km) 0/0.00

'DESCRPT: RAILROAD DEPOT RENOVATION IN ADAIRSVILLE

OTH Share:
, PE:LOCL' 'ROW: LOCL
CST:2000 ' FED Share:

$20,000
$226,000 $180,800

PROJECT: 671208- TYPE WORK: ENHANCEMENT,

FUND: STP

LENGTH (miles / kin) 0/0.00

DESCRPT: RAILROAD DEPOT RENOVATION IN CARTERSVILLE

OTHShare:
'PE:LOCL" ROW: LOCL , CST: 2000 FED Share:

$45,200
$765,000 $604,350

OTHShare:

PROJECT: 671225- TYPE WORK: REPLACE BRIDGE

"FUND: BRIDGE

LENGTH (miles / km) 0.27 /0.43

DESCRPT: CR 8511HARD1N BRIDGE ROAD @ ETOWAH RIVER NORTH OF EUHARLEE '

, PE:2000' ROW: LOCL CST:

$160,650 $45,000
AFTER 2002

"END OF BARTOW COUNTY

'OTHShare:

$300,000

, ..

I

STATE, TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

Page 23 of275

!

BENHILL COUNTY

"t'

PROJECT: 0000120 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

I

DESCRPT: FITZGERALD DOWNTOWN REVITALIZATION & STREETSCAPE

CST: 2001 FED Share:

$875,000 $700,000

I...~.

OTHShare:

$175,000

I

PROJECT: 471440- TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

I

DESCRPT: STREETSCAPES IN THE CITY OF FITZGERALD

CST: 2000 FED Share:

$625,000 $500,000

I

END OF BENHILL COUNTY

OTHShare:

. $125,000

I,'

I
I. I
I
I I
I'
I I
I.
I'
I

r--------------------------------------------~-

STATE TRANSPORTATION IMPROVEMENTPROGRAM

BERRIEN COUNTY

PROJECT: 0000121 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (ndles I km) 0/0.00

DESCRPT: ALAPAHA WALKING TRAIL

PE:LOCL ROW: LOCL CST: 2001 FED Share:

9/16~9
Page 24 of275
$16,000 $12,800

PROJECT: 0000208 TYPE WORK: IMPROVE INTERSECTION FUND: STP . LENGTH (mileslkm) 0.25/0.40
DESCRPT: SR 76/ADEL ROAD AT DOGWOOD DRIVElCR356 LUMP SUM PROJECT

OTHShare:
PE:2000 ROW: LOCL CST: 2001 FED Share: GAShare:

$3,200 $5,000
. $318,QOO $286,200
$31,800

PROJECT: 432110- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.41/0.66

DESCRPT: SR 135 @ ALAPAHA RIVER @ ATKINSON CO LINE

ASSOCIATED PROJECTS: 43211X-

PE:2oo0 ROW: 2002 CST:

$66,000 $10,000 AFTER 2002

PROJECT: 432111- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (milesI km) 0.23/0.37

DESCRPT: SR 125 @ NEW RIVER BERRIEN-TIFT CO LINE

ASSOCIATED PROJECTS: 43211Z-

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 442920- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.LENGTH (miles I km) 0.23/Q.37

DESCRPT: SR 64/SR 84/SR 168 @ ALAPAHA RIVER OVERFLOW NEAR ATKINSON CO

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:

$20,000 $10;000 $468,000 $374,400 $93,600

PROJECT: 442925- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23/0.37

DESCRPT: SR 168 @ TEN MILE CREEK APP 4.2 MI W O~ JCT SR 11

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:

$20,000 $10,000 $593,000 . $474,400 $118,600

PROJECT: 442930- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.22/0.35

DESCRPT: SR 168 @ FIVE MILE CREEK APP 3 MI E OF JCTSR 135

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:

$20,000 $10,000 $539,000 $431,200 $107,800

PROJECT: 442931- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.24/0.39

DESCRPT: SR37@CATCREEKAPP 1 MlWOFRAYCITY

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

END OF BERRIEN COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

BIBB COUNTY

PROJECT: 0000122 TYPE WORK: ENHANCEMENT

FUND: STP

MACON TIP # MCN-72

LENGTH (miles I km) 0 10.00

DESCRPT: SEC 1021103 OF OCMULGEE HERITAGE GREENWAY TRAILILANDSCAPING

PE:LOCL ROW: LOCL CST: 2000 FED Share:

9116/99 Page 25 of275
$1,000,000 $800,000

PROJECT: 310980- TYPE WORK: RECSTIREHAB

FUND: NHS

MACON TIP # MCN-l1

LENGTH (miles I km) 0.97 /1.56

DESCRPT: 1-16 @ SR 540 INCLI-16 ML BR@SALRRlI STREAM & 1 RIVER

OTHShare:
PE: 1986 ROW: 2001 CST:

$200,000
UNDERWAY $500,000
AFTER 2002

PROJECT: 311000- TYPE WORK: RECSTIREHAB

FUND: NHS

MACON TIP # MCN-IO

, LENGTH (miles I km) 1.8612.99

DESCRPT: 1-16 IN MACON FM SR 11 EAST TO SR 87 INCL BRIDGES EXC MLK

EXIST. LANES: 04 PROPOSED LANES: 06

ASSOCIATED PROJECfS: 311400~

PROJECT: 311005- TYPE WORK: REHAB. BRIDGE

FUND: NHS

MACON TIP # MCN-66

LENGTH (miles I km) 0.2510.40

DESCRPT: 1-16 IN MACON- BRIDGE AT MARTIN LUTHER KING DRIVE

EXIST. LANES: 04 PROPOSED LANES: 06

PROJECT: 311400- TYPE WORK: RECSTIREHAB

FUND: NHS

MACON TIP # MCN-13

LENGTH (miles I km) 1.62/2.61

DESCRPT: 1-75/MACON FROM PIERCE AVElCR 478 EAST TO 1-16

EXIST. LANES: 04 PROPOSED LANES: 06

ASSOCIATED PROJECTS: 311000-

PROJECT: 311410- TYPE WORK: RECSTIREHAB

FUND: NHS

MACON TIP # MCN-9

LENGTH (miles I km) 1.1 11.77

DESCRPT: 1-161175 FM 1-75 @ HARDEMAN AVE TO 1-16 @ SPRING ST

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1986 ROW: 2001 CST:

UNDERWAY $7,000,000 AFTER 2002

PE: 1986 ROW: NONE CST: 2002 FED Share: GA Share:

UNDERWAY
$10,000,000 $8,000,000 $2,000,000

PE: 1992 ROW: 2002 CST:

UNDERWAY $10,000,000 AFTER 2002

PE: 1992 ROW: 2002 CST:

UNDERWAY $3,450,000 AFTER 2002

PROJECT: 311460- TYPE WORK: REHAB. BRIDGE

FUND: 1M

MACON TIP # MCN-l A

LENGTH (miles I km) 0.45 / O.72

DESCRPT: RECONSTRUCT HARTLEY BRIDGE RO/CR 740 BRIDGE & APP OVER 1-75

EXIST. LANES: 02 PROPOSED LANES: 05

PROJECT: 311465- TYPE WORK:' RECSTIREHAB

FUND: 1M

MACONTIP#MCNIB

LENGTH (mileslkm) 1.51/2.43

DESCRPT: RECONSTRUCT HARTLEY BRIDGE ROil7511-475 INTERCHANGE

PROJECT: 311910- TYPE WORK: NEWCONSTRUCTION FUND: NHS

MACON TIP # MCN-15

LENGTH (miles / km) 0.2 10.32

DESCRPT: 1-75 NEW INTERCHANGE AT SARDIS CHURCH RO

PE: 1992 ROW: 2000 CST: 2000 FED Share: GA Share:
PE: 1992 ROW: 2000 CST: 2002 FED Share: GA Share:
PE: 1997 ROW: 2000 CST: 2000 FED Share: GA Share:

UNDERWAY $3,000,000 $6,122,000 $5,509,800 $612,200
UNDERWAY $2,000,000
$18,268,000 $16,441,200
$1,826,800
UNDERWAY' $1,256,000 $6,889,000 $5,511,200 $1,377,800

.-------------------~.'-'~--------------------------

STATE TRANSPORTATION IMPROVEMENTPROGRAM

BIBB COUNTY

PROJECT: 311950- TYPE WORK: RECSTIREHAB

FUND: NHS

MACON TIP # MCN-54

LENGTH (miles / km) 0.5/0.81

DESCRPT: I-475IZEBULON RD INTERCHANGE MODIFICATION {INCL LIGHTING}

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ,ROW: 2002
CST: 2002 FED Share:
GAShare:

9/16/99 Page 26 of275
UNDERWAY $180,000
$3,978,000 $3,1'82,400
$795,600

PROJECT: 311992- TYPE WORK: ENHANCEMENT

FUND: NHS

MACON TIP # MCN-71

LENGTH (miles / km) 0/0.00

DESCRPT: 1-475 FM 1-75 NR HARTLEY BRDGE RD TO 1-75/NOISE BARRIER WALL

PE: 1997 ROW: NONE C,ST:2000 FED Share: GAShare:

UNDERWAY'
$2,900,QOO $2,320,000
$580,000

PROJECT: 312090- TYPE WORK: RECSTIREHAB

FUND: NHS

MACON TIP # MCN-60

LENGTH (miles / km) 2.47/3.98

DESCRPT: 1-75 FM PIERCE AVE/SR 247IUS 41 TO ARKWRIGHT ROAD

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1998 ROW: 2001 CST: '

UNDERWAY $2,000,000 AFTER 2002

PROJECT: 322000- TYPE WORK: RECSTIREHAB

FUND: STP

MACON'TIP # MCN-18

LENGTH (miles /km) 2.29/3.69

DESCRPT: SR 87/RIVERSIDE DRIMACON FM HALL RD TO NORTHSIDE DR

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 322005-

PROJECT: 331870- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

MACON TIP # MCN-47

LENGTH(miles/km) 0.18/0.29

DESCRPT: CR 7421TUCKER ROAD @ ROCKY CREEK 1 MI W OF MACON CIT LMTS

PROJECT: 332230- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-51 '

LENGTH (miles / km) 1.2412.00

DESCRPT: ~R 19 PASSING LANES NB FM MP 19.127 TO MP 20.370

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1992 ROW: 2001 CST:

UNDERWAY $1,000,000 AFTER 2002

PE: 1995 ROW: LOCL CST: 2000 FED Share: :GA Share:
PE:2000 ROW: 2002, CST:

UNDERWAY
$557,000 $445,600 $111,400
$14,000 $137,000 AFTER 2002

PROJECT: 333050- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN~9A

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 87lMACON AT JOE TAMPLIN IND BLVD & 1-16 - PHASEIA

, PE:2002 ROW: LOCt CST:

$5,000 AFTER 2002

PROJECT:. 333055- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN~9B

LENGTH (miles / kin) 1.211.93

DESCRPT: SR 87lMACON FM JOE TAMPLIN EXT TO & ALONG WEAVER RD -PH 1B

PROJECT: 333090- TYPE WORK: IMPROVE INTERSECTION FUND: STP

MACON TIP # MCN-42

' LENGTH (miles / km) 4.25 /6.84

DESCRPT: SR 247IUS 129 FROM HOUSTON CO LINE TO NORTH OF SOFKEE RD

LUMPSUM PROJECT

PE:1999 ROW: LOCL CST: 2001 FED Share: GAShare:
PE: 1999 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$3,274,000 $2,619,200
$654,800

UNDERWAY

$935,000

\

\

$841,500

$93,500

STATE TRANSPORTATION IMPROVEMENT PROGRAM

BIBB COUNTY

PROJECT: 333135- TYPE WORK: TURN LANES

FUND: STP

MACON TIP # MCN-42.

LENGTH (miles 1 km) 0.1 10.16

DESCRPT: SR 11 TURN LANES FM SR 49/BIBB TO CR 19/JONES

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 33313Z-

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

9116/99 Page 27 of275
$787,000
. $708,300 $78,700

PROJECT: 342080- TYPE WORK: SAFETY

FUND: STP

MACON TIP # MCN-36

LENGTH (miles! km) 0.86/1.38

DESCRPT: JEFFERSON'LE FM WALNUT CK-RECREATION & MILLER'LD TO BRISTOL

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOClATED PROJECTS: 35 I095-

PE: 1995 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$2,268,000 $1,814,400
$453,600

PROJECT: 350520- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-22

LENGTH (miles 1 km) 0.6/0.97

DESCRPT: FOREST HILL RD IN MACON FROM FORSYTH ROAD TO WIMBISH ROAD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1984 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$2,510,000 $2,008,000.
$502,000

PROJECT: 350560- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-63

LENGTH (miles 1 km)

DESCRPT: SR 247IUS 41IPIO NONOAVE FM I~75 TO SR 49IUS 129

1.3 /2.09

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1992 ROW: 1987 CST: 2000 FED Share: GAShare:

. UNDERWAY UNDERWAY $3,885,000 $3,108,000
$777,000

PROJECT: 350960- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-40

LENGTH (miles / km) I.3 12.09

DESCRPT: SR 74 FM W OF 1-475 WITRN LNES TO E OF LOG CABIN DRiSR 74 SP

PE: 1994 ROW: 1997 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $4,040,000 $3,232,000
$808,000

PROJECT: 351090- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-24

LENGTH (miles / km) 0.85/1.37

DESCRPT: JEFFERSONVILLE RD FM EMERY HWY/SR 19 TO WALNUT CREEK BRIDGE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOClATED PROJECTS: 342080-

PE: 1996 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$1,535,000 $1,228,000
$307,000

. PROJECT: 351095- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

MACON TIP # MCN-55

LENGTH (mileslkm) 0.22/0.35

DESCRPT: CR 727/JEFFERSONVILLE RD. @ WALNUT CREEK IN NE MACON

EXIST. LANES: 02 PROPOSED LANES: 05

PE: 1996 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$1,235,000 ' $988,000 $247,000

PROJECT: 351100- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-26

LENGTH (miles 1 km) 0.9/1.45

DESCRPT: CR 88ILOG CABIN DR FM SR 74lMERCER UNIV DR TO HOLLINGSWORTH

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOClATED PROJECTS: 351105-

PE: 1995 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$3,682,000 $2,945,600
$736,400

PROJECT: 351105- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

MACON TIP # MCN-56

LENGTH (mileS1 km) 0.22/0.35

DESCRPT: CR 88ILOG CABIN DRIVE @ ROCKY CREEK WEST OF SR 74

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 351100-

PE: 1995 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$1,549,000 $1,239,200
$309,800

--------------------------_._----

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

91/6199

Page 28 of275

BIBB COUNTY

PROJECT: 3511 to- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-30

LENGTH (miles I km) 0.64/1.03

DESCRPT: LOG CABIN DR FM EISENHOWER PKWY TO MERCER UNIV DRi SR 74

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$1,591,000 $1,272,800
$318,200

PROJECT: 351120- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-31

LENGTH (miles I km) 2.04/3.28

DESCRPT: BLOOMFIELD RDILOG CABIN DR FM ROCKY CK RD TO SR 22IEISENHOWE

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: LOCL , CST: 2000 "FED Share: . GA Share:

UNDERWAY
$4,743,000 $3,794,400
$948,600

PROJECT: 351130- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-25

LENGTH (miles I km) 1.8112.91

'DESCRPT: CR 723IFOREST HILL RD FM WIMBISH RD TO NORTHSIDE DRiCR 79

EXIST. LANES: 02 PROPOSED LANES: O~

ASSOCIATED PROJECTS: 351135-

PE: 1995
ROW: toct.
CST: 2002
FED Share:
GA Share:

UNDERWAY
$3,542,000 $2,833,600
$708,400

PROJECT: 351135- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.MACON TIP # MCN-59

LENGTH (miles I km) 0.2/0.32

. DESCRPT: CR 723IFOREST HILL ROAD@ SABBATH CREEK NORTH OF SR 19

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 351130-

PE: 1995 ROW: LOCL CST: 2002 FEDShar.e: GA Share:

UNDERWAY
'$250,000 $200,000 $50,000

PROJECT: 351140- TYPE WORK: RECSTIREHAB

. FUND: STP

PE:1996

MACON TIP # MCN-29

LENGTH (miles 11m) 2.1 13.38

ROW: LOCL

DESCRPT: NW PKWY-NEW LOC FM LOG CABIN TO NAPIER@PARK ST' THEN TO SR 19

CST: 2002

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

GAShare:

UNDERWAY
$7,680,000 $6,144,000 $1,536,000

PROJECT: 351150- TYPE WORK: RECSTIREHAB

FUND: STP

MACON TIP # MCN-27

LENGTH (miles / km) 0.9/1.45

DESCRPT: CR 79INORTHSIDE DR FM WESLEYAN DR TO FOREST HILLRD/CR 723

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: LOCL CST: 2000 FED Share:' GAShare:

UNDERWAY
$2,637,000 $2,109,600
$527,400

PROJECT: 362695- TYPE WORK: NEW'CONSTRUCTION FUND: STATE

MACON TIP # MCN-49

LENGTH (miles / km) 1.7412.80

DESCRPT: SR 5401EISENHOWER PKWY FM 1-16 N TO SR 19IUS 80lEMERY HWY .

ASSOCIATED PROJECTS: 36Y695-

PE: 1986 ROW: 2001 CST: 2002
GAShare:

UNDERWAY $1,008,000
$22,66.2,000
$22,662,000

PROJECT: 363630- . TYPE WORK:' NEW CONSTRUCTION FUND: STATE

MACON TIP # MCN-50

LENGTH (miles / km) 1.9/3.06

to DESCRPT: SR 540IFALL LINE FWY FM LOWERBOUNDARY ST E 1-16

ASSOCIATED PROJECTS: 36Y630-

PE: 1992 ROW: 2001 . CST:,

UNDERWAY $2,174,000 AFTER 2002

PROJECT: 36Y630- TYPE WORK: . NEW CONSTRUCTION FUND: NHS

MACON TIP # MCN-50

LENGTH (miles / km) 0/0.00

DESCRPT: SR 540IFALL LINE FWY FM L. BOUNDARY ST E TO 1-16 -FOR FED PE

ASSOCIATED PROJECTS: 363630-

PE:2000' ROW: NONE CST: NONE

$1,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99 Page 29 0/275

BIBB COUNTY

PROJECT: 36Y695- TYPE WORK: NEW CONSTRUCTION FUND: NHS

MACON TIP # MCN-49

LENGTH (miles / km) 0 /0.00

II
M.i li

DESCRPT: SR 5401EISENHOWER PKWY FM 1-16 N TO SR 19IUS 80 - FOR FED PE

ASSOCIATED PROJECTS: 362695-

PE:2oo0 ROW: NONE CST: NONE

$1,000

PROJECT: 371422- TYPE WORK: SIGNALS

FUND: STP

MACON TIP # MCN-70

LENGTH (miles / km) 0 /0.00

DESCRPT: CONSTRUCTION OF MACON TRAFFIC CONTROL CENTER

PE: 1998 'ROW:LOCL
CST: 2000 FED Share:
GA Share:

UNDERWAY
$450,ODO $360,000
$90,000

PROJECT: 371423- TYPE WORK: SIGNALS

FUND: STP

PE: 1998

MACON TIP # MCN-61

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: MACON URBAN AREA SIGNAL UPGRADES/COMMUNICATIONIITS - PHASE 2

CST: 2000

FED Share:

GAShare:

UNDERWAY
$2,342,000 $1,873,600
$468,400

PROJECT: 371426- TYPE WORK: SIGNALS

FUND: STP

PE: 1998

MACON TIP # MCN-62

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: MACON URBAN AREA SIGNAL UPGRADES/COMMUNICATIONIITS - PHASE 3

CST: 2000

FED Share:

GAShare:

UNDERWAY
$2,170,000 $1,736,000
$434,000

PROJECT: 371774- TYPE WORK: ENHANCEMENT

FUND: STP

MACON TIP # TEA-1 ,

LENGTH (miles / km) 1 /1.61

DESCRPT: OCMULGEE HERiTAGE GREENWAY IN MACON

PE:LOCL ROW: LOCL CST: 2000 FED Share:

PROJECT: DNR252- TYPE WORK: NEW CONSTRUCTION FUND: REC TRAILS

MACON TIP # DNR-1

LENGTH (miles/km) 0/0.00

DESCRPT: DNR RECREATIONAL TRAILS PROG - CENTRAL CITY PARK TRAIL HEAD

OTHShare:
PE:NONE ROW: NONE CST: 2000 FED Share:

OTHShare:

PROJECT: DNR253- TYPE WORK: NEW CONSTRUCTION FUND: REC TRAILS

MACON TIP # DNR-2

LENGTH (miles / km) 0/0.00

DESCRPT: DNR REC TRAILS PROG - PIERCE AVENUE WATER WORKS TRAIL HEAD

PE:NONE ROW: NONE CST: 2000 FED Share:

END OF BIBB COUNTY

OTHShare:

$1,000,000 $800,000 $200,000
$125,000 $100,000
$25,000
$125,000 $100,000 $25,000

~~.'

--------------------------,-,_._..=------------,---

STATE TRANSPORTATION IMPROVEMENT PROGRAM .

9116/99

Page 30 of275

BLECKLEY COUNTY

PROJECT: 0000123 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0/0.00

DESCRPT: COCHRAN STREETSCAPE

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$55,000 $44,000

PROJECT: 21094X- TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles I km) 0/0.00

DESCRPT: I-16.@ SR SR 26/338/257/19 & SR 112IBLECKLEY -SEE LAURENS

OTH Share:
PE:NONE ROW: NONE CST: NONE

$11,000

ASSOCIATED PROJECTS: 210940-

PROJECT: 222360- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 2.514.03

DESCRPT: SR 87 FM NORTH OF SR 257 NW TO THE COCHRAN BYPASS

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: 2000 CST: 2000
GA Share:

UNDERWAY $1,867,000 $5,296,000
$5,296,000

PROJECT: 245336- TYPE WORK: REPLACE BRIDGE.

FUND: BRIDGE

,i .

LENGTH(mileslkm) 0.24/0.39

DESCRPT:SR 126 @ GUM SWAMP CREEK 5.8 MI E OF COCHRAN

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

END OF BLECKLEY COUNTY I

J

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page 31 of275

BRANTLEY COUNTY

PROJECT: 533155- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles / km) 0.25/0.40

ROW: 2002

$10,000

I

DESCRPT: SR 321HARRELL HIGHWAY @ BARBERS CREEK 2 MI E OF HORTENSE

CST: 2002 FED Share:

$794,000 $635,200

GA Share:

$158,800

I'

PROJECT: 533156- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles / km) 0.21 /0.34

ROW: 2002

$10,000

I

DESCRPT: SR 32/HARRELL HIGHWAY @ MILL BRANCH 4 MI E OF HORTENSE

CST:

AFTER 4002

I

PROJECT: 533157- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$21,000

LENGTH(miles / km) 0.24/0.39

ROW: 2002

$10,000

DESCRPT: SR 321HARRELL HIGHWAY @ BROWNTOWN swAMP 9 MI E OF HORTENSE

CST: 2002

$901,000

I

FED Share: GAShare:

$720,800 $180,200

I

PROJECT: 533158-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

PE:2001 ROW:

$20,000 AFTER 2002

DESCRPT: SR 15 @ DIX BRANCH IN CITY LIMITS OF HOBOKEN

CST:

AFTER 2002

I

I

PROJECT: 533159-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.29/0.47

PE:2000 ROW:

$34,000 AFTER 2002

DESCRPT: SR 23IUS 301 @BUFFALO CREEK 2 MI S OF HORTENSE

CST:

AFTER 2002

I

END OF BRANTLEY COUNTY
I

I

E
I I
D
I

m

STATE TRANSPORTATION IMPROVEMENTPROGRAM

li"koo'Ks COUNTY

PROJECT: 0000079 TYPE WORK: ENHANCEMENT

.FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: DOWNTOWN QUITMAN BEAUTIFICATION & PED SAFETY PLAN

PROJECT: 431900- TYPE WORK: REPLACE BRIDGE'

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: CR 305 @ NEGRO BRANCH APPROX 2 MILES WEST OF QUITMAN .

PE:LOCL ROW: LOCL CST: 2001 FED Share:
OTH Share:
PE: 1997 ROW:LOCL CST: 2002 FED Share: GA Share:

9/16199 Page 32 of275
$223,000 $178,400 $44,600 UNDERWAY $464,QOO $371,200 $92,800

PROJECT: 432150- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.4/0.64

DESCRPT: SR 122 @ LITTLE RIVER BROOKS-LOWNDES'CO LINE

ASSOCIATED PROJECTS: 43215X-

PE:2000 . ROW: CST:

$97,000 AFTER 2002 AFTER 2002

END OF BROOKS COUNTY .

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199
Page 33 of275

BRYAN COUNTY

PROJECT: 511022- TYPE WORK: NEW CONSTRUCTION FUND: NHS LENGTH (miles / km) 0.2 /0.32
DESCRPT: 1-95 NOISE WALL JUST SOUTH OF SR 25IUS 17 INTERCHANGE

PE: 1992 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$601,000 $480,800 $120,200

i~iI.:

PROJECT: 511325- TYPE WORK: NEW CONSTRUCTION FUND: 1M

PE: 1997

UNDERWAY

LENGTH (miles / km) 8.3 /13.36

ROW: NONE

I'

DESCRPT: 1-95 FOG DETECTION SYS IN BRYAN-CHATHAM-EFFINGHAMl511325IXIZ

CST: 2000 FED Share:

$1,500,000 $1,350,000

ASSOCIATED PROJECTS: 51132X-

GA Share:

$150,000

I

PROJECT: 532370- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1.5 /2:42

I:! .;

DESCRPT: SR 144 EB FM S OF CR 244/ML 14 TO N OF CR 154/ML 15.5 EXIST. LANES: 02 PROPOSED LANES: 03

PE:2000 ROW: CST:

$15,000 AFTER 2002 AFTER 2002

I

END OFBRYANCOUNTY

I

I

I

I

I

I

I

I

I

I

~

~---------------------------------------~--~~~~- -

STATE TRANSPORTATION1MPROVEMENT PROGRAM

BULLOCH COUNTY

PROJECT: 521270- TYPE WORK: RECSTIREHAB

FUND: STP ~".

. LENGTH (miles'l km) 1.412.25

DESCRPT: SR 67 FM JUST S OF CR 248/585 NORTH TO 5-LN SECTION

EXIST. LANES: 02 PROPOSED LANES: 05

PE:]992' ROW: ]997 CST: 2000 FED Share: GAShare:

9116l9S Page 34 of275
UNDERWAY UNDERWAY $2,980,000
$2,384,000 $596,000

PROJECT: 522460- TYPE WORK: RECSTIREHAB

',FUND: STP',

LENGTH(tniles / km) 10.9/17.48

.DESCRPT: SR 67 FM 1-16 TO STATESBORO BYP

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2002 ROW: CST:

$372,000 AFTER 2002 AFTER 2002

PROJECT: 522465- TYPE WORK: ' REHAB. BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.12/0.19

DESCRPT: SR 67 @ WOODCOCK BRANCH & ZETTEROWER BRANCH .

PROJECT: 522640- . TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 6.85 1 I ] .03

DESCRPT: E. STATESBORO BYP FM SR 73IUS 25 TO SR 73IUS 301

EXIST. LANES: 02 PROPOSED LANES: 04

PE: ]992: ROW: 2000 CST: 206] FED Share: GAShare:
PE: ]997 ROW: 200] CST:.

UNDERWAY $10,000
$2,405,000 $],924,000
$481,000
UNDERWAY $460,000
AFTER 2002

PROJECT: 522650- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 4.917.89

DESCRPT: W.BYPASS/SR 67IUS 25 FM SR 73IUS 25 NW TO SR 26IUS 80

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 523250- TYPE WORK: TURN LANES

FUND: STP

LENGTH (miles / km) 0.2 10.32

DESCRPT: SR 26 TURN LANESFM SR 67 TO ZETTEROWER RD

PROJECT: 542040- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2 10.32

DESCRPT: CR 927 @ MANN BRANCH 9 MI S OF BROOKLET

PROJECT: 542380- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.27 10.43

DESCRPT: SR 46 @ LOTTS CREEK 1.8 MI E OF REGISTER

PE: ]995 ROW: 200] CST: 2002
GA Share:

UNDERWAY $50,000
$3,000,000
$3,000,000

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$1,819,000 $],455,200
$363,800 .

PE: ]998 ROW: LOCL CST: 2000 FED Share: GA Share:

. UNDERWAY
$598,000 $478,400 . $119,600

PE:2000 ROW: 2002 CST:

$34,000 $10,000 AFTER 2002

PROJECT: 550500- TYPE WORK: RECSTIREHAB

FUND: STP .

LENGTH (miles / km) 1.47/2.37

DESCRPT: BRANNEN ST/CS 802 FM GENTILLY Ro/CS 673 TO SR 26 -STATESBORO

EXIST. LANES: 02 PROPOSED LANES: 05

PE: ]992 ROW: LOCL CST: 2000 FED Share: .GA Share:

UNDERWAY
$],029,000 $823,200 $205,800

STATE TRANSPORTATION IMPROVEMENT PROGRAM
1iVLLOCH COUNty-~"' END OF BULLOCH COUNTY

9/16/99 Page 35 of275

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199

Page 36 of275

"BU;R'KE:C'O;UN~T~Y ~~'l:'m~-------------------------------

PROJECT: 222100- TYPE WORK: RECSTIREHAB

FUND: STATE

PE: 1993

UNDERWAY

LENGTH (miles / km) 5.9/9.50

ROW: 2000

$1,210,000

DESCRPT: SR 121IUS25FMWAYNESBOROBYPASS@CR451 TOCR438

CST: 2001

$12,874,000

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22YI0o-

GAShare:

$12,874,000

PROJECT: 222110- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 10/16.10

DESCRPT: SR 121IUS 25 FM CR 438IBURKE CO TO SR 88 IN RICHMOND CO

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22211X- 22YII0-

PE: 1993 ROW: CST:

UNDERWAY AFTER 2002 AFTER.2002

PROJECT: 22255X- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 0/0.00

DESCRPT: SR 121IUS 25/SAVN RVR PKWY FM CR 16 TO CR 118/JENKINS-222550

ASSOCIATED PROJECTS: 222550-

PE:NONE ROW: NONE CST: NONE

PROJECT: 22YI00- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 121IUS25 FM BYP @CR451 TO CR 438 FOR FED PE; 222100

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222100-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 22YI10- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 121IUS 25 FM CR 438 TO SR 88/RlCHMOND- FOR FED PE;22211O

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222110-

'PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 22Y480- TYPE WORK: RECSTIREHAB

. FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 121IUS 25 SAV.RVR PKY CR 118/354 TO SR 24 @BYP-FOR FED PE

EXIST. LANES: 02 PROPOSED LANES: 04 .

ASSOCIATED PROJECTS: 222480-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 231260- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 5.4 /8.69

DESCRPT: SR 24 WB MP 22-23.3/EB24.3-25.6/WB 29-30.3&37-1.1/JEFFERSON

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 23126X-

PE: 1997 ROW: 2002 CST:

UNDERWAY $100,000
. AFTER 2002

END OF BURKE COUNTY

--_.._._-_._------.-------~ -----------------------

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99

Page 37of275

BUTrs COUNTY

PROJECT: 0000149 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0/0.00

DESCRPT: INDIAN SPRINGSHOTEL PHASE 2

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$313,000 $250,400

'jf

..t1
,\'

PROJECT: 332360- TYPE WORK: RECSTIREHAB

FUND: STP

OTH Share: PE: 1999

$62,600 UNDERWAY

LENGTH (mileslkm) 3.74/6.02

ROW: 2002

$149,000

DESCRPT: SR 421US 23 PPL @ MPI0.60-11.881 MPl1.88-13.351 MP 14.95-.74

CST:

AFTER 2002

EXIST. LANES: 02 PROPOSEDLANES: 03

.

ASSOCIATED PROJECTS:33236X-

PROJECT: 332510- TYPE WORK: REPLACE BRIDGE

FUND: STP

LENGTH (mileslkm) 0.9/1.45

DESCRPT: SR 16 OVER OCMULGEE RIVER ATJASPER CL(M.L.17.45)

PE: 1997 ROW: 2001 CST:

UNDERWAY $89,000
AFTER 2002

PROJECT: 333170- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23/0.37

DESCRPT: SR 36 @ TOWALIGA RIVER 7.5 MI SW OF JACKSON

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 333171- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.21 10.34

DESCRPT: SR 36 @ YELLOWWATERCREEK 1 MI N OF JCT SR 42

PE:2001 ROW: (ST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 333172- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.28 10.45

DESCRPT: S.R 36 @ SOUTH RIVER AT BUTTS-NEWTON CO LINE

ASSOCIATED PROJECTS: 33317X-

END OFBUTTS COUNTY

PE:2001 ROW: CST:

$34,000 AFTER 2002 AFTER 2002

mt
I,,)
.~

_ ---,----""-~_. ._---------._------

STATETRANSPORTATION IMPROVEMENT PROGRAM

911619S

Page 38 of275

CALHOUN Co'UNTY

PROJECT: 0000080

TYPE WORK: ENHANCEMENT

FUND: STP

, ',

LENGTH (miles I km) 0/0.00

DESCRPT: ARLINGTON RR DEPOT REHAB

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$104,000 $83,200

PROJECT: 431650- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.21 10.34

DESCRPT: SR 37 @ KEEL CREEK 3 MI S O~ LEARY

OTHShare:
PE: 1996 ROW: 1999 CST: 2000 FED Share: GAShare:

$20,800
UNDERWAY UNDERWAY
$483,000 $386,400
$96,600

PROJECT: 442950- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

, LENGTH (miles I km) 0.22/0.35

DESCRPT: SR 216 @ LITTLE PACHITLA CREEK 1 MI N OF EDISON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 4lf2951 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.27 10.43 DESCRPT: SR 234@CHICKASAWHATCHEECREEK 8MI NEOF LEARY~:

PE:2000 ROW: CST:

$31,000 AFTER 2002 AFTER 2002

PROJECT: 471425- TYPE WORK: ENHANCEMENT

FUND: STP

.LENGTH (miles I km) 0 10.00

DESCRPT: STREETSCAPES IN THE CITY OF EDISON

END OF CALHOUN COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTH Share:

$403,000 $322,400
$80,600

~.
I
I I I I I I'
I'
I
E
I I I
~
I I
B
D
I

STATE TRANSPORTATION IMPROVEMENTPROGRAM

CAMDEN COUNTY

PROJECT: 0000067 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: KINGSLAND STREETSCAPE PHASE II

PE:LOCL ROW: LOCL CST: 2001 FED Share:

9/16199 Page 39 of275
$250,000 $200,000

PROJECT: 0000068 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: COASTAL HWY 17 SCENIC BYWAY FEASIBILITY STUDY IN 9 COUNTIES

OTH Share: .
PE:2000 ROW: LOCL CST: NONE

$50,000 $125,000

. PROJECT: 0000069 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: WOODBINE WALKWAY AND RIVERWALK PHASE 2

PE:LOCL ROW: LOCL CST: 2001 FED Share:

.PROJECT: 0000070 TYPE WORK: . ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: ST. MARYS HISTORIC WATERFRONT PROJECT PHASE 1

OTH Share:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

OTHShare:

PROJECT: 51141X- TYPE WORK: MAINTENANCE

FUND: OTHER

LENGTH (miles / km) 0/0.00

DESCRPT: SAVANNAH & KINGSLAND WELCOME CNTRS ON 1-95/BATHROOMS/CHATHAM

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 511410-

PE:NONE ROW: NONE CST: 2000

PROJECT: 511430-

TYPE WORK: NEW CONSTRUCTION

FUND: NHS

LENGTH (miles / km) 0.5 /0.81

DESCRPT: 1-95 NEW INTERCHANGE AT HORSE STAMP CHURCH ROADICR 138

PE:2000 ROW: LOCL CST:

. $250,000 $200,000 $50,000
$625,000 $500,000 $125,000
$0
..
$5,000 . AFTER 2002 .

PROJECT: 521910- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 3.3 /5.31

DESCRPT: SR 40 FM KINGS BAY RD SE TO SR 40 SPUR AND SIDEWALKS

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 522690- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles/km) 0.1/0.16

DESCRPT: SR 25IUS 17 BRIDGE OVER ST. MARY'S RIVER IFI.A STATE LINE

PROJECT: 570810- TYPE WORK: REPLACE BRIDGE

FUND: HPP

LENGTH (miles / km) . 2.09/3.36

DESCRPT: CR 75INORTH RIVER CAUSEWAY AT NORTH RIVER

PE: 1993 ROW: 1998 CST: 2000 FED Share: GA Share: OTHShare:
PE: 1993 ROW: 2000 CST: 2002 FED Share: GAShare: OTHShare:
PE: 1998 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$6,791,000 $5,432,800
$358,200 $1,000,000
UNDERWAY $5,000
$3,050,000 $1,220,000
$305,000 $1,525,000
UNDERWAY
$2,719,000 $2,175,200
$543,800

..,-- --y-~ ,., - - *

_._-----------------

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page40of275

CAMDEN co""lJNTy

PROJECT: 571431- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00
DESCRPT: WETLAND MITIGATION SITE NE.A.R, WOODBINE WEST OF SR i lO@SATILLA

PE:NONE ROW: 2000 CST: NONE

$700,000

END OF CAMDEN COUNTY

--------------------_.- -

.._-----

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 41 of275

CANDLER COUNTY

PROJECT: 0000071

TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (mileslkm) 0/0.00

DESCRPT: SIDEWALKSIBIKE LANES TO LINK COMMUNITY SERVICES IN METTER

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$250,000 $200,000

PROJECT: 542400-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.28 10.45

DESCRPT: SR 46 @ FIFTEEN MILE CREEK 2.8 MI E OF METTER

OTHShare:
PE:2000 ROW: CST:

$50,000
$44,000 AFTER 2002 AFTER 2002

PROJECT: 542401- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.31 10.50

DESCRPT: SR 129 @ CANOOCHEE RIVER 4 MI S OF METTER

PE:2000 ROW: CST:

$60,000 AFTER 2002 AFTER 2002

PROJECT: 542402- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.22/0.35

DESCRPT: SR 129 @ CANOOCHEE RIVER OIF 4 MI S OF METTER

PE:2000 ROW: CST:

$20,000. AFTER 2002 AFTER 2002

END OF CANDLER COUNTY

I I I I I

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 42 0/275

CARR'OLL COUNTY

PROJECT: 0000110 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

".

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: DOWNTOWN CARROLLTON STREETS CAPE

CST: 2001

$1,250,000

FED Share:

$1,000,000

PROJECT: 621990- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR llUS 27 AT SR 166 IN CARROLLTON

OTHShare:
PE:2000 ROW: NONE CST:

$250,000 $25,000
AFTER 2002

PROJECT: 631300- TYPE WORK: RECSTIREHAB

FUND: STP .

LENGTH (miles / km) 4.517.25

DESCRPT: SR 166 FM CR 828/141 TO 4-LN/CARROLLTON..INCL BRIDGES

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 . ROW: 2002 CST:

UNDERWAY $6,728,000 AFTER 2002

PROJECT: 631320- TYPE WORK: RECSTIREHAB

FUND: STP

. LENGTH (miles / km) 1.65 12.66

DESCRPT: SR I6IUS 27ALT FM SR 166 SE TO W OF STRIPLING CHAP Rb/CR 24

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 2000 CST:

UNDERWAY $1,761,000 AFTER 2002

PROJECT: 631490- TYPE WORK: NEW CONSTRUCTION . FUND: STP LENGTH (miles / km) 1.412.25
DESCRPT: VILLA RICA BYP EXTEND W.FM PROPOSED SR 61 BYPASS TO SR 101 EXIST. LANES: 00 PROPOSED LANES: 02 ASSOCIATED PROJECTS: 662540-
PROJECT: 632865- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.86/1.38
DESCRPT: SR 61 AT SANDHILL-HICKORY LEVEL RD/CR 394 & OLD SR 61/CR 945 LUMP SUM PROJECT

PROJECT: 641890- TYPE WORK: . RECSTIREHAB

FUND: STP

LENGTH (miles / km) 3.5 /5.64

DESCRPT: N CARROLLTON BYP/TEMP SR 977 FM SR 1 TO SR 166

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 641910- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 4.05 /6.52

DESCRPT: SR 100 NB MP 5.5-6.81 NB MP 13.3-14.551 SB MP 15.3-16.8 .

EXIST. LANES: 02 PROPOSED LANES: 03

PE:2001 ROW: CST:

$37,000 AFTER 2002 AFTER 2002

PE: 1999 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$306,000 $275,400
$30,600

PE: 1992 ROW: 1997 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY . $8,979,000 $7,183,200 $1,795,800

PE: 1993 ROW: 2000 CST:

UNDERWAY $70,000
AFTER 2002

PROJECT: 642080- TYPE WORK: REPLACE BRIbGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: CR 834/SMITHFIELD ROAD @ INDIAN CREEK 4 MI NORTH OF BOWDON

ASSOCIATED PROJECTS: 642085-

PE: 1995 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$375,000 $300,000 $75,000

I

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199

Page 43 of275

If I

CARROLL COUNTY

PROJECT: 642085- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1995

UNDERWAY

LENGTH (miles / km) 0.21 /0.34

ROW: LOCL

II.'

DESCRPT: CR 834/SMITHFIELD ROAD @ TURKEY CREEK 3.5 MI NORTH OF BOWDON

CST: 2000

FED Share:

$794,000 $635,200

I,

ASSOCIATED PROJECTS: 642080-

GA Share:

$158,800

PROJECT: 642090- TYPE WORK: REPLACE BRIDGE

FUND:. BRIDGE

PE: 1995

UNDERWAY

LENGTH (miles / km) 0.21 /0.34

ROW: LOCL

I'

DESCRPT: CR 523/JONES MILL ROAD @ SNAKE CREEK 1.5 MI N OF WHITESBURG

CST: 2000 FED Share:

$702,000 $561,600

GA Share:

$140,400

I

PROJECT: 642310- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1999

UNDERWAY

LENGTH (miles / km) 0.3 /0.48

ROW: LOCL

I

DESCRPT: CR 829/CLEM-LOWELL RD @ WHOOPING CREEK SOUTH OF CARROLLTON

CST: 2002

FED Share:

GAShare:

$492,000 $393,600
$98,400

I

PROJECT: 64242X-

TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles / km) 0 /0.00

PE:NONE ROW: NONE

DESCRPT: SR 997 FM PLEASANT RDG@HUTCHESON TO SR 8@CASHTOWN"R/HARALSON CST: NONE "

I

EXIST. LANES: 00 PROPOSED LANES: 02 ASSOCIATED PROJECTS: 642420-

I

PROJECT: 650620-

TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 1.1 /1.77

PE:2001 ROW: 2002

$30,000 $55,000

DESCRPT: SR 16/CARROLL TON FM COLUMBIA RD TO SR 1 DRAINAGE IMPROVMENTS

CST:

AFTER 2002

I

PROJECT: 662540- TYPE WORK: NEW CONSTRUCTION FUND: OTHER

PE:2001

$20,000

B

LENGTH (miles / km) 1 /1.61 DESCRPT: SR 61 CONN FM N OF NS RR BRIDGE @ DOUGLAS CL TO SR 61

ROW: CST:

AFTER 2002 AFTER 2002

EXIST. LANES: 00 PROPOSED LANES: 02

I

ASSOCIATED PROJECTS: 631490-

PROJECT: 811064- TYPE WORK: RECSTIREHAB

FUND: 1M

PE: 1995

UNDERWAY

I

LENGTH (miles / km) 0 /0.00 DESCRPT: UPGRADE 1-20 WB & EB WEIGH STATIONS INCL SCALE REPL &DOUGLAS

ROW: 2000 CST: 2000

$100,000 $4,900,000

FED Share:

$4,410,000

I

ASSOCIATED PROJECTS: 81Y064-

END OF CARROLL COUNTY

GA Share:

$490,000

I

I

I

~

. STATE TRANSPORTATION IMPROVEMENTPROGRAM

(:ATOOSA COUNTY

PROJECT: 610730- TYPE WORK: RECSTIREHAB

FUND: 1M

CHATTANOOGA TMA TIP # IM-97-5 DESCRPT: 1-75 @ SR 3IUS 41

LENGTH (niiles / km) 0.95 /1.53

.:EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 . ROW: 1998 CST: 2000 FED Share: GAShare:

9/16/99 Page 44 of275
UNDERWAY UNDERWAY $6,337,000 $5,703,300
$633,700

PROJECT: 611210- TYPE WORK: RECSTIREHAB

FUND: NHS'

CHATTANOOGATMA TIP#GA-OI

LENGTH (miles/km) 0.59/0.95

DESCRPT: 1-75 AT SR I46/CLOUD SPRINGS ROAD

PE:2000 ROW: 2001 CST:

$34,000 $5,000,000 AFTER.2002

PROJECT: 621530- TYPE WORK: RECSTIREHAB

FUND: STP

CHATTANOOGA TMA TIP # STP-98-2

LENGTH (miles/km) 2/3.22

DESCRPT: SR 151 FM RELOC HACKETTRD/CR 179 TO US 41 @RlNGGOLD-62Y530

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 62Y530-

PROJECT: 62Y530- TYPE WORK: RECSTIREHAB

FUND: 1M

CHATTANOOGA TMA TIP # STP-98-11

LENGTH (iniles/km) 0/0.00

DESCRPT: SR 151 FM RELOC CR 179 TO US-4IISHOW IM$ FOR RAMPS/621530

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 621530-

PROJECT: 631520- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

CHATTANOOGA TMA TIP # BHF-99-3 .

LENGTH (miles / km) 0.23 /0.37

DESCRPT: SR 2 AT TIGER CREEK 2.4 MI EAST OF RINGGOLD

PROJECT: 631600- TYPE WORK: TURN LANES

FUND:' STP

CHATTANOOGA TMA TIP # STP-180-1 (7) .

. LENGTH (miles / km) 0.92 /1.48

DESCRPT: SR 151 FROM CR 382 TO SR 2/US 41 IN RINGOLD AND SIGNALS

PROJECT: 632885- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH/miles / km) 0.24 10.39

DESCRPT: SR 3IUS 41 @ TIGER CREEK 1.9 MI EAST OF RINGGOLD

PE: 1992 ROW: 2002 CST:

UNDERWAY $1,576,000 AFTER 2002

PE:NONE ROW: 2002 . CST:

$1,237,000 . AFTER2002

PE: 1996 ROW: 1999 CST: 2000 FED Share: GA Share:
PE: 1995 ROW: 1999 CST:2000 FED Share: GAShare:
PE:2000~
ROW: 2002 CST:

UNDERWAY UNDERWAY
$568,000 $454,400 $113,600
UNDERWAY UNDERWAY
$342,000 $273,600
$68,400
$20,000 $10,000 AFTER 2002

PROJECT: 632895- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (miles / km) 0.24 /0.39

DESCRPT: SR 3IUS 41 @ TIGER CREEK 1.9 MI EAST OF RINGGOLD

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 642210- TYPE WORK: RECSTIREHAB

FUND: STP

CHATTANOOGA TMA TIP # STP-98(3)

LENGTH (miles / km) 0.59 /0.95

DESCRPT: SR 146/CLOUD SPGS RD FM 1-75 NORTH TO SR 3IUS 41

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: 2001 CST:

$34,000 $314,000 AFTER 2002.

--------------_._.. -,-----------------------

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 .

Page 450f275

CATOOSA COUNTY

PROJECT: 642220- TYPE WORK: RECSTIREHAB

FUND: STP

r

CHATIANOOGA TMA TIP # STP-98(4)

LENGTH (mUeslkm) 2.213.54

DESCRPT: SR 146 FM SR 1IUS 27 EASTWARD TO LAKEVIEW RD/CR 553

t.

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: 2001 CST:

$137,000 $1,256,000 . AFTER2002

PROJECT: 642230- TYPE WORK: RECSTIREHAB

FUND: STP

CHATIANOOGATMA TIP # STP-98(5)

LENGTH (miles Ikm) 3.09/4.97

DESCRPT: CR'S 381-245 & 244 FM SR 3IUS 41 NORTHWARD TO TENN STATE LIN

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2001 . ROW: LOCL CST:

$48,000 AFTER 2002

PROJECT: 642240- TYPE WORK: RECSTIREHAB

FUND: STP

CHATIANOOGATMA TIP # STP-98(6)

LENGTH (mileslkm) 5.75/9.26

DESCRPT: SR 3IUS 41 FM SR 151 NORTHWESTLY TO SR 146

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 631505-

PROJECT: 650440- TYPE WORK: RECSTIREHAB

FUND: STP

CHATIANOOGA TMA TIP # STP-99-2

LENGTH (mileslkm) 2.34/3.77

DESCRPT: SR 146/CLOUD SPGS RD FM LAKEVIEW DR TO 1-75 & BRIDGE &65Y440

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECTS: 65Y440-

PROJECT: 650520- TYPE WORK: RECSTIREHAB

FUND: STP

CHATIANOOGA TMA TIP # STP-98(7)

LENGTH(mileslkm) 2.3/3.70

DESCRPT: DIETZ ROADICR 384 FM SR 146 TO POST ROADICR 382

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: CST:

$159,000 AFTER 2002 AFTER 2002

PE: 1992 ROW: 2000 CST: 2001 FED Share: GAShare:
PE:2000 ROW: LOCL CST:

UNDERWAY. $3,074,000 $8,313,000 $6,650,400 $1,662,600
$325,000
AFTER 2002

PROJECT: 65Y440- TYPE WORK: RECSTIREHAB

FUND: STP

CHATIANOOGA TMA TIP # STP~98-2

LENGTH(mileslkm) 0/0.00

DESCRPT: SR 146/CLOUD SPGS RD FM LAKEVIEW DR TO 1-751FOR Q23 $1650440

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECTS: 650440-

PROJECT: 670710- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

CHATIANOOGA TMA TIP # BRZ-98-1

LENGTH(mileslkm) 0.14/0.23

DESCRPT: CR 259 SOUTH OF RINGGOLD @ LITTLE CHICKAMAUGACRK

PROJECT: 671218- TYPE WORK: ENHANCEMENT

. FUND: STP

CHATIANOOGA TMA TIP #

LENGTH(mileslkm) 0/0.00

DESCRPT: STREETSCAPES & SIDEWALKS IN THE CITY OF FORT OGLETHORPE

END OF CATOOSA COUNTY

PE:NONE ROW: 2000 CST: NONE

$1,075,000

PE: 1995 ROW: LOCL CST: 2000 FED Share: GAShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

UNDERWAY $1,447,000 $1,157,600
$289,400
$750,000 $600,000 $150,000

CHARLTON COUNTY

- PROJECT: 0000124 TYPE WORK: ENHANCEMENT

. FUND: STP ~l

'LENGTH(mileslkm) 0/0.00

'DESCRPT: FOLKSTON STREESCAPE; MUSEUM & WEL<::0MECENTER', '

PROJECT: 522350- TYPE WORK: RECSTIREHAB

FUND: STP , '.

LENGTH'(miles I km) 2.5 14.03

DESCRPT: SR 40 EIFOLKSTONI MP 2.75/EOF CR 821KENNISONS'RIn:O MP 5.6

EXIST. LANES: 02 PROPOSED LANES: 03

9116/99 Page 46 o/2!5

PE:LOCL ROW: LOCL CST:;2000 . FEDShiJre:
OTR Share: . PE:1992
...ROW:2000 CST:

$118,000 $94,400
$23,600 UNDERWAY
$100,000 AFTER.2002

PROJECT: 523245-

TYPE WORK: MAINTENANCE

FlJND.: -NHS

PE: NONE'

LENGTH'(mileS/km) 2.11/3.40:-! ~; '" ~ .'., -'ROW.-NONE

DESCRPT: SR 4IUS 1 FM US 301 TO MP7.33 NB & FM MP 7.64 TO-US 301 SB , .... ,.. . . CST: 2000

LUMP SUM PROJECT

~ . - . " ,( < . FED Share: ..

. 'GAShare:

$121,000 $96,800 $24,200

PROJECT: 5331'85- TYPE WORK: MAINTENANCE

FUND: SIP' .,

LENGTH (miles I km) 11.5 118.50'-

DESCRPT: SR 252 FM SR 4 TO CAMDEN COUNTYLINE

LUMP SUM PROJECT

<

PE:NONE .ROW: NONE' . CST: 2000 FED Share: GAShare:

$284,000 $227,200 J' $56,800

.END OF CHARLTON COUNTY .
~ .'

~'1,",'
-t1
I11f
I I
I'
I I I I I I I I
E
I
I.
I

STATE TRANSPORTATION IMPROVEMENT PROGRAM

CHATHAM COUNTY

PROJECT: 0000021 TYPE WORK: ENHANCEMENT

FUND: STP

SAVANNAH TIP # 2000-H-18

LENGTH (miles / km) 0 /0.00

DESCRPT: COASTAL GEORGIA GREENWAY-MULTI-USE TRAILS-9 COUNTIES

PE:LOCL ROW: LOCL CST: 2000 FED Share:

9/16/99 Page 47 of275
$500,000 $400,000

PROJECT: 0000022 TYPE WORK: ENHANCEMENT

FUND: 'STP

SAVANNAH TIP # 2000-H-16

LENGTH (miles / km) 0 /0.00

DESCRPT: GARDEN CITY BIKE LANE

OTHShare:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$100,000
$300,QOO $240,000

OTJI Share:

PROJECT: 0000072 TYPE WORK: ENHANCEMENT

FUND: STP

PE: LOCL

SAVANNAH TIP # 20OQ-H-17

LENGTH (miles / km) 0 /0.00

ROW: LOCL

'DESCRPT: TOM TRIPLETT COMMUNITY PARK TRAIL & OGEECHEE CANAL MASTER PL

CST: 2000

FED Share:

$60,000
$500,000 $400,000

PROJECT: 521495- TYPE WORK: NEW CONSTRUCTION FUND: NHS

SAVANNAH TIP # 93-H-Q5

LENGTH (miles / km) 1.14 / 1.84

DESCRPT: SR 204/ABERCORN ST @ VETERANS PKY (SOUTHWEST BYP)

EXIST. LANES: 04 PROPOSED LANES: 06

OTJI Share:
PE: 1992 ROW: LOCL CST: 2000 FED Share: GAShare:

$100,000 UNDERWAY
$9,202,000 $7,361,600 $1,840,400

PROJECT: 521505- TYPE WORK: NEW CONSTRUCTION' FUND: HPP

PE: 1992

SAVANNAH TIP # 87-H-IO

LENGTH (miles / km) 1.9/3.06

ROW: LOCL

DESCRPT: HARRY S.TRUMAN PKYIPH IV FM WHITFIELD AVE TO MONTGOMERY X-RD

CST: 2000

EXIST. LANES: 00 PROPOSED LANES: 04

FED Share:

GAShare:

UNDERWAY
$7,766,000 $6,212,800 $1,553,200

PROJECT: 521508- TYPE WORK: NEW CONSTRUCTION FUND: NHS,

SAVANNAH TIP # 87-H-09

LENGTH (miles / km) 2.2/3.54

DESCRPT: HARRY S.TRUMAN PKYIPH III FM MONTGOMERY X-RD TO DERENNE AVE

EXIST. LANES: 00 PROPOSED LANES: 04

PE: 1992 ROW:LOCL CST:2000 ' FED Share: GAShare:

UNDERWAY
$22,540,000 $18,032,000
$4,508,000

PROJECT: 521770- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 87-H-34

LENGTH (miles / km) 1.913.06

DESCRPT: SR 26 FM BRYANWOOD RD TO WIBULL RV INCL BIKE SH & BRG-52Y770

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 52Y770-

PE: 1992 ROW: 1996 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $8,600,000 $6,880,000 $1,720,000

PROJECT: 521855- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 87-H-18B

LENGTH (miles / km) 1.3812.22

DESCRPT: SR 26 FM 4-LN ElLYNES PKWY TO VICTORY DRICS 188

EXIST. LANES: 02 PROPOSED LANES: 04

PROjECT: 521860- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 9Q-H-6

LENGTH (miles / km) 3.69/5.94

DESCRPT: SR 25 FM 4-LN N/SR 204 NE TO SR 307 (INCLD TWO BRDGES &BlKE)

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: LOCL CST: 2001 FED Share:
OTHShare: PE: 1992
ROW: 1998 CST: 2000 FED Share: GAShare:

UNDERWAY
$7,090,000 $3,545,000
$3,545,000 UNDERWAY UNDERWAY $6,049,000 $4,839,200 $1,209,800

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99 Page 48 0/275

CliATH'AM COUNTY



'.

PROJECT: 521865- TYPE WORK: RECSTIREHAB

FUND: 'STP

SAVANNAH TIP # 90-H-07

LENGTH (miles I km) 2.4/3.86

PE: 1992 ROW: 1998

UNDERWAY UNDERWAY

DESCRPT: SR 25IUS 17 FM OGEECHEE RVR OFLW TO S/SR 204(& NEW BR)

CST:2001 .

$6,310,000

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

$5,048,000

ASSOCIATED PROJECTS: 521867-

GAShare:

$1,262,000

PROJECT: 521867- TYPE WORK: REHAB. BRIDGE

FUND: 'BRIDGE

SAVANNAH TIP # 93-H-l1

LENGTH (mileslkm) 0.05/0.08

DESCRPT: SR 25IUS 17/0CEAN HWY @ OGEECHEE RIVER OVERFLOW

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 521865-

PE: 1992 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$1,455,QOO $1,164,000
$291,000

PROJECT: 522050- TYPE WORK: RECSTIREHAB

FUND:' STP

SAVANNAH TIP # 91-H-16

LENGTH (;,ules I km) 0.6/0.97

DESCRPT: SR 26IUS 80 INTERCHANGEIFLYOVER BRIDGE @ JOHNNY MERCERBLVD

PE:2000 ROW: LOCL CST:

$170,000 AFTER 2002

PROJECT: 52217X- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 96-H-5

LENGTH (miles / km)' 0/0.00

DESCRPT: SR 17IUS 80 FM SR 17 TO CHERRY ST IN BLOOMINGDALEIEFFINGHAM

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 522170-

PROJECT: 522490- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 93-H-03 .

LENGTH (miles Ikm) 5.77/9.29

DESCRPT: SR 26IUS80 FM W OF BULL RIVER TO E OF LAZARETTO CRK & ny"

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 52Y490-

PROJECT: 522870- TYPE WORK: RECSTIREHAB

FUND: NHS

SAVANNAH TIP # 2000-H-04

LENGTH (miles I km) 2.39/3.85

DESCRPT: SR 204/ABERCORN ST FMKING GEORGE BLVD TO RIO RD

.EXIST. LANES: 04 PROPOSED LANES: 06

PE:NONE ROW: NONE eST: NONE

PE: 1994 ROW: 2000 CST:

UNDERWAY $593,000
AFTER 2002
\

PE:2000 .' ROW: NONE CST:

$15,000 AFTER 2002

PROJECT: 523230- TYPE WORK: SAFETY

FUND: NHS

SAVANNAH TIP # 20oo-H-02

~ LENGTH. (miles I km) 0 10.00

DESCRPT: ATMSI SAVANNAH/CHATHAM COUNTY/GDOT REGIONAL TCC

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$1,000,000 $800,000 . $200,000

PROJECT: 523235- TYPE WORK: SAFETY

FUND: NHS

SAVANNAH TIP # 2000-H-03

LENGTH (miles / km) 0 10.00

DESCRPT: ATMSI SAVANNAH SLO SCAN/CMSIRADAR.

PE:NONE
ROW:NONE CST: 2002 . FEDShizre: GA Share:

$1,650,000 $1,320,000
$330,000

PROJECT: 52Y505- TYPE WORK: 'NEW CONSTRUCTION FUND: NHS

SAVANNAH TIP # 87-H-I0

LENGTH (miles / km) 1.9 13.06

DESCRPT: HARRY S.TRUMAN PKYIPH IV FM WHITFIELD TO MONTOGMERY-Q05 $

EXIST. LANES: 00 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 521505-

PE: 1992 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$2,318,000 . $1,854,400
$463,600

STATE TRANSPORTATION IMPROVEMENT PROGRAM

CHATHAM COUNTY

PROJECT: 52Y770- TYPE WORK: ENHANCEMENT

FUND: STP

SAVANNAH TIP # 87-H-34

LENGTH (mileslkm) 1.94/3.12

DESCRPT: SR 26 FM BRYANWOOD RD TO WIBULL RV(SHWN FOR BIKE $)-521770

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 521770-

PROJECT: 532510- TYPE WORK: IMPROVE INTERSECTION FUND: STP

SA VANNAH TIP # 93-H-06

LENGTH (miles I km) 0.3 10.48

DESCRPT: SR 204/ABERCORN ST. @ EISHENHOWER IN SAVANNAH

PE:NONE ROW: LOCL CST: 2000 FED Share:
OTHShare:
PE:NONE ROW: 1995 CST: 2000 FED.Share: GAShare:

9116/99 Page 49 of275
$250,000 $200,000
$50,000
UNDERWAY $960,000 $864,000 $96,000

PROJECT: 532570- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 93-H-12

LENGTH (miles I km) 0.12/0.19

DESCRPT: ABERCORN ST @ TIBET AVE

PE:1995 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$767,000 $613,600 $153,400

PROJECT: 532750- TYPE WORK: TURN LANES

FUND: STP

SAVANNAH TIP # 97-H-01

LENGTH (miles I km) 0.31 10.50

DESCRPT: SR 204/ABERCORN ST. @ EGRESS LN/OGLETHORPE MALL IN SAVANNAH

EXIST. LANES: 06 PROPOSED LANES: 07

PE: 1.998 ROW: LOCL CST: 2002 FED Share: GAShare:

UNDERWAY
$750,000 $675,000
$75,000

PROJECT: .532760- TYPE WORK: TURN LANES

FUND: STP

SAVANNAH TIP # 97-H-02

LENGTH (miles I km) 0.2 10.32

DESCRPT: SR 204/ABERCORN ST. @ DERENNE AVE IN SAVANNAH

PE: 1998 ROW: LOCL CST: 2002 . FEDShare: GAShare:

UNDERWAY
$174,000 $156,600
$17,400

PROJECT: 532770- TYPE WORK: TURN LANES

FUND: STP

SAVANNAH TIP # 97-H-03

LENGTH (miles I km) 0.47/0.76

DESCRPT: SR 204/ABERCORN ST. @APACHE AVE IN SAVANNAH

PE: 1998 ROW:LOCL CST: 2002 FED Share: GA Share:

UNDERWAY
$234,000 $210,600
$23,400

PROJECT: 532780- TYPE WORK: TURN LANES

FUND: STP

SAVANNAH TIP # 97-H-04

LENGTH(mileslkm) 0.41/0.66

DESCR)'T: SR 204/ABERCORN ST. @ LARGO DRIVE IN SAVANNAH

PE: 1998 ROW: LOCL CST: 2002 FED Share: GAShare:

UNDERWAY
$277,000 $249,300
$27,700

PROJECT: 533070- TYPE WORK: REPLACE BRIDGE

FUND: STP

SAVANNAH TIP # 2000-H-Q6

LENGTH (miles I km) 0.2 10.32

DESCRPT: SR 26 OVER PLACENTIA CANAL IN THUNDERBOLT

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$485,000 $388,000
$97,000

PROJECT: 550550- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 92-H-03

LENGTH(mileslkm) 3.215.15

DESCRPT: SR 204 SPURIDIAMOND CSWY FM FERGUSON AVE TO MCWHORTER RD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 2001 CST: 2002 FED Share: GA Share:

UNDERWAY $1,810,000
$26,071,000 $20,856,800
$5,214,200

-----

"._1_.__ . __"'" .."_ __ ~~

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99

Page 50 of275

CHATHAM COUNTY

.
,

PROJECT: 550570- TYPE WORK: RECSTIREHAB

FUND: STP

, SAVANNAH TIP # 94-H-22

LENGTH (miles / km) 1.5512.50

PE: 1995' ROW: LOCL

UNDERWAY

DESCRPT: MONTGOMERY CROSS/MIDDLEGROUND: SR204 TO SR204-CONTRACT 2

CST: 2002

$5,041,000

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

$4,032,800

GAShare:

SI,008,200

PROJECT: 550575- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 2000-H:05

LENGTH (miles / kin) 1.25 12.01

DESCRPT: MONTGOMERY CROSSIMIDDLEGROUND: SR204 TO SR204-CONTRACT 1

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$2,000,000 $1,600,000
$400,000

PROJECT: 550580- TYPE WORK: RECSTIREHAB

FUND: STP

SAVANNAH TIP # 94-H-23

LENGTH (miles / km) 2.1 /3.38

DESCRPT: WHITE/COFFEE BLUFF RDS FM N OF LIDLE OGEECHEE RVR TO WILLOW

EXIST. LANES: 02 PROPOSED LANES: 04

, PE: 1995 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$3,402,000 $2,721,600
$680,400

PROJECi: 550594- TYPE WORK: NEW CONSTRUCTION FUND: STP

SAVANNAH TIP # 91-H-16

LENGTH (miles / km) 0.5/0.81

DESCRPT: SR 17/SR 26IUS 80 NEW INTERCHANGE AT THE POOLER PARKWAY

ASSOCIATED PROJECTS: 550593-

PE: 1996 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$6,000,000 $4,800,000 $1,200,000

PROJECT: 562165- TYPE WORK: RECSTIREHAB

FUND: 'STATE

SAVANNAH TIP # 2000-H-07

. LENGTH (miles / km)

1 /1.61

DESCRPT: SR 307IDEAN FOREST ROAD FM RB. MILLER RD TO SR 21

EXIST. LANES: 04 PROPOSED LANES: 05

PE:NONE ROW: 2000 CST:

$300,000 AFTER 2002

PROJECT: 571402- TYPE WORK: ENHANCEMENT

FUND: STP

SAVANNAH TIP # 99-H-7

. .LENGTH(miles/km) 0/0.00

DESCRPT: SIDEWALKS ALONG 6 STREETS IN POOLER

PROJECT: 571404- TYPE WORK: ENHANCEMENT

FUND:' STP

SAVANNAH TIP # 99-H-6

LENGTH(miles / km)

0/0.00

DESCRPT: TYBEE ISLAND LIGHT STATION STRUCTURE

PROJECT: 571406- TYPE WORK: ENHANCEMENT

FUND: STP

SAVANNAH TIP # 99-H-5

LENGTH (miles / km) 0/0.00

DESCRPT: CENTRAL OF GA RAILROAD BUILDINGS IN SAVANNAH

END OF CHATHAM COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share: GA Share: OTHShare:
PE:LOCL 'ROW:LOCL
CST: 2000 FED Share:
OTHShare: PE:LOCL
ROW: LOCL "
CST: 2000
FED Share:
OTHShare:

$78,000 $62,400
($400) $16,000
$187,000 $149,600
$37,400
$187,000 $149,600
$37,400

~.
Ii

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page 51 of275

f

CHATTAHOOCHEE COUNTY

PROJECT: 321580- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1989

UNDERWAY

~.
~

DESCRPT: SR 1 @ HICHITEE CREEK EXIST. LANES: 02 PROPOSED LANES: 04

LENGTH (miles / km) 0.3/0.48

.ROW: NONE CST: 2001
FED Share:

$865,000 $692,000

ASSOCIATED PROJECTS: 322160-
I'

GA Share:

$173,000

PROJECT: 332955- TYPE WORK: MAINTENANCE

FUND: STP

PE: 1998

UNDERWAY

LENGTH (miles / km) 0.5/0.81

ROW: NONE

I

DESCRPT: SR 520 WESTBOUND AT MP 9.5-SLIDE REPAIR LUMP SUM PROJECT

CST: 2000 FED Share:
GAShare:

$597,000 $477,600 $119,400

I

END OF CHATTAHOOCHEE COUNTY

I,

I

I

I

I

I I,

I

I

I

)

I

I

I

STATE TRANSPORTATION IMPROVEMENTPROGRAM

CHATTOOGA COUNTY

PROJECT: 0000111 TYPE WORK: ENHANCEMENT

FUND: STP

PE: LOCL

,.'

LENGTH (miles 1 km) 0/0.00

ROW: LOCL

iJESCRPT: SUMMERVILLE-DOWDYPK TURNTABLEIDEPOTRESTORATIONIPED WALKWY' CST:'ZOOO

FED Share:

PROJECT: 621082- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 8/12.88

DESCRPT: SR lIUSZ7/SUMMERV'LE BYP FM CR 329 TO N OF CR325 @ SR llUS27

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 62Y082-

OTHSltare:
PE: 1993 ROW: 2001 , CST:'

9116199 Page 52 of275
$319,000 $255,200 $63,800 UNDERWAY $2,180,000 AFTER 2002

PROJECT: 621610- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 11.7/18.84

DESCRPT: SR llUS 27 FM CR 331ITRION TO LAFAYETIE BYP & WALKER CO

EXIST. LANES: OZ PROPOSED LANES: 04

ASSOCIATED PROJECTS: 62161X-

PE:.1992 ROW: CST:

UNDERWAY AFTER 2002 AFTER 2002

PROJECT: 62Y082- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0/0.00

DESCRPT: SR lIUS27/SUMMERV'LE BP FM CR 329 TO CR325-FOR FED PE;62 1082

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 621082-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 642470- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE,

PE: 2000

LENGTH (miles 1 km) 0.22/0.35

ROW: LOCL

DESCRPT: CR 3321BACK BERRYTON ROAD @ RACCOON CREEK CENTER OF BERRYTON

CST: 2002

FED Share: ,

END OF CHATTOOGA COUNTY

OTHShare:

$21,000 '
$700,000 $560,000
$140,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

CHEROKEE COUNTY

PROJECT: 611220- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km) 0/0.00

DESCRPT: 1-575@9 LOC/CHEROKEEISR372IPICKENSISEE PICKENS-61122X LUMP SUM PROJECT

ASSOCIATED PROJECfS: 61122X-

PE: 1997 ROW: NONE CST: 2000 FED Share: GAShare:

9/16199 Page 53 of275
UNDERWAY

$500,000 $450,000 $50,000

PROJECT: 611221- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # CH AR 233

. LENGTH (miles 1 km) 0.2/0.32

DESCRPT: 1-575 SAFETY UPGRADES AT SIXES ROAD

PE: 1997 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$1,200,ODO $i,080,000
$120,000

PROJECT: 611222- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # CH AR234

LENGTH (mileslkm) 0.2/0.32

DESCRPT: 1-575 SAFETY UPGRADES AT HOLLY SPRINGS RD/J. E. BROWN HWY

PE: 1997 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 611223- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # CH AR 235

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: 1-575 SAFETY UPGRADES AT SR 20/SR 140

PE: 1997. ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 611224- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # CH AR 236

LENGTH (mileslkm) 0.2/0.32

DESCRPT: 1-575 SAFETY UPGRADES AT SR 20

PE: 1997 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 611225- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # CH AR237

LENGTH(mileslkm) 0.2/0.32

DESCRPT: 1-575 SAFETY UPGRADES AT SR 5 BUSINESS/SR 20

PE: 1997 ROW: NONE CST: 2000 ' FED Share: GA Share:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 611226- TYPE WORK: . SAFETY

FUND: 1M

ATLANTA TMA TIP # CH AR238

LENGTH (mileslkm) 0.2/0.32

DESCRPT: 1-575 SAFETY UPGRADES AT AIRPORT DRIVE

PE: 1997 ROW: NONE CST: 2000 FEDShare: GA Share:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 611227- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # CH AR 239

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: 1-575 SAFETY UPGRADES AT HOWELL BRIDGE ROAD

PE: 1997 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 61 p50- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # CH AR 229

LENGTH (mileS1 km) 1.21 11.95

DESCRPT: 1-575 AUXILIARY LANES BETWEEN SR 92 AND TOWNE LAKE PARKWAY

PE:2001 ROW: CST:

$15,000 AFfER2002AFfER2002

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 54 of275

CHEROKEE COUNTY

PROJECT: 611260- TYPE WORK: RECSTIREHAB

FUND: NHS

..

ATLANTA TMA TIP # CH AR 230 '

LENGTH (miles 1 km) 0.28 10.45

DESCRPT: 1-575 AUXILIARY LANES BETWEEN SR 20.AND SR 5 BUSINESS

PE:2001 ROW: NONE CST: '

$10,000 AFTER 2002

PROJECT: 611270- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # CH AR 231

LENGTH (miles! km)' 0.28 10.45

DESCRPT: 1-575 AT SR 20 - INTERCHANGE RECONSTRUCTION

PE:2001 ROW: CST:

$15,000 AFTER 2002 AFTER 2002

. PROJECT: 632790- TYPE WORK: RECSTIREHAB

FUND: MIN. GUARANTEE PE: 2000

ATLANTATMATIP#CHI82

LENGTH (mileslkm) 3.2/5.15

' ROW:2001

DESCRPT: SR 20 TRUCK CLIMBING LANES AND INT IMP FM 1-575 TO CR 238

CST: 2002

FED Share:

GAShare:

PROJECT: 632840- TYPE WORK:' RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # CH 197

LENGTH (mileslkm) 1.712.74

DESCRPT: SR 140 FM ARNOLD MILL RD/CR 777 TO MOUNTAIN RD/CR 311

PE:2000 ROW: 2002 . CSi:2002 FED Share: GAShare:

PROJECT: 632845- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # CH 196

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: SR 140 @ SUGAR PIKE RD/CR 296

PE:2000 ROW: 2002 CST: 2002 FED Share: GAShare:

PROJECT:, 632850- TYPE WORK: REC$TIREHAB

FUND: STP

ATLANTA TMA TIP # CH 195

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: SR 140 @ HICKORY ROAD/CR 778 & BATESVILLE ROAD/CR 298

PE:2000 ROW: 2002 CST: 2002 FED Share: GA Share:

PROJECT: 632855- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # CH 194

LENGTH (miJeslkm) 0.4/0.64

DESCRPT: SR 140 AT MAULDIN ROAD/CR 323 AND UNIVETER ROAD/CR 309

PE:2000' ROW: 2002 . CST:2002 FED Share: GA Share:

PROJECT: 632860- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTATMATIP# CH 198

LENGTH(mileslkm) 0.2/0.32

DESCRPT: SR 140 AT SCOTT ROAD/CR 288

PE:2000 ROW: 2002 CST: 2002 FED Share: GA Share:

PROJECT: 642485- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # CH 200

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: SR 140: REALIGN HOSPITAL RD & SHOAL CK RD IN CITY OF CANTON

PE:LOCL ROW: 2000 CST: 2000 FED Share:
OTH Share:

$214,000 $2,082,000 . $4,275,000 $3,420,000
$855,000
, $90,000 $115,000 $1,965,000 $1,572,000 $393,000
$12,000 $20,000 $246,000 $196,800 $49,200
$11,000 $26,000 $217,000 $173,600 $43,400
$16,000 $47,000 $310,000 $248,000 $62,000
$13,000 , $21,000 $258,000 $206,400
$51,600
$300,000 $565,000 $452,000
$113,000

..
STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 . Page 55 of275

CHEROKEE COUNTY

PROJECT: 642490- TYPE WORK: NEW CONSTRUCTION FUND: STP

PE:LOCL

:

ATLANTA TMA TIP # CH AR BP035

LENGTH (miles 1 km) 1.512.42

ROW: LOCL

~!

DESCRPT: SR 5 BUS MULT-USE TRAIL FM JUNIPER ST TO BOLING PK IN CANTON

CST:2000.

$160,000

I< .1

FED Share:

. $128,000

I

PROJECT: 642495- TYPE WORK: ENHANCEMENT

FUND: STP

OTH Share: PE:LOCL

$32,000

ATLANTATMA TIP#CHARBP021

LENGTH (mileslkm) 0/0.00

ROW: LOCL

I

DESCRPT: JOHN T PETIT MULTI-USE TRAIL &DRAINAGE;LN WIDENING IN CANTON

CST: 2000

FED Share:

$144,ODO $115,200

I

PROJECT: 662610-. TYPE WORK: ENHANCEMENT

FUND: STP

OTH Share: PE:2001

$28,800 $5,000

ATLANTA TMA TIP # CHARBP018

LENGTH (mileslkm) 0/0.00

ROW: LOCL

I

DESCRPT: TOWNE LAKE PKWY FM 1-575 TO EAGLE DR

CST:20(l2 FED Share:

$185,000 $148,000

OTHShare:

$37,000

I

PROJECT: 662612- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # CHARBP020

LENGTH (mileslkm) 0/0.00

PE:2001 ROW: LOCL

$5,000

DESCRPT: WADE GREEN RD FM HWY 92 TO COBB CO LINE

CST: 2002

$84,000

Ii.i

FED Share:

$67,200

OTHShare:

$16,800

I

PROJECT: 662614- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # CH AR BP015

LENGTH (miles 1 km) 0/0.00

. PE:2001 ROW: LOCL

$5,000

DESCRPT: OLD TOWNE LAKE PKWY FM BELLS FERRY RD TO EAGLE DR

CST: 2002.

$173,000

I

FED Share: OTHShare:

$138,400. $34,600

PROJECT: 662615- TYPE WORK: NEW CONSTRUCTION FUND: STP

I

ATLANTA TMA TIP # CH AR BP037

LENGTH (miles 1 km) '. 1.512.42.

DESCRPT: SUNSETIIVY DRS FM MARlETIA TO MCCOLLUM IN CANTON

PE:LOCL ROW: LOCL CST: 2000

$275,000

FED Share:

$220,000

I

OTHShare:

$55,000

PROJECT: 662616- TYPE WORK: NEW CONSTRUCTION FUND: STP

PE:LOCL

I

ATLANTA TMA TIP # CH AR BP038

LENGTH (miles 1 km) 0.9/1.45

DESCRPT: EDWARDS STIMERIDAN ST IN CANTON FROM MARlETIA RD TO END

ROW: LOCL CST: 2000

$150,000

FED Share:

$120,000

I

OTHShare:

$30,000

PROJECT: 662617- TYPE WORK: NEWCONSTRUCTION FUND: STP

PE:LOCL

ATLANTA TMA TIP # CH AR BP034

LENGTH (miles 1 km) 2/3.22

ROW: LOCL

I

DESCRPT: MEDICAL DISTRICT IN CANTON:HOSP RD@SRI40 TO HOSP DR@SR5 BUS'

CST: 2000

FED Share:

$800,000 $640,000

~

PROJECT: 662618- TYPE WORK: NEW CONSTRUCTION FUND: STP

OTHShare: PE:LOCL

$160,000

ATLANTA TMA TIP # CH AR BP036

LENGTH (miles 1 km) 0/0.00

ROW: LOCL

~

DESCRPT: PED BRIDGE FM W OF CANTON MILL LOFTS TO SR 5 BUS TO JUNIPER

CST: 2000 FED Share:

$750,000 $600,000

OTHShare:

$150,000

STATETRANSPORTA'TION IMPROVEMENT PROGRAM

CHEROKEE COUNTY

PROJECT: 662619- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # CH AR BP033

LENGTH (miles 1 km) 0 10.00

DESCRPT: LOWER SCOTT MILL RD FM SR 140 TO CHURCH IN CANTON

PE:LOCL ROW: LOCL CST: 2000 FED Share:

9116/99 Page 56 of275
$116,000 $92,800

PROJECT: 662620- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # CH 181

LENGTH (mileslkm) 3.67/5.91

DESCRPT: OLD SR 5 FM WOODSTOCK CL TO HOLLYSPRINGS CL

OTR Share:
PE:2000 ROW: LOCL CST: 2001 FED Share:

$23,200 $300,000
$2,500,0.00 $2,000,000

PROJECT: 671951- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # CI:i 199 .

LENGTH (mileslkm) 0.21/0.34

DESCRPT: CR 107IHOWELL BRIDGE RD @ SHARP MTN CREEK SW OF BALL GROUND

OTR Share:
PE:2000 ROW: LOCL CST:

$500,000 $30,000
AFTER 2002

END OFCHEROKEE COUNTY

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

CLARKE COUNTY

PROJECT: 0000159 TYPE WORK: ENHANCEMENT

FUND: STP

PE: LOCL

ATHENSTIP#

LENGTH (mileslkm) 0/0.00

ROW: LOCL

DESCRPT: ATHENS-CLARKE CO/WHITEHEAD & OGLETHORPE ELEMENTARYIPED IMP

CST: 2000

FED Share:

9116/99 Page 57 of275
$225,000 $180,000

OTIJ Share:

$45,000

PROJECT: 0000160 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

ATHENS TIP #

LENGTH (miles I km) 0 10.00

ROW: LOCL

I

DESCRPT: ATHENS-eLARKE COIRIVER BEND ROAD BIKE LANES

CST: 2000 FED Share:

$302,000 $241,600

I.

. PROJECT: 0000161 TYPE WORK: ENHANCEMENT

FUND: STP

OTHSlIare: PE:LOCL

$60,400

ATHENS TIP #

LENGTH (mileslkm) 0/0;00

. ROW: LOCL

I

DESCRPT: ATHENS-CLARKE COIMULTI-USE BRIDGES OVER TRAIL & SANDY CREEKS

CST: 2000

FED Share:

. $361,000 $288,800

OTIJ Share:

$72,200

I

PROJECT: 0000162 ATHENS TIP #

TYPE WORK: ENHANCEMENT'

FUND: STP

LENGTH (miles I km) 0/0.00

PE:LOCL ROW: LOCL

DESCRPT: ATHENS-CLARKE COrrHE UNIVERSITY OF GEORGIA RIVER TRAIL PH II

CST: 2000

$365,000

I

FED Share:

$292,000

OTHShare:

$73,000

I

PROJECT: 122160- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP # 11-01(2)

LENGTH (mileslkm) 4/6.44

DESCRPT: SR 15 ALrnrs 129 FM LAVENDER DR/CLARKE TO SR 330/JACKSON

PE: 1992 ROW: 2000 CST: 2001

UNDERWAY $3,054,000 $8,950,000

I

EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 12216X-

FED Share: GAShare:

$7,160,000 $1,790,000

PROJECT: 122600- TYPE WORK: IMPROVE INTERSECTION FUND: STP

I

ATHENS TIP # 11-04

LENGTH (mileslkm) 0.5 10.81

DESCRPT: SR 10 LOOP/ATHENS PERIMETER AT US 78ILEXINGTON RD

PE: 1994 ROW: 2000 CST: 2001

UNDERWAY $495,000 $712,000

EXIST. LANES: 0 PROPOSED LANES: 02

FED Share:

$569,600

I

GAShare:

$142,400

PROJECT: 122850- TYPE WORK: RECSTIREHAB

FUND: NHS

PE: 1998

UNDERWAY

I

ATHENS TIP # 11-09

LENGTH(mileslkm) 0.2/0.32

DESCRPT: SR 10 LOOP/ATHENS PERIMETER AT PETER ST/CS 306 & OLYMPIC DR

ROW: 2001 CST: 2002

$500,000 $10,500,000

EXIST. LANES: 00 PROPOSED LANES: 02 .

FED Share:

$8,400,000

I PROJECT: 122890- TYPE WORK: RECSTIREHAB

FUND: NHS .

GA Share: . PE: 1998

$2,100,000 UNDERWAY

ATHENS TIP # 11-15

LENGTH (mileslkm) 0.25/0.40

I

DESCRPT: SR 10LPIPAUL BROUN PKWY AT SR 10/ATLANTA HWY IN ATHENS

ROW: 2002 CST:

$4,000,000 AFTER 2002

I

PROJECT: 132660- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP # 11-08

LENGTH (mileslkm) 7.92/12.75

I

DESCRPT: SR 10lUS 78 FM WHIT DAVIS RD/CR 166 TO SMOKEY/CR 26i& OGLETH EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 13266X- 231940-

I

PE: 1998 ROW: 2002 CST:

UNDERWAY $1,580,000 AFTER 2002

_.- ---_._----STATE TRANSPORTATION IMPROVEMENTPROGRAM

CLARa COUNTY

PROJECT: 'l32805ATHENS TIP # IV-02

TYPE WORK: REPLACE BRIDGE

'FUND: BRiDt1E

LENGTH (miles I km) 0.42 10.68

. DESCRPT: SR 15IUS 129 @ MIDDLE OCONEE RIVER 3 MI SOutH OF ATHENS

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOClATED PROJECTS: 132800-

PE: 1999 ROW: LOCL CST: 2002 FED Share: GA Share:

9116199 Page 58of275
UNDERWAY
$826,000 $660,,800 $165,200

PROJECT:' '142200- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP # 11-14

LENGTH flniles I km) 0.2510.40

DESCRPT: WINTERVILLE RD/CR 470 AT NELLIE B. AVE/CR 141

PE:2000 ,
ROW: LOCL CST:

$5,000 AFTER 2002

GA Share:

$0

PROJECT: 142205- TYPE WORK: RECSTiREHAB

FUND: STP

ATHENS TIP # 11-15

LENGTH(mileslkm) 0.25/0.40 .

DESCRPT: WINTERVILLE RD/CR 470 AT INDIAN HILLS & SPRING VALLEY-REALGN

PE:2000 ROW: LOCL CST:
GAShare:

$5,000 AFTER 2002
$0

PROJECT: 142210- .TYPE WORK: RECSTIREHAB

-FUND: STP .

ATHENS TIP # 11-16

LENGTH (miles I km) 0.2510.40

DESCRPT: SPRING VALLEY RD/CR 140 ATATHENA DR AND MOSS lID-REALIGNMENT

, PE:2000 ROW:LOCL CST:

GAShare:

$5,000 AFTER 2002
$0

PROJECT: 142215- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP # 11-17

LENGTH(mileslkm) 0.7/I.13

DESCRPT: BARNETT SHOALS/GAINES SCHOOL:RD FM GREENCREST TO CEDAR SHOAL

, PE:2060 ROW: CST:

$5,000 AFTER 2002 AFTER 2002

PROJECT: 142220- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP #

LENGTH (miles I km) 0.2510.40

DESCRPT: GAINES SCHOOL RD/CR 471 AT HILSMAN MIDDLE SCHOOL

PROJECT: 142225- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP # 11-18

LENGTH(~es/km) 0.2510.40

.DESCRPT: GAINES SCHOOL ROAD/CR 477 AT CEDAR SHOALS DRIVE

PROJECT: 142230ATHENS TIP # 11-02

TYPE WORK: RECSTIREHAB

FUND: STP

" LENGTH (mil~/km) 2.4 13.86

DESCRPT: OLD HULL RD/CR 127 FM NORTH AVE TO HULL RDISR 72(EXCEPTION)

EXIST. LANES: 02 PROPOSED LANES: 03

PROJECT: 142235- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP # 11-19

LENGTH (mileslkm) 0.2510.40

DESCRPT: HAWTHORNE AVEiCR 811 At 'OLD WEST BROAD ST/CR 938

PE:2000 ROW: ' CST: .
GA Share:
PE:2000" ROW: CST:
GA Share:
PE:2000 ROW: LOCL CST:
GA Share:
PE:2000 ROW: LOCL CST:
GA Share:'

. $5,000 AFTER 2002 AFTER 2002
$0
$5,000 AFTER 2002 AFTER 2002
$0
$5,000 AFTER 2002
$0
. $5,000 AFTER 2002 .
$0

__. _ - - ------~-------_.

.._ - - - - - - - - - - - -

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 59 of275

CLARKE COUNTY

PROJECT: 170522- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATHENS TIP # IV-05

LENGTH (mileslkm) 0.2/0.32

DESCRPT: CR 119/NOWHERE ROAD @ EAST SANDY CREEK 4 Ml NORTH OF ATHENS

PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

$20,000
$605,000 $484,000 $121,000

PROJECT: 171570- TYPE WORK: ENHANCEMENT

FUND: STP

ATHENS TIP # V-D4

LENGTH (miles 1 km) 0/0.00

DESCRPT: HERITAGE TRAIL PHASE II ALONG OCONEE RIVER IN ATHENS

END OF CLARKE COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTll Share:

$867,000 $693,600
$173,400

STATE TRANSPORTATION IMPROVEMENTPROGRAM

/
cLAY COUNTY

PROJECT: 0000081

TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: PLANNING FOR MULTI-USE TRAIL FM FORT GAINES TO GEORGE BAGBY

PE:2000 . ROW: NONE CST: NONE

9/16/99 Page 60 of275
$30,000

PROJECT: 422230- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 7.44/11.98

DESCRPT: SR 1 FM BLUFFTON BYP TO CARNEGIE VILULAH WICR 153lRANDOLpH

. EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 42223X- 42Y230-

PROJECT: 42Y230- TYPE WORK: RECSTIREHAB

FUND: NBS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 1 FM BLUFFTON BYP TO CR 153lRANDOLPH - FOR FED P~; 422230

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422230-

END OF CLAY COUNTY

PE: 1993' ROW: 2001 . CST:

UNDERWAY $1,119,000
AFTER~002

PE:2000 ROW: NONE CST: NONE

$1,000

:;"

.~.
.~

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 61 of275

CLAYTON COUNTY

S..

PROJECT: 712630 TYPE WORK: RECSTfREHAB

FUND: NHS

PE: 1992

UNDERWAY

ATLANTA TMA TIP # CL AR 031

LENGTH (mileslkm) 2.4/3.86

ROW: 2000

$920,000

DESCRPT: 175 @ SR 54: INCL RR BRIDGE OVER 1-75

CST: 2002

$15,139,000

FED Share:

$12,111,200

ASSOCIATED PROJECTS: 712602-

GAShare:-

$3,027,800

PROJECT: 713050- TYpE WORK: IMPROVE INTERSECTION FUND: 1M

- ATLANTA TMA TIP # AR 222

LENGTH (miles I km) 010.00

DESCRPT: 1-6751 1-751 1-20-IMPACT ATTENTUATORS & BARRIER WALL @ BRDG

PE: 1993 ROW: NONE CST: 2000 FED Share:

UNDERWAY
$1,100,000 $1,100,000

PROJECT: 713210 TYPE WORK: RECSTfREHAB

FUND: 1M

ATLANTA TMA TIP # CL AR 179

LENGTH (mileslkm) 1.4712.37

DESCRPT: 1-285 EAST TO 1-75 SOUTH RAMP ALIGNMENT

PROJECT: 713820- TYPE WORK: MAINTENANCE

FUND: NHS

ATLANTA TMA TIP # AR BOD

LENGTH (mileslkm) 010.00

DESCRPT: BRIDGE JACKING PROJECT IN CLAYTONIDEKALB

LUMP SUM PROJECT

ASSOCIATED PROJEOTS: 71382X- 71Y820-

PROJECT: 714040- TYPE WORK: NEW CONSTRUCTION FUND: HPP

ATLANTA TMA TIP # CL AR 227

LENGTH (miles I km) 010.00

DESCRPT: 1-75 FM MT ZION ROAD TO OLD DIXIE HWY FOR 3 NOISE BARRIERS

PROJECT: 714070- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # AR 282

LENGTH (miles I km) 3.53 15.68

DESCRPT: ATMS/I-75 SURVEILLANCE DEVICES FM TARA BLVD TO 1-285

PROJECT: 714075- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP # AR 307

LENGTH (miles I km) 10.5 116.89

DESCRPT: ATMS/I-75 COMMISURVEIL FM HUDSON BR RDIHENRY TO TARA BLVD

ASSOCIATED PROJECTS: 71407X-

PROJECT: 714200- TYPE WORl(: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # AR 157

LENGTH (miles I km) 0.42/0.68

DESCRPT: 1-75 SOUTHBOUND EXIT RAMP TO AND WEST ALONG MT ZION BLVD

LUMP SUM PROJECT

PROJECT: 71Y820- TYPE WORK: MAINTENANCE

FUND: 1M

ATLANTA TMA TIP # AR 130

LENGTH (miles I km) 0/0.00

DESCRPT: BRIDGE JACKING PROJECT IN CLAYTONIDEKALB

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 713820-

PE: 1995 ROW:2001 CST: 2002 FED Share: GA Share:

UNDERWAY $680,000
$2,400,000 $2,160,000
$240,000

PE: 1997 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$1,490,000 $1,192,000
$298,000

PE: 1999 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$1,800,000 $1,440,000
$360,000

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$1,784,000 $1,427,200
$356,800

PE:NONE

ROW: NONE

CST: 2001

$9,132,000

FED Share:

$7,305,600

GAShare:

.. $1,826,400

PE: 1999 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$64,000 $57,600
$6,400

PE: 1997 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY -
$510,000 $459,000
$51,000

;---------_._-----------------------------_.------- _.

--------S-T.-:4-T.-E-T.-'RAN,--S.-rp-O-R-T.-:,4'-T-l0"''N-IM'"-'p' -'R-O-v:-E..M.. -E-'N-r-p-'R-O-G-1UM - - - - - -
9116199
Page 62 of275

CLAYTON COUNTY

PROJECT: 722160- TYPE WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # AR 157

LENGTH (miies1 km) 0.1 10.16

DESCRPT: SR 3 TURN LANES FM NORTH OF MCDONOUGH ROTO SOUTH AVE

LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$918,000 $826,200
$91,800

PROJECT: 731520- TYPE WORK: 'REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # CL 095

LENGTH (miles1 km) 0.26/0.42

DESCRPT: SR 3IUS 19 @ CEN OF GA RAILROAD .35 MI S OF JCT 1-285

PE: 1996 ROW: 2001 CST: 2002 FED Share: GAShare:

UNDERWAY $116,000
$3,461,000 $2,768,800
$692,200

PROJECT: 731855- TYPE WORK: TURN LANES'

FUND: STP

ATLANTA TMA TIP # AR 157

LENGTH (mileslkm) 0.1/0.16

DESCRPT: SR 85 TURN LANES FM WARREN DR TO MARTHA ST

LUMPSUM PROJECT

PE:NONE ROW: NONE 'CST: 2000 FED Share: GA Share:

$412,000 $370,800
$41,200

PROJECT: 731885- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # CL 235

LENGTH (miles I km) 0/0.00

DESCRPT: SR 85 FM SR331 TO POINTE SOUTH PKWY & SR138 FM SR85 TO NAVE

PROJECT: 753010- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # CL 234

LENGTH (miles 1 km) 0.21 10.34

DESCRPT: CR 13511REX ROAD @ LITTLE COTTON INDIAN CREEK IN REX

PE:NONE ROW: NONE CST: 2000 FED Share:
OTHShare: PE: 1999
ROW: LOCL CST: 2002 FEDShare: ' GAShare:

$657,000 $525,600
$131,400 UNDERWAY
$1,645,000 $1,316,000
$329,000

PROJECT: 753020- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # CL 231

LENGTH (mileslkm) 2.11/3.40

DESCRPT: CONL.EY RO/CR 171 FM SR 54 TO DEKALBCOIADD CURB/GUTTER

PE:2000 ROW: LOCL CST: 2000 FED Share:

$46,000
$457,000 $365,600

PROJECT: 753022- TYPE WORK.: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # CL 232

LENGTH (mileslkm) 1.26/2.03,

, DESCRPT: LAKE HARBIN RD FM MADDOX RD TO SR 421ADDCURB & GUTTER

OTHShare:
PE:2000' ROW: LOCL CST: 2000 FED Share:

$91,400 $34,000
$335,000 $268,000

PROJECT: 762609- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # CL ARBP092

LENGTH (milislkm) 5.619.02

DESCRPT: FOREST PARK ALONG US 19/41; SR 54; SR 160 & SR 331 '

OTHShare:
PE:LOCL ROW:LOCL CST: 2000 FED Share:

$67,000
$625,000 $500,000

PROJECT: 771210- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # CL 230

LENGTH (miles 1 km) 1.5 12.42

DESCRPT: ANVILBLOCK RD FM 5 LANE TO HENRY CO IADD CURB & GUTTER

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$125,000 $58,000
$576,000 $460,800

\

OTHShare:

$115,200

0.

.._

. STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 63 of175

CLAYTON COUNTY

PROJECT: 771226- TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

:ft'
l:

ATLANTA TMA TIP # CL AR BP022B

LENGTH (miles / km)

DESCRPT: JESTERS CREEK GREENWAY PHASE II

0/0.00

ROW: LOCL CST: 2000

$1,250,000

{

FED Share:

$1,000,000

PROJECT: 999993- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP #

LENGTH (miles / km)

/

DESCRPT: FUNDING CURRENTLY UNASSIGNED

OTH Share:
PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$250,000
$14,621,000 $11,696,800
$2,924,200

END OF CLAYTON COUNTY

,------=._'-----,...--_._----...----------------------

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99

Page 64 0/275

CLINCH co'fiNTY

PROJECT: 422030- TYPE WORK: RECSTIREHAB

FUND: STATE

,,

LENGTH (miles / km) 1.5 12,42

DESCRPT: SR 38IUS 84 FM W CLIHOMERVILLE TO WEST OF WOODYARD CK

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 2000 CST:

UNDERWAY $2,101,000 AFTER 2002

PROJECT: 422120- TYPE WORK: RECSTIREHAB

FUND: STATE

,

LENGTH (miles/km) 10.4/16.74

DESCRPT: SR 38 FM WEST OF WOODYARD CK TO CR 472 IN MANORl42212X

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 42212X- 422125- 42Y120-

PE: 1994 ROW: 2001 CST:

UNDERWAY $2,862,000 AFTER 2002

PROJECT: 42\'120- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 38 FM WOODYARD CK TO CR 472 IN MANOR - FOR FED PE; 422120

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422120-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 42Y400- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 89IUS 441 FM CR 8 FARGO TO CR 40/204 - FOR FED PE; 422400

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422400-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 42Y41O- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0 /0.00

DESCRPT: SR 89IUS 441 FM CR 40/204 TO SHIRLEY RD - FOR FED PE; 422410

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422410-

PE:2000 . ROW:NONE
CST: NONE

$1,000

!.

PROJECT: 442715- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1996

UNDERWAY

LENGTH (miles / km) 0.23/0.37

ROW: 1999

UNDERWAY

DESCRPT: SR 177 @ SWEETWATER CREEK TO STEPHEN C FOSTER ST PARK

CST: 2000

. $711,000

. FEDShare:

$568,800

GAShare:

$142,200

END OF CLINCH COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

COBB COUNTY

PROJECT: 712806- . TYPE WORK: NEW CONSTRUCTION FUND: 1M

ATLANTA TMA TIP # CO AR 078M

LENGTH (miles/km) 0.210.32

DESCRPT: KENNEDY INTERCHANGE 1-75NB TO 1-285WB FLYOVER BRIDGE (CT 5)

EXIST; LANES: 00 PROPOSED LANES: 02

PE: 1997 ROW: LOCL CST: 2002 FED Share: GAShare:

9/16/99 Page 650f275
UNDERWAY
$10,001,000 $9,000,900 $1,000,100

PROJECT: 713240- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANTA TMA TIP # COAR 180

LENGTH (miles/km) 0.66/1.06

DESCRPT: 1-285 @ PACES FERRY ROAD - INTERCHANGE RECST

PE: 1995 ROW: 1998 CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY $19,739,000 .$17,765,100 $1,973,900

PROJECT: 713260- TYPE WORK: RfHAB. BRIDGE

FUND: 1M

ATLANTA TMA TIP # COAR213

LENGTH (miles/km) 0/0.00

DESCRPT: 1-75 SOUTH TO 1-285 WESTBOUND FLY OVER BRIDGE

PE:2000 ROW: NONE CST:

$700,000 AFTER2002 .

PROJECT: 713600- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANTA TMA TIP # CO AR 238

LENGTH(miles/km) 0.47/0.76

DESCRPT: 1-75 REBUILD INTERCHANGE AT WINDY HILL ROAD

PE:2000 ROW: CST:

$5,000 AFTER 2002 AFTER 2002

PROJECT: 713640- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # AR318B

LENGTH(miles/km) 13.1/21.06

DESCRPT: 1-575 FM 1-75 NORTH TO SIXES ROAD CHEROKEE - FOR HOV

EXIST. LANES: 04 PROPOSED LANES: 06

ASSOCIATED PROJECTS: 71364X-

PE:2000 ROW: NONE CST:

$7,000,000 AFTER 2002

PROJECT: 713700- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ATLANTA TMA TIP # COAR274

LENGTH(miles/km) 0.2/0.32

DESCRPT: 1-75 CONSTRUCT GATEWAY WELCOME CENTER @ WADE GREEN ROAD

EXIST. LANES: 00 PROPOSED LANES: 01

PE: 1996 ROW: NONE CST: 2002 FED Share:

PROJECT: 713730- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # COAR239

LENGTH (miles/km) 1.12/1.80

DESCRPT: 1-75 NORTHBOUND OFF-RAMP FROM 1-75 TO AND ON BARRETT PKWY

OTHShare:
PE: 1998 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY.
$14,000,000 $11,200,000
$2,800,000 UNDERWAY
$2,244,000 $1,795,200
$448,800

PROJECT: 71397Q.. TYPE WORK: MAINTENANCE

FUND: NHS

ATLANTA TMA TIP # AR 130

LENGTH(miles/km) 0/0.00

DESCRPT: BRIDGE JACKING IN COBB-CHEROKEE-CATOOSA

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 71397X-

PE: 1998 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$2,000,000 $1,600,000
$400,000

PROJECT: 714020-. TYPE WORK: MAINTENANCE

FUND: 1M

ATLANTA TMA TIP#AR 13IL

LENGTH (miles-/km) 0/0.00

DESCRPT: BRIDGE PAINTING ON INTERSTATES IN COBB COUNTY

LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$491,000 $441-,900
$49,100

STATE TRANSPORTATION IMPROVEMENT PROGRAM

COBlj'COUNTY

PROJECT: 714090- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP # AR 341

'LENGTH (miles I km) 8.58 113.81

DESCRPT: ATMS/I-575 COMMISURVEILLANCE FM 1-75TO SR 92/CHEROKEE

ASSOCIATED PROJECTS: 71409X-

PE:2002 ROW: NONE CST: 2002 FED Share: GAShare:

9/16199
Page 660/275
$5,000
$6,332,000 $5,065,600 $1,266,400

PROJECT: '714130- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ATLANTA TMA TIP # AR 318A

LENGTH (miles I km) 14.2 /22.78' ,

DESCRPT: 1-75 FM KENNEDY PKWY TO WADE GREEN ROAD FOR HOV LANES'

PE:2000 ROW: CST:

$9,999,000 AFTER 2002 AFTER.2002

PROJECT: 714150- TYPE WORK: TURN LANES

FUND: NHS

ATLANTA TMA TIP # CO 308

LENGTH (miles I km)0.2 10.32

DESCRPT: 1-75 AT CHASTAIN RD - SB ANDNB OFF RAMPS

PROJECT: 714160- TYPE WORK: TURN LANES

FUND: NHS"

ATLANTA TMA TIP # CO 309

LENGTH (miles I km) 0.2/0.32

DESCRPT: 1-575 AT BARRETT PARKWAY - SB & NB OFF RAMPS

PROJECT:, 7i 4170- TYPE WORK: TURN LANES

FUND: NHS

ATLANTA TMA TIP # C0310

LENGTH(mileslkm) 0.2/0.32

DESCRPT: 1-575 AT CHASTAIN RD - SB AND NB OFF RAMPS

PROJECT: 714180- TYPE WORK: MAINTENANCE

FUND: NHS

ATLANTA TMA TIP # CO ARBP199

LENGTH(mileslkm) 0/0.00

DESCRPT:CUMBERLAND BOULEVARD OVER 1-285 - ADDITION OF SIDEWALKS

PROJECT: 731850- TYPE WORK: ' TURN LANES'

FUND: STP

ATLANTA TMA TIP# AR 157

LENGTH (mileslkm) 0.1 10.16

DESCRPT: SR 3 TURN LANES FM ELIZABETH CHURCH RD TO THIRD ARMY RD

LUMP SUM PROJECT

PROJECT: 73) 865- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTATMA TIP#C0311

'LENGTH(mileslkm) 0.23/0.37

DESCRPT: SR 92 @ PROCTOR CREEK (LAKE) IN SWACWORTH

PROJECT: 752630- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # C6272

LENGTH(mileslkm) 0.2/0.32

, DESCRPT: CR 4455ICANTON ROAD & RR BR OVER SR 3IUS 41 N OF'MAR1ETTA

PE::2000 ROW: NONE CST: 2002 FED Share: GAShare:

$84,000
$1,754,000 $1,403,200
$350,800

PE:2000 'ROW:NONE
CST: 2002 FED Share:
GAShare:

$20,000
$400,000 $320,000
$80,000

, PE:2000 ROW: NONE CST: 2002 FED Share: GAShare:

$50,000
$990,000 $792,000 $198,000

PE:2000 ROW: NONE CST: 2001 FED Share: GAShare:

$15,000
$300,000 $240,000
$60,000

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$1,030,000 $927,000 $103,000

PE:2000 ROW: 2001 CST: 2002 FEDShare: GA Share:

$20,000 $10,000 $791,000 $632,800 $158,200

PE: 1997 ROW: LOCL' CST: 2001 FED Share: GA Share:

UNDERWAY
' $2,700,000 $2,160,000 $540,000

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9116/99 Page 67 of275

COBBCOUNrY

PROJECT: 752840- TYPE WORK: IMPROVE INTERSECTION FUND: NHS

PE: 1997

UNDERWAY

ATLANTA TMA TIP # CO 280

LENGTH (mileslkm) 1.65/2.66

ROW: LOCL

, DESCRPT: SR 6IUS 278 AT OGLESBY RD & HILL RD EB & WB

CST: 2000

$540,000

FED Share:

$540,000

,.
.,
.:.lo
~.'

PROJECT: 753025- TYPE WORK: ENHANCEMENT

FUND: STP

PE:2000

$5,000

ATLANTA TMA TIP # CO 281

LENGTH (miles I km) 0.55 10.89

ROW: LOCL

,~

DESCRPT: MARlETT A ST/SR 6 BU FM NEW MACLAND RD TO BROWNSVILLE RDIBIKE

CST: 2000

$1,800,000

'"I"

FED Share:

$1,440,000

ASSOCIATED PROJECTS: 771230-

OTH Share:

$360,000

PROJECT: 762450- TYPE WORK: VEHICLE PURCHASE

FUND: STP

ATLANTA TMA TIP # CO AR 273

LENGTH (miles I km) 0/0.00

DESCRPT: REPLACEMENT OF 10 CNG EXPRESS & LOCAL BUSES

PE:NONE ROW: NONE CST:20Ql FED Share:

$3,250,000 $2,600,000

PROJECT: 762470- TYPE WORK: VEHICLE PURCHASE

FUND: CMAQ

ATLANTA TMA TIP # CO 282

LENGTH(mileslkm) 0/0.00

DESCRPT: EXPRESS BUS SERVICE IN 1-75 CORRIDOR (YEAR 1)

OT}] Share:
PE:NONE ROW: NONE CST: 2001 FED Share:

$650,000
$2,200,000 $1,760,000

PROJECT: 762471- TYPE WORK: VEHICLE PURCHASE

FUND: CMAQ

ATLANTA TMA TIP # CO 283

LENGTH (miles I km) 0 10.00

DESCRPT: EXPRESS BUS SERVICE IN 1-20 CORRIDOR (YEAR 1)

OT}] Share:
PE:NONE ROW: NONE CST: 2001 FED Share:

$440,000
$2,200,000 $1,760,000

PROJECT: 762490- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # CO AR BP118

LENGTH (mileslkm) 0/0.00

DESCRPT: CSX RR TRAIL FM SCOBB DR TO PAULDING COUNTY LINE

OTHShare:
PE: 1995 ROW: LOCL CST: 2000 FED Share:

$440,000 UNDERWAY'.
$1,000,000 $800,000

PROJECT: 762492- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # CO ARBP124A

LENGTH (mileslkm) 0/0.00

DESCRPT: PHI LUCILLE CK TRAIL FM SILVER COMET TRAIL TO TOWN SQUAREIPS

OTHShare:
PE: 1995 ROW: LOCL CST: 2000 FED Share:

$200,000 UNDERWAY
$238,000 $190,400

PROJECT: 762494- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # CO ARBP124B

LENGTH (miles Ikm) 0/0.00

DESCRPT: PH 2 LUCILLE CREEK TRAIL FM SILVER COMET TRAIL TO SHIPP RD

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$47,600 UNDERWAY
$560,000 $448,000

PROJECT: 762495- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # COAR BP149

LENGTH (miles Ikm) 0/0.00

DESCRPT: CUMBERLAND PKWY FM CUMBERLAND BLVD TO PACES FERRY

OTHShare:
PE: 1995 ROW: LOCL , CST: 2000 FED Share:

$112,000 UNDERWAY:
$155,000 $124,000

OTHShare: .

$31,000

__________.__. a__ . _. . __ , . ~~~--~~-~-~~~~~~~~~~~~~~----------------~------ - -

~,

a

_

STATE TRANSPORTATION IMPROVEMENT PROGRAM .

9116199

Page 68of275

COBB COUNTY

PROJECT: 762496- .TYPE WORK: ENHANCEMENT

FUND: STP

PE: 2000

ATLANTA TMA TIP # COARBP187A

LENGTH (mileslkm) 0/0.00

ROW:'LOCL

DESCRPT: CUMBERLAND AND TOWN CENTER AREA & TRANSIT LINKAGES - PHASE 1

CST: 2000

FED Share:

$5,000
$1,000,000 $800,000

PROJECT: 762498- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # CO AR BP186

LENGTH (miles I km) 4.517.25

DESCRPT: SR 8IUS 278NETERANS MEMORIAL HWY FM AUSTELL RD TO ALLEN RD

OTH Share:
, PE:2000 ROW: LOCL CST: 2000 FED Share:

$200,000 $5,000
$898,000 $718,400

OTH Share:

PROJECT: 762558- TYPE WORK: ENHANCEMENT

FUND: STP

PE: LOCL

ATLANTA TMA TIP # CO ARBP187C

LENGTH (mileslkm) 0/0.00 " ROW: LOCL

DESCRPT: CUMBERLAND AND TOWN CENTER AREA & TRANSIT LINKAGES - PHASE 3

CST: 2001

FED Share: .

$179,600
$1,000,000 $800,000

OTH Share:

PROJECT: 762560- TYPE WORK: .ENHANCEMENT

FUND: STP

PE: LOCL

ATLANTA TMA TIP # COARBPI87B

LENGTH (mileslkm) 0/0.00

ROW: LOCL

'DESCRPT: CUMBERLAND AND TOWN CENTER AREA & TRANSIT LINKAGES - PHASE 2

CST: 2000

FED Share:

$200,000
$1,000,000 . $800,000

PROJECT: 762564- TYPE WORK: ENHANCEMENT'

. FUND: CMAQ

ATLANTA TMA TIP # CO ARBP188

LENGTH (mileslkm) 0.76/1.22

DESCRPT: WINDY HILL ROAD FROM COBB PARKWAY TO CIRCLE 75 PARKWAY

OTHShare:
PE:LOCL . ROW:LOCL
CST: 2000 FED Share:

$200,000
. $120,000 $96,000

PROJECT: 770269- TYPE WORK: . REPLACE BRIDGE'

FUND: BRIDGE '

ATLANTA TMA TIP # CO 268

LENGTH (miles I km) 0.4/0.64

DESCRPT: CR 2121IHOLLOMAN RD WEST OF AUSTELL @SWEETWATERCRK TRIB

OTH Share:
PE: 1996 ROW: LOCL CST: 2000 FED Share: GA Share:

$24,000 . UNDERWAY
$270,000 $216,000
$54,000

PROJECT: 770922- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # CO AR 177B

LENGTH (mileslkm) 1.2/1.93

DESCRPT: VILLAGE PKWY FM SPRING RD TO WINDY HILL ROAD

PE: 1995 . ROW:NONE
CST: 2000 FED Share:

PROJECT: 770960- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # CO AR 165E

LENGTH (miles I km) 0 10.00

DESCRPT: SIDEWALKS FOR TRANSIT @ TOWN CENTER AREA

OTHShare:
PE: 1995 1l0W:NONE CST: 2000 FED Share:

OTHShare:

PROJECT: 770973- TYPE WORK: ENHANCEMENT

FUND: CMAQ

. PE: 1995

ATLANTA TMA TIP # CO AR 177E

LENGTH (mileS I km) 0 10.00

ROW: NONE

DESCRPT: BICYCLEIPEDESTRlAN FOR BIKE AWARENESS SIGNAGE & PARKING FAC' .

CST: 2000

FED Share:

orn sso

UNDERWAY
$165,000 $132,000 .
$33,000 UNDERWAY
$429,000 $343,200
$85,800 UNDERWAY
$30,000 $24,000
$6,000

4= _"
STATE TRANSPORTATION IMPROVEMENTPROGRAM

COBBCOONTY

PROJECT: 771040- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # CO 271

LENGTH (miles I km) 0.22/0.35

DESCRPT: CR 944/0LD DALLAS ROAD @ NOSES CREEK 4.1 Ml W OF MARIETTA

PE: 1996 ROW: LOCL CST: 2000 FED Share: GAShare:

9116/99
Page 69 of275
UNDERWAY
$629,000 $503,200 $125,800

PROJECT: 771132- TYPE WORK: ENHANCEMENT

FUND: CMAQ

PE:LOCL

ATLANTA TMA TIP # CO AR 177H

LENGTH (miles I km) 0 10.00

ROW: LOCL

'I.'

DESCRPT: MARIETTA MULTIUSE TRAIL - PHASE 2

CST: 2000 FED Share:

$215,000 $172,000

i~t,;

PROJECT: 771133- TYPE WORK: ENHANCEMENT

FUN~: CMAQ

OTR Share: PE:LOCL

$43,000

ATLANTA TMA TIP # CO AR 1771

LENGTH (miles I km) 0 10.00

ROW: LOCL

DESCRPT: POWDER SPRINGS MULTI-USE TRAIL
I

CST: 2000 FED Share:

$189,000 $151,200

OTR Share:

$37,800

It:t

PROJECT: 771134- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # CO AR 177J

LENGTH (miles I km) 0 10.00

PE:LOCL ROW: LOCL

DESCRPT: CCT BIKES - ON-BUS PILOT PROGRAM

CST: 2000

$30,000

I

FED Share:

$24,000

OTHShare:

$6,000

I

PROJECT: 771205- TYPE WORK: MAINTENANCE

FUND: STP

ATLANTA TMA TIP # AR 13tH

LENGTH (miles I km) 0 10.00

DESCRPT: BRIDGE PAINTING fN COBB & CLAYTON COUNTIES177Y205IX

PE:NONE ROW: NONE CST: 2001

$386,000

LUMPSUM PROJECT

I

ASSOCIATED PROJECTS: 77120X- 77Y205-

FED Share: GAShare:

$308,800
$77,20~

PROJECT: 771230- TYPE WORK: ENHANCEMENT

FUND: STP

I

ATLANTA TMA TIP # CO 285

~ENGTH (miles I km)

DESCRPT: STREETSCAPE AND SIDEWALKS fN POWDER SPRINGS

0/0.00

PE:LOCL ROW: LOCL tST:2000

$756,000

FED Share:

$604,800

I

ASSOCIATED PROJECTS: 753025-

OTHShare:

$151,200

PROJECT: 771232- TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

I

ATLANTA TMA TIP # CO AR BP120B

,LENGTH (miles Ikm) 0/0.00

DESCRPT: MULTI-USE TRAIL FM KENNESAW MTN TO CHArrAHOOCHEE TRAIL

ROW: LOCL CST: 2000

$480,000

FED Share:

$384,000

I

OTHShare:

$96,000'

PROJECT: 771236- TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

ATLANTA TMA TIP # CO 286

LENGTH (miles / km) 0/0.00

ROW: LOCL

I.

DESCRPT: GLOVER STEAM LOCOMOTIVE COLLECTION EXHIBIT fN KENNESAW

CST: 2000 FED Share:

$1,000,000 $800,000

I

PROJECT: 771238- TYPE WORK: ENHANCEMENT

FUND: STP ,

OTHShare: PE:LOCL

$200,000

ATLANTA TMA TIP # CO 284

LENGTH (miles / km) 0/0.00

ROW:LOCL

I

DESCRPT: MAIN ST FROM PARK ST TO MORNfNGSIDE DR fN ACWORTH

CST: 2000 FED Share:

$138,000 $110,400

I

OTHShare:

$27,600

-. \. .:

COBB COUNTY

PROJECT: 771341- TYPE WORK: NEW CONSTRUCTION' FliND: STP';'

ATLANTA TMA TIP # CO AR BP201 .

LENGTH(iniles 1 km) 1.14/1.84

DESCRPT: 'DOWNTOWN KENNESAWSTREEfSCAPE

PROJECT: .77Y205- TYPE WORK: '~INrENANCE

FUND: 1M'

ATLANTATMA'TIP# AR BIL

LENG:rH(milis/km) 0/0.00' " .

. DESCRPT: BRIDGE PAINTING IN COBB & CLAYTON COUNTIES17712051X

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 771205-

9116199 Page 70of275

. 'PE:2000 ROW:tOCL CST: 2000 ," FED Share:
OTHShare: PE:NONE'
:; 'ROW:NONE 'CST:200'1 .
FED Share: GA Share:

$70,000
$1,248,000 $998,400
$249,600
$143,000 $128,700
$14,300

PROJECT: -999996- TYPE WORK:' RECSTIREHAB

'FUND:NHS '

ATLANTA:TMA TIP #

'''hENGTH (itlileslkm)

1

-DESCRPT: FUNDING CURRENTLY UNASSIGNED

."

PE:NONE ROW: NONE
'CST:2boi'
FED Share: GA Share:

-, $73,903,000
$59,122,400 $14,780,600

END OFCOBB COUNTY

,.

.'

~',

1'" \;".

l

,

',

I

'. ,"

. ~ -."

.; ~ ."

. ~..

....

".

STATE TRANSPORTATION IMPROVEMENT PROGRAM

COFFEE COUNTY

. PROJECT: 421345- TYPE WORK:. RECSTIREHAB

FUND: STP

LENGTH (miJeslkm) 4.817.73

DESCRPT:' SR 32 FM W/CR 296 EAST TO WEST CITY LIMITS OF DOUGLAS

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 1997 CST: 2002 FED Share: GAShare:

9116199 Page 71of175
UNDERWAY UNDERWAY . $5,521,000 $4,416,800 $1,104,200 ,

PROJECT: 422250- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.1/0.16

DESCRPT: SR 3 llUS 441 @MILL CREEK

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2000 CST: 2000 FED Share: GA Share:

UNDERWAY $10,000
$600,000 $480,000 $120,000

PROJECT: 42Y900- TYPE WORK:' RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: SR 31IUS 441 FM CR 416 TO BROXTON SCL - FOR FED PE; 421900

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422900-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 42Y905- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) . 0/0.00

DESCRPT: SR 31 FM SCLIBROXTON TO NCLIBROXTON - FOR FED PE; 421905

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422905~

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 42Y910- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: SR 31IUS 441 FM NIBROXTON TO SR 107 - FOR FED PE; 421910

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422910-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 431830- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH(mileslkm) 2.45/3.94

DESCRPT: SR 135 FM SR 31IUS 441 EAST TO SR 32 INCLUDING RR SEPARATION

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2002 ROW: CST:

$58,000 AFTER 2002 AFTER 2002

PROJECT: 432115- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.27/0.43

DESCRPT: SR 135 @ SATILLA RIVER APP 6 MI S OF DOUGLAS

PE:2000 ROW: 2002 CST:

$21,000 $10,000 AFTER 2002

PROJECT: 432116- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.22 10.35

DESCRPT: SR 135 @ INDIAN CREEK APP 3.5 MI S OF DOUGLAS

PE:2000 ROW: 2002 .t;ST:

$20,000 $10,000 AFTER 2002

PROJECT: 432117- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.22/0.35

DESCRPT: SR 1351US 221 @ TIGER CREEK APP 6 MI NE OF DOUGLAS

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

- - - - ----------_._---,-~._._--STATE TRAIVSPO'R'TATI(J'N:JMPReJVEMENT PROGRAM

COFFEE COUNTY

PROJECT.: 432118- TYPE WORK:" REPLACE BRIDGE

FUND: BRIDGE

,.

LENGTH (mileslkm) 0.2510.40

.: : DESCRPT: SR 1351US221 @RRPROP. (NO TRACKS)@ SWWEST GREEN CTY LIM"

PE:2000 ROW: 2002 CST:

9116/99 Page 71of275
$20,000 $10,000 AFTER 2002

PROJECT:" 442940- TYPE WORK: RECSTIREHAB

FUND: STP "

LENGTH (miles 1 km) 2.37/3.82

DESCRPT:SR 158 FM 200 IT WEST OF THURSTON PAULK RD TO SR 206 "

'EXIST. LANES: O;Z'PROPOSED LANES: 04

PROJECT: 442971- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles/km) 0.21/0.34

DESCRPT: SR 268/AMBROSE-BROXTON RD @ROSES CRK 1.1 MI W OF BROXTON

PE:2000 ROW: 2002 CST:

$76,000 $1,000,000 AFfER2002

PE:2000 ROW: CST:

$20,000 AFfER2002 AFfER2002

PROJECT:' 450380- TYPE WORK: RECST/REHAB

FUND: STP

"',

LENGTH (miles Ikm) 2.7/4.35

DESCRPT: SR 206IPERIMETER RD FM SR 32 TO SR 31 IN DOUGLAS

EXIST. LANES: 02 PROPOSED LANES: 04

END OF COFFEE COUNTY

PE: 1992 !lOW: 1995 CST: 2000 .
FED Share: GAShare:

UNDERWAY UNDERWAY $3,213,000 $2,570,400
$642,600

L

- - - - - - _ . _ - - - - - - - - - - - - _ ._.._... _ - - _ - : . . . _ - - - - - - - - - - - - - - -

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

Page 730f275

COLQUITT COUNTY

PROJECT: 0000082 TYPE WORK: ENHANCEMENT

FUND: STP

PE: LOCL

LENGTH (miles / km) 0/0.00 DESCRPT: DOWNTOWN MOULTRIE STREETSCAPE COMMERCIAL HISTORIC DISTRICT

ROW: LOCL CST: 2001

FED Share:

$1,250,000 $1,000,000

PROJECT: 431540- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2 /0.32

DESCRPT: SR 37 @ LITTLE CREEK 5 MILES WEST OF JCT SR 111

OTH Sharer
PE: 1995 ROW: 1999 CST: 2000 FED Share: GA Share:

$250,000
UNDERWAY UNDERWAY
$798,000 $638,400 $159,600

PROJECT: 431780- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 4.6317.45

DESCRPT:SR 133 FM SPENCE FIELD TO SR 35 (E.MOULTRIE BYPASS)

EXIST. LANES: 04 PROPOSED LANES: 05

PE:2002 ROW: CST:

$124,000 AFTER 2002 AFTER 2002

PROJECT: 442750- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2 /0.32

DESCRPT: CR 493/FUNSTON-SALE CITY @ LITTLE CREEK APP 1 MI NW FUNSTON

PE: 1997 ROW: LOCL CST: 2002 FED Share: GAShare:

PROJECT: 450570- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: CS 1079/ADEL ROAD@ OKAPILCO CREEK IN EAST MOULTRIE

PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

PROJECT: 471450- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2/0.32

DESCRPT: CR 4/WILBURN MURPHY RD. @ LITTLE CREEK OVERFLOW S OF FUNSTON

PE:2000 ROW: LOCL CST:

UNDERWAY
$283,000 $226,400
$56,600
$48,000
$963,000 $770,400 $192,600
$20,000
AFTER 2002

PROJECT: 471455- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23 /0.37

DESCRPT: CR 186/HAGET STILL ROAD @ OCHLOCKONEE RIVER SE OF DOERUN

OTHShare:
PE:2000 ROW: LOCL CST:

$21,500 $20,000
AFTER 2002

PROJECT: 471460- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2/0.32

DESCRPT: CR 355/0'NEAL ROAD @BRUSHY BRANCH APP 3.7 MI SW OF DOERUN

OTHShare:
PE:2000 ROW:LOCL CST:

$43,800 $20,000
. AFTER 2002

PROJECT: 471465- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2/0.32

DESCRPT: CS 835/SW 13TH AVE @ OCHLOCKONEE RIVER TRIB. IN MOULTRIE

OTHShare:
PE:2000 ROW: LOCL CST:

. $21,500
$20,000 -
AFTER 2002

OTHShare:

$29,500

-------------,-~---,----:---------_._---

STATE TRANSPORTA.TION IMPROVEMENT PROGRAM

9/16/99

Page 74 of275

COLQUITT COUNTY END OF COLQUITT COUNTY

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99

Page 75of275

~. ;. (

COLUMBIA coliNTYM.;-----------------------------

{i .-.

PROJECT: 0000150 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

AUGUSTA TMA TIP #

LENGTH (miles/km) 0/0.00

ROW: LOCL

DESCRPT: EVANS TO LOCKS ROAD MULTI-USE FACILITY & LANDSCAPING

CST: 2000

$1,368,000

FED Share:

$1,094,400

GAShare:

($594,400) _

OTHShare:

$868,000

PROJECT: 210910- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km) 0/0.00

DESCRPT: 1-20/SR 402 SEWAGE HOOKUP FOR REST AREAS #62 AND #63

LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$600,000 $540,000 $60,000

PROJECT: 221805- TYPE WORK: RECSTIREHAB

FUND: STP

AUGUSTA TMA TIP # STP- 12

LENGTH (miles / km) 3 /4.83

DESCRPT: SR 104 FM MP 8.95 S OF CR 515 TO MP 11.95 S OF CR 80

. EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2001 CST:

UNDERWAY $1,337,000 AFTER 2002

PROJECT: 221860- TYPE WORK: RECSTIREHAB

FUND: STP

AUGUSTA TMA TIP # STP3

LENGTH (miles / km) 2.88/4.64

DESCRPT: SR 28IFURYS FERRY RD FM RVRWATCH PKWY/RICHMOND TO N OF CR 98

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22186X-

PE: 1992 ROW: 1999 CST: 2000 FED Share: GA Share:

PROJECT: 231350- TYPE WORK: RECSTIREHAB

FUND: STP

, LENGTH (miles / km) 1.43 /2.30

DESCRPT:SR 47 SB FRM MP 2.45 NEAR KEG CREEK SOUTH TO MP 3.88

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1994 ROW: 2002 . CST:

UNDERWAY UNDERWAY
$7,300,000 $5,840,000 $1,460,000
UNDERWAY $77,000
AFTER 2002

PROJECT: 231440- TYPE WORK: RECSTIREHAB

FUND: STP

AUGUSTA TMA TIP # STP-2

LENGTH (miles / km) 1.4212.29

DESCRPT: SR 232 FM JUST WEST OF CRAWFORD CK TO CR 223 INCL~ BRIDGE

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2002 ROW: CST:

$100,000 AFTER 2002 AFTER 2002

PROJECT: 232305- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR 47 @: KEG CREEK 6.9 MI N OF APPLING

PE:2000 ROW: CST:

$22,000 AFTER 2002 AFTER 2002

PROJECT: 232306- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 223 @ UCHEE CREEK 2.2 MI NW OF GROVETOWN

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 245200- TYPE WORK: RECSTIREHAB

FUND: STP

AUGUSTA TMA TIP # STP-9 .

LENGTH(miles/km) 2.48/3.99

DESCRPT: NORTH BELAIR RD/CR 580 FM SR 104 @ SR 383 TO SR 28/FURY'S FY

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 245205-

PE:2000 ROW: LOCL CST:

$110,000 AFTER 2002

---------, ,--_._.... ---------_ _ ......... ----_._1& --__ _.. _._.__._._-_._.,-

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199

Page 760f275

COLUMBIA COUNTY

PROJECT: 245205- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

AUGUSTA TMA TIP # BRM-4

LENGTH (miles 1 km) 0.42/0.68

DESCRPT: CR 580INORTH BELAIR ROAD @ CSX RAILROAD SW OF SR 28

. EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 245200-

PE:2000 ROW: LOCL CST:

$102,000 AFTER 2002

PROJECT: 250475- TYPE WORK: RECSTIREHAB

FUND: STP .

AUGUSTA TMA TIP # STP-l

LENGTH (miles 1 km) 0.57/0.92

. DESCRPT: CR 145 FM BASTON TO RWATCHIBASTON FM SRI04 TO S OF LAKESHORE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 262410-

PE: 1993 . ROW:LOCL
CST: 2000 FED Share:
GA Share:

UNDERWAY
$4,388,000 $3,510,400
$877,600

PROJECT: 250620- TYPE WORK: NEW CONSTRUCTION FUND: STP

AUGUSTA TMA TIP # STP-I0

LENGTH (miles 1 km) 1.33 12.14

DESCRPT: WILLIAM FEW PARKWAY EXTENSION FM SR 104 TO HARDY-MCMANUS RD

EXIST. LANES: 00 PROPOSED LANES: 02

PE:2000 ROW: LOCL CST:

$5,000 AFTER 2002

PROJECT: 262080- TYPE WORK: RECSTIREHAB

FUND: STP

AUGUSTA TMA' TIP # STP-13

LENGTH (miles 1 km) 2.29/3.69

DESCRPT: SR 104 FM CR 91lHALALI FARM RDTO ElCR 515 (INCL BRIDGES)

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2001 CST:

UNDERWAY $1,995,000 AFTER 2002

PROJECT: 262410- TYPE WORK: RECSTIREHAB

FUND: STP

AUGUSTA TMA TIP # STP-ll

LENGTH (mileslkm) 0.27/0.43

DESCRPT: CR 136IBASTON RD FM S OF LAKESHORE DR TO NORTH OF REVERE RD

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 250475-

PE: 1992 ROW:LOCL 'CST:2000 FED Share: GA Share:

UNDERWAY
$545,000 $436,000 $109,000

PROJECT: 811062- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (mifeslkm) 0/0.00

DESCRPT: UPGRADE 1-20 EB AND WB WEIGH STATIONS INCL SCALE REPLACEMENT

PE: 1995 ROW: 2000 CST: 2000 FED Share: GA Share:

UNDERWAY $40,000
$4,960,000 $4,464,000
$496,000

END OF COLUMBIA COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

COOK COUNTY

PROJECT: 410420- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles 1 km) 0.6 10.97 DESCRPT: 1-75 @ SR 37/ADEL [pM 1500 FT WEST TO 650 FT EAST 1-75]

EXIST. LANES: 02 PROPOSED LANES: 05

PE: 1992 ROW: CST:

9116199 Page 77 of275
UNDERWAY
AFTER2002~
AFTER 2002

PROJECT: 410520- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (mileslkm) 9.3 114.97

DESCRPT: 1-75 FM SR 37 TO CR 246

EXIST. LANES: 04 PROPOSED LANES: 08

PROJECT: 410530- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 10.2 116.47

DESCRPT: 1-75 FM CR 246/COOK TO CR 204 IN TIFT COUNTY/SEE 41053X

EXIST. LANES:"04 PROPOSED LANES: 08

ASSOCIATED PROJECTS: 41053X-

PROJECT: 432085- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.21 10.34

DESCRPT: SR 7IUS 41 @ GIDDENS MILL CREEK NORTH ADEL

PE: 1993 ROW: 2001 CST: 2002 FED Share: GA Share:
PE: 1993 ROW: 2000 CST: 2001 FED Share: GAShare:
PE:2000 ROW: CST:

UNDERWAY $12,000,000 $28,748,000 $22,998,400 $5,749,600
UNDERWAY $4,800,000
$29,544,000 $23,635,200 $5,908,800
$20,000 AFTER 2002 AFTER 2002

PROJECT: 442990- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.27 10.43

DESCRPT: SR 37 @ WITHLACOOCHEE RIVER OIF APP 6 MI E OF ADEL

PE:2000 ROW: CST:

$22,000 AFTER 2002 AFTER 2002

PROJECT: 442991- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.34 10.55

DESCRPT: SR 37 @ WITHLACOOCHEE RIVER AT COOK-BERRIEN CO LINE

ASSOCIATED PROJECTS: 44299X-

END OF COOK COUNTY

PE:2000 ROW: CST:

$42,000 AFTER 2002 AFTER 2002

.

.

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99 Page 78of275

PROJECT: 0000092 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00,

.DESCRPT: NEWNAN TEMPLE/CLARK CORRIDOR IMPROVEMENT & LANDSCAPING

PROJECT: 3i2190- TYPE WORK: SAFETY

FUND: 1M.

.

LENGTH (miles / km) 1.2/1.93

DESCRPT: 1':'85 SAFETY UPGRADES AT 5 LOCATIONS IN COWETAI ONE IN TROUP

ASSOCIATED PROJECTS: 31219X-

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$100,000 $80,000

OTJI Share:
PE:LOCL . ROW: LOCL CST: 2001 FED Share:

$20;000
$500,000 $400,000

OTH Share:
PE: 1998 ROW: NONE CST: 2000 FED Share: GAShare:

$100,000 UNDERWAY
$8,085,000 $7,276,500
$808,500

PROJECT: 332170- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.25/0.40
DESCRPT: SRI4/US 29 AT SR 154

PE: 1995 ROJv.1999 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$209,000 $188,100
$20,900

PROJECT: 332180- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0.25 /0.40

DESCRPT: SR 16 AT SR 54 .

PE: 1996 ROW: LOCL CST:2oot FED Share;

UNDERWAY
$135,000 $135,000

.PROJECT: 333120- TYPE WORK: IMPROVE INTERSECTION FUND: STP

.

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 14IUS 29/27 ALT AT CS 529/MAIN ST-IMPROVE INTERSECTION

LUMP SUM PROJECT

PROJECT: 333176- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 74 @ SOU. RAILROAD (7t8831X) CITY OF SENOIA

PROJECT: 343225- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles/km) 4.8/7.73

DESCRPT: CR 298/CR 549 FM HEARD CO. LINE TO SR 34 - BRING TO STANDARD

PROJECT: 343495- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.2/0.32
DESCRPT: SR 154 AT RAYMOND HILL RD/CR 32 lUST SOUTH OF 1-85 LUMP SUM PROJECT

PE:2000 ROW: LOCL CST: 2001 FED Share: GAShare:
PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:
PE:1999 ROW: LOCL CST: 2002 FED Share: GA Share:
PE: 1999 ROW: LOCL CST:200t FED Share: GA Share:

$5,000
$106,000 $95,400
. $10,600
$20,000 $10,000 $717,000 $573,600 $143,400
UNDERWAY
$4,000,000 $3,200,000
$800,000
UNDERWAY
$136,000 $122,400
$13,600

STATE TRANSPORTATION IMPROVEMENTPROGRAM

COWETA COUNTY

PROJECT: 371306- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.25/0.40

DESCRPT: CR 21lHAPPY VALLEY CIRCLE @ BROWNS CREEK 6 MI N OF NEWNAN

PE: 1995 ROW: LOCL CST: 2002 FED Share: GAShare:

9116199 Page 790f275
UNDERWAY
$361,000 . $288,800
$72,200

PROJECT: 371331- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.12/0.19

DESCRPT: CR 91IMCINTOSH TRAIL @ SOU. RR (7188511) W OF SHARPSBURG

PE: 1999 ROW: LOCL . CST: 2001 FED Share: GAShare:

UNDERWAY
$363,000 $290,400
$72,600

PROJECT: 371332- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.21 10.34

DESCRPT: CR 14/JIM STARR ROAD @ CEDAR CREEK 6 MI N OF NEWNAN

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$377,000 $301,600 $75,400

PROJECT: 371333- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.25/0.40

DESCRPT: CR 201IBETHLEHEM CH. ROAD @ NEW RIVER 3.5 MI S OF NEWNAN

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$321,000 $256,800 $64,200

PROJECT: 371334- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.25 10.40

DESCRPT: CR 227/GRANDMA BRANCH RD. @ NEW RIVER 2.5 M NW OF GRANTVILLE

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$363,000 $290,400 $72,600

PROJECT: 371335- .TYPE WORK: REPLACE)BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.25 10.40

DESCRPT: CR 227/GRANDMA BRANCH RD. @ NEW RIVER TRIB. NW OF GRANTVILLE

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$299,000 $239,200
$59,800

PROJECT: 371336- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (mileslkm) 0.25/0.40

DESCRPT: CR 25/0LD ATLANTA HWY @ WAHOO CREEK N OF NEWNAN

PE: 1999 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
. $419,000 $335,200
$83,800

PROJECT: 371337- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.25 10.40

DESCRPT: CR 14IBRIMER ROAD @ CEDAR CREEK 6 MI N OF NEWNAN

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$438,000 $350,400 $87,600

PROJECT: 371760- TYPE. WORK: ENHANCEMENT

. FUND: STP

LENGTH(mileslkm) . 0/0.00

DESCRPT: CHATTAHOOCHEE-FLINT HERITAGE HWY MARKETING TOOLS

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$105,000 $84,000
$21,000

- . STATE TRANSPORTATION IM~P,R-O- VE-M-E- NT~P-R- OG-R-A- M------9-/16/99
Page80of275

COWETACOUNTY

PROJECT: 371766- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) '0/0.00

DESCRPT: 8 STREETS IN DOWNTOWN NEWNANISTREETSCAPES

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$1,250,000 $1,000,000

END OF COWETA COUNTY

OTHShare:

$250,000

"

-.

STATE TRANSPORTATION IMPROVEMENTPROGRAM

CRA WFORD COUNTY

PROJECT: 363130- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 9.8/15.78

DESCRPT: SR 96 FM E OF FLINT RlV TO FT VALLEY BP/SR 49C & BRlDGIPEACH EXIST. LANE~: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 36313X- 36Y130-

PE: 1992 ROW: 2000 CST: .

9116199 Page 81 of275
UNDERWAY $1,019,000 # AFTER 2002

PROJECT: 36Y130-. TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0 10.00

DESCRPT: SR 96 FM FLINT RlV TO SR 49C1PEACH - FOR FED PE; 363130

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 363130-

PE:2000 ROW: NONE CST: NONE

$1,000

END OF CRAWFORD COUNTY

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _~_

e,

_

STATE TRANSPORTATION IMPROVEMENTPROGRAM

'CRISP COUNTY

PROJECT: 410260- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 6.9/11.11

DESCRPT: 1-75 FM SR 300 TO DOOLY COUNTY LINE & 41R260 FOR HPP RiW $

EXIST. LANES: 04 PROPOSED LANES: 08

ASSOCIATED PROJECTS: 41R260-

:PE: 1986 ROW: 2000 CST: 2001 FED Share: : '.~ GA Share:

9/16/99 Page 81 of175
.UNDERWAY $1,457,000
$19,800,000 $15,840,000
$3,960,000

PROJECT: 41R260- TYPE WORK:' RECSTIREHAB

. FUND: HPP

LENGTH (mileS/ km) 11.9/19.13
DESCRPT: 1-75 FM SR 300 TO DOOL Y COUNTY LINE FOR HPP R/W $ I 410260

EXIST. LANES: 04 PROPOSED LANES: 08

ASSOCIATED PROJECTS: 410260-

PE: 1986 ROW: 2000 CST: NONE

UNDERWAY $10,312,000

PROJECT: 422470- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 7.5 /12.08

DESCRPT: SR 30lUS 280 FM EAST OF FLINT RVR TO CR 415 WEST OF CORDELE

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: CST:

. $170,000 AFTER 2002 AFTER2002 .

PROJECT: 432080- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 0.18/0.29

DESCRPT: SR 30lUS 280fl6TH AVE AT 15TH ST IN CORDELE

PE:2000 ROW: 2001 CST:

$31,000 $201,000 AFTER 2002

PROJECT: 442660- TYPE WORK:' NEW CONSTRUCTION FUND: STP LENGTH (miles / km) 2.8 /4.51
DESCRPT: SR 90fCR 366 RELOCATION FROM SOUTH OF CR 365 TO SR 257

PE:2000 ROW: 2002 CST:

$73,000 $252,000 . AFTER 2002

PROJECT: 450550- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles / km) 0.31 /0.50
DESCRPT: 24th AVENUE GRADE SEPARATION AT NORFOLK SOUTHERN RAILWAY

PE: 1998 . ROW: 2001
CST:

UNDERWAY $700,000
AFTER200i

PROJECT: 471427- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: STREETSCAPES IN THE CITY OF CORDELE

END OF CRISP COUNTY

PE:LOCL ROW:LOCL CST: 2000 FED Share:
OTHShare:

$250,000 $200,000
$50,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

DADE COUNTY

PROJECT: 0000136 TYPE WORK: ENHANCEMENT

FUND: STP

CHATIANOOGA TMA TIP #

LENGTH (mileslkm) 0/0.00

DESCRPT: LOOKOUT MOUNTAIN PARKWAY SCENIC OVERLOOK

PE:LOCL ROW: LOCL CST: 2001 FED Share:

9116/99
Page 83 of275
$125,000 $100,000

PROJECT: 610990- TYPE WORK: REPLACE BRIDGE

FUND: 1M

CHATIANOOGA TMA TIP # IM-97-8

LENGTH (mileslkm) 0/0.00

DESCRPT: 1-24/1-59INTERCHANGE - THREE BRIDGES

OTHShare:
PE: 1995 ROW: NONE CST: 2000 FED Share: GAShare:

$25,000 UNDERWAY
$4,118,000 $3,706,200
$411,800

PROJECT: 611080- TYPE WORK: NEW CONSTRUCTION FUND: NHS . LENGTH(mileslkm) 0/0.00
DESCRPT: 1-59/SR 406- NEW INTERCHANGE AT HICKS HOLLOW ROAD (CR 271)

PE:2000 ROW: CST:

$125,000 AFTER 2002 AFTER 2002

PROJECT: 611310- TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles I km) 1.6/2.58

DESCRPT: I-59 @ 3 LOCjI-24 @ 111-75 @4IWHITFIELD/CATOOSA-61131 0IXIZ

ASSOCIATED PROJECTS: 61131X-

END OFDADE COUNTY

PE: 1998 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$7,475,000 $6,727,500
$747,500

---~---~------------_..:...._----,-----
STATE TRANSPORTATION IMPROVEMENT PROGRAM

9//6/99 Page 84 of275

DAWSONC:;::'O~UN~-T*'y;r----------------------------

PROJECT: 0000202 TYPE WORK: TURN LANES

FUND: STP

LENGTH (miles 1 km) 0.37/0.60

DESCRPT: SR 53 AT BLUE RIDGE OVERLOOKICR 195 & WAR HILL PARK RD/CR218

LUMP SUM PROJECT

PE:2000 ROW: LOCL CST: 2001 FED Share: GAShare:

$5,000
$194,000 $174,600
$19,400

. PROJECT: 132790- TYPE WORK: NEW CONSTRUCTION FUND: APD LENGTH (miles 1 km) 0.5 10.81
DESCRPT: SR 400 INTERCHANGE AT SR 53

PE: 1998 ROW: 2002 CST: .

UNDERWAY $20,000,000 AFTER 2002

PROJECT: 142070-
"

TYPE WORK: REPLACE BRIDGE

FUND: STP

LENGTH (mileslkm) 0.4/0.64

DESCRPT: SR 136 AT SHOAL CREEK AND BURT CREEK

END OF DAWSON COUNTY

PE: 1996 ROW: 1997 CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY
$546,000 $436,800 $109,200

STATE TRANSPORTATION IMPROVEMENT PROGRAM ~---=~ 9116/99

DEKALB COUNTY

Page 850f275
..

PROJECT: 713250- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANTA TMA TIP # DKAR 183

LENGTH (mileslkm) 1/1.61

DESCRPT: 1-285 SOUTH AUXILLARY LN FM SR 8 TO STN MTN FWY & FWY BRIDGE

ASSOCIATED PROJECTS: 713320-

PE: 1995 ROW: NONE CST: 2001 FED Share: GAShare:

UNDERWAY
$2,543,000 $2,288,700
$254,300

PROJECT: 713280- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANTA TMA TIP # DK AR 205

LENGTH (miles 1km) 0 10.00

DESCRPT: 1-285 @ SR IO/MEMORIAL DR & RELOCATE GEORGE LUTHER DR

. PE: 1997 ROW: 2000 CST: 2002 FED Share: GAShare:

UNDERWAY $17,487,000 $11,116,000 $10,004,400 $1,111,600

PROJECT: 713290- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANT A TMA TIP # DK AR 206

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: 1-285 @SR 155/FLAT SHOALS ROAD

PE: 1999 ROW: 2001 CST:

UNDERWAY $1,150,000 AFTER 2002

PROJECT: 713300- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANT A TMA TIP # DK AR 207

LENGTH (miles 1 km) 0/0.00

DESCRPT: 1-285 @ BOULDERCREST ROAD

PE: 1998 ROW: 2001 CSn2002 FED Share: GAShare:

UNDERWAY $1,150,000 $18,400,000 $16,560,000 $1,840,000

PROJECT: 713373- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTATMA TIP#AR281

LENGTH (mileslkm) 12.5/20.11

DESCRPT: ATMS/I-285 SURVEIL FM 1-75/CLAYTON NE THRU FULTN TO 1-201DEK

ASSOCIATED PROJECTS: 713372-

PE:2000 ROW: NONE CST: 2000 FED Share: GAShare:

$5,000
$6,300,000 $5,040,900 $1,260,000

PROJECT: 713410- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # OK AK 215A

LENGTH (miles 1km) 13 120.85

DESCRPT: ATMS/ 1-285 COMMUNICATION/SURVEIL FM 1-20 E TO 1-85 N 1& Y

ASSOCIATED PROJECTS: 71Y410-

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$2,462,000 $1,969,600
$492,400

PROJECT: 714000- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANTA TMA TIP#DKAR219

LENGTH(mileslkm) 0.5/0.81

DESCRPT: 1-285 @ ASHFORD DUNWOODY ROAD

ASSOCIATED PROJECTS: 71YOOO-

PE:NONE ROW: 2001 CST:

$7,000,000 AFTER 2002

PROJECT: 714030- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ATLANTA TMA TIP # OK AR 222

LENGTH (miles 1 km) 0/0.00

DESCRPT: 1-285 NOISE BARRIERS FM NORTHLAKE PKWY TO HENDERSON MILL RD

PE: 1999 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$4,480,000 $2,240,000 $2,240,000

PROJECT: 714085- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP#AR305

LENGTH (mileslkm) 14.9/24.04

DESCRPT: ATMS/I-20 COMMISURVEILLANCE FM 1-285 TO SRI38/SR20IROCKDALE

ASSOCIATED PROJECTS: 714082-

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$12,968,000 $10,374,400 $2,593,600

STATE,TRANSPORTATION IMPROVEMENT PROGRAM

DEKALB COUNTY ,

PROJECT: 714110- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ATLANTA TMA TIP # AR 303

LENGTH (miles / km) 3.11/5.01

DESCRPT: 1-20 NOISE BARRIERS FM FLAT SHOALS ROAD TO COLUMBIA DR (N&S)

PE:200.o . ROW: NONE CST:

9/16/99 Page 86 0/275
$30,000 AFTER 2002

PROJECT: 71Y41O- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # OK AR 215B

LENGTH (miles / km) 13/20.85

DESCRPT: ATMS/ 1-285 COMMISURVEIL FM 1-20 E. TO 1-85 N.ISEE713410

ASSOCIATED PROJECTS: 713410-

PE:NONE ROW: NONE . CST:2002 FED Share: GA Share:

$7,583,QOO $6,066,400 $1,516,600

PROJECT: 721405- TYPE WORK:' REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # OK 022B

LENGTH (miles / km) 0.02/0.03

. DESCRPT: ASHFORD-DUNWOODY RD @ NANCY CRK

PE: 1992 ' ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$1,188,000 $950,400 $237,600.

PROJECT: 722145- TYPE WORK:' SAFETY

FUND: NHS

ATLANTA TMA TIP # AR 306

LENGTH (miles / km) 5.52/8.89

. DESCRPT: ATMS/SRI41 COMMISURVEIL FM 1-285 TO SPALDING DRIGWINNETI

ASSOCIATED PROJECTS: 72214X-

PE:NONE ROW: NONE CST: 2002 FED Share: GA Share:

$5,032,000 $4,025,600 $1,006,400

PROJECT: 731500- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # OK 254

LENGTH(miles/km) 0/0.00

DESCRPT: SR 42lBRIARCLIFF ROAD AT SHERIDAN ROAD/CR 139

PE: 1999 ROW:LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$703,000 $632,700
$70,300

PROJECT: 731770.. TYPE WORK: ENHANCEMENT

FUND: HPP

ATLANTA TMA TIP # OK 266

'LENGTH (miles / km) 8.28/13.33

DESCRPT: BUFORD HIGHWAY/SR l3IUS 23 ARTERIAt ENHANCEMENTS , ,

PROJECT: 751320- . TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # OK 101

LENGTH (miles/km) 0.28/0.45'

DESCRPT: CR 5189IROCKBRIDGE RD @ SNAPFINGER CREEK

PE: 1999 ROW: NONE CST: 2001 FED Share:
OTHShare:
PE: 1991 . ' ROW:LOCL
CST: 2000 FED Share:
GAShare:

UNDERWAY
$1,312,000 $1,049,600
$262,400 UNDERWAY
$1,150,000 $920,000 $230,000

PROJECT: 752880- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # AT 164

LENGTH(miles/km) 0.42/0.68

'DESCRPT: SR 154lMEMORIAL DRIVE AT SR ISS/CANDLER ROAD

PE: 1997 ROW: 2000 CST: 2000' FED Share: GAShare:

UNDERWAY $2,576,000 ' $225,000 $180,000 $45,000

PROJECT: 752900- TYPE WORK: REPLACE BRIDGE

FUND: STP'

ATLANTA TMA TIP # OK 250

LENGTH(miles/km) 0.2/0.32

DESCRPT: SR 155/CANDLER RD AT SHOAL CKlREPL CLVT&REMOVE PED BRIDGES

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1996 ROW: 2000 CST: 2002 FED Share: GAShare:

UNDERWAY $744,000 $670,000 $536,000 $134,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

DEKALBCOUNTY

PROJECT: 752910- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # DK 252

LENGTH (miles 1 km) 0.2/0.32.

DESCRPT: SR 155/CLAIRMONT ROAD @PONCE DE LEON PLACE - DRAINAGE PIPE

PE: 1999 ROW: 2000 CST: 2000 FED Share: GAShare:

9116199 Page 87 of275
UNDERWAY $10,000
$140,000 $112,000 $28,000

PROJECT: 752930- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # DK 260

LENGTH (mileslkm) 0.2/0.32

DESCRPT: BOULDERCREST ROAD AT THE SOUTH RIVER SOUTH OF 1-285

PE: 1999 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$1,528,000 $1,222,400
$305,600

It'..ut~~,..

PROJECT: 752940- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTATMA TIP # DK258

LENGTH(mileslkm) 0.2/0.32

PE: 1999 ROW: LOCL

UNDERWAY

DESCRPT: CR 5194/FLAT SHOALS ROAD @ DOLITTLE CREEK JUST SOUTH OF 1-20

CST: 2002

$633,000

FED Share:

$506,400

GA Share:

$126,600

PROJECT: 752950- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # DK 259

LENGTH (miles 1 km) 0.2 I 10.34

DESCRPT: CR 3271lMERCER UNIV. DRIVE @ N FORK PEACHTREE CREEK

PE: 1999 ROW: LOCL CST: 2002 FED Share: GA Share:

UNDERWAY
$404,000 $323,200 $80,800

PROJECT: 753030- TYPE WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # DK 261

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: PANOLA RD/CR 5150 AT ROCK SPRINGS RD

PROJECT: 753035- TYPE WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # DK246

LENGTH(mileslkm) 0.2/0.32

DESCRPT: EAST PONCE DE LEON/CR 5151 AT HAMBRICK RD

PROJECT: 753045- TYPE WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # DK '239

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: TILLY MILL RD/CR 1698 AT NORTH PEACHTREEIPEELER RD

PROJECT: 753 I 70- TYPE WORK: ENHANCEMENT

FUND: HPP

ATLANTA TMA TIP # DK 268

LENGTH (miles Ikm) 0/0.00

DESCRPT: SR IS5/CANDLER ROAD MAJOR ARTERIAL ENHANCEMENTS

PROJECT: 753200- TYPE WORK: ENHANCEMENT

FUND: HPP

ATLANTA TMA TIP#DK267

LENGTH(mileslkm) 0/0.00

DESCRPT: SR 154/SR 1OIMEMORIAL DRIVE MAJOR ARTERIAL ENHANCEMENTS

PE:2000 ROW: LOCL . CST:2000 FED Share:
OTHShare: PE:2000
ROW: LOCL CST: 2000 FED Share:
ornsso
PE:2000 ROW: LOCL CST: 2000 FED Share:
OTHShare: PE: 1999
ROW: LOCL CST: 2001 FED Share:
OTHShare: PE: 1999
ROW: LOCL CST: 2001 FED Share:
OTHShare:

$5,000
$450,000 $360,000
$90,000 $5,000
$900,000 $720,000
$180,000 $5,000
$600,000 $480,000
$120,000 UNDERWAY
$10,146,000 $8,116,800
$2,029,200 UNDERWAY
$10,885,000 $8,708,000
$2,177,000 .

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

DEKALB'COUNIT

PROJECT: 753265- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # DK273

LENGTH (miles/km)

DESCRPT: EAST PONCE DE LEON AVE @ MCCLENDON DR

0/0.00

PE:2000 ROW: LOCL . CST:

9/16199 Page 88 of275
$10,000 AFTER 2002

, PROJECT: 753290- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # DK 274

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 236/LAVISTA RD AT BRIARCLIFF RD/CR 1532

OTHShare:
PE:2000 ROW: LOCL CST:

$15,000 $15,000
AFTER~002

PROJECT: 762500- TYPE WORK: ENHANCEMENT

FUND: STP

. ATLANTA TMA TIP # DK AR BP022

LENGTH (miles / km) 0/0.00

.' DESCRPT: TILLY MILL RD FM MT VERNON TO PEELER RD

OTHShare:
PE: 1999 ROW: LOCL CST: 2000 FED Share:

$15,000 UNDERWAY
$880,000 $704,000

PROJECT: 762502- TYPE WORK:' ENHANCEMENT

' FUND: STP

ATLANTATMA TIP#DKARBP021

LENGTH (miles/km) 0/0.00

DESCRPT: SR 260/GLENWOOD AVE FM 1-20 TO EAST LAKE RD

OTHShare:
PE: 1999 ROW: LOCL CST: 2000 FED Share:

$176,000 UNDERWAY
$510,000 $408,000

PROJECT: 762611- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # DK AR BP038

LENGTH (miles / km) 2.5 /4.03

DESCRPT: PERIMETER AREA AROUND DUNWOODY MARTA STATION

OTHShare:
PE:LOCL' ROW: LOCL CST: 2000 FED Share:

$102,000
. $500,000 $400,000

OTH Share:

PROJECT: 770911- TYPE WORK: ENHANCEMENT

FUND: CMAQ

PE:'1995

ATLANTA TMA TIP # DK AR 165CDE

LENGTH (miles / km) 3.99/6.42

ROW: NONE

DESCRPT: SIDEWALKS AT BUFORD HWY- NEW PEACHTREE RD. & SHALLOWFORD RD. . CST: 2000

FED Share:

$100,000 UNDERWAY
$316,000 $252,800

PROJECT: 770912- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # DKAR 165AB

LENGTH (miles/km) 1.21/1.95

DESCRPT: SIDEWALKS AT BRIARWOOD ROAD & DRESDEN ROAD

OTHShare:
PE: 1995 ROW: NONE CST: 2000 FED Share:

$63,200 UNDERWAY
$96,000 $76,800

PROJECT: 771122- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTATMA TIP # DKAR 177A

LENGTH (miles/km) 0/0.00

DESCRPT: SIDEWALKS ON BUFORD HlGHWAY FM CHAMBLEETUCKER TO 1-285

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$19,200
$113,000 $90,400

PROJECT: 771170- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # DK 255

LENGTH (miles / km) 0.21 /0.34

DESCRPT: CR 1644IBRIARWOOD ROAD @ NORTH FORK P'TREE CREEK N OF 1-85

OTHShare:
PE: 1999 ROW: LOCL CST: 2002 FED Share: GAShare:

$22,600 UNDERWAY
$350,000 $280,000
$70,000

I

--------_._--------, ,-----_.,--_.---------,---

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199

Page 89 of2"75

I

DEKALB COUNTY

PROJECT: 771180- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1999

UNDERWAY

ATLANTA TMA TIP # DK 256

LENGTH (miles I km) 0.19 10.31

ROW: LOCL

.~'I.'~,.

DESCRPT: CR 164IELLINGWOOD DRIVE @ CONLEY CREEK NEAR PANTHERSVILLE RD

CST: 2002

FED Share:

$187,000 $149,600

GAShare:

$37,400

PROJECT: 771190- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # DK 257

LENGTH (miles I km) 0.21 10.34

DESCRPT: CR 1563IFLOWERS ROAD @ NORTH FORK P'TREE CREEK NEAR MERCER U

PE: 1999 ROW: LOCL CST: 2002 FED Share: GA Share:

UNDERWAY
$429,000 $343,200 $85,800

PROJECT: 771220- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # DK 263

LENGTH (miles I km) 0.5/0.81

DESCRPT: CITY OF AVONDALE ESTATES STREETSCAPE VARIOUS LOCATIONS

PE:LOCL ROW: LOCL CST: 2000 FED Share:

OTHShare:

PROJECT: 771222- TYPE WORK: ENHANCEMENT

FUND: STP

PE: LOCL

ATLANTATMA TIP#DK262

LENGTH (mileslkm) 1.89/3.04

ROJv." LOCL

DESCRPT: CHAMBLEE-DUNWOODY RD FROM NEW P'TREE RD TO BUFORD HWY/SR 13

CST: 2000

FED Share:

PROJECT: 771224- TYPE WORK: ENHANCEMENT

. FUND: STP

ATLANTA TMA TIP # DK-264

LENGTH (miles I km) 0 10.00

DESCRPT: DOWNTOWN DECATUR STREETSCAPES & SIDEWALKS PHASE II

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

PROJECT: 771244- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT 166

LENGTH(mileslkm) 0/0.00

DESCRPT: MORELAND AVE FM LITTLE FIVE POINTS TO PONCE DE LEON AVE

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

PROJECT: 771246- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT ARBP072

LENGTH (mileslkm) 0/0.00

DESCRPT: BOULEVARD DRIVE STREETSCAPE AND ON-STREJ:;TBIKE ROUTE

OTHShaTe:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

PROJECT: 999994- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP #

LENGTH (miles I km)

I

DESCRPT: FUNDING CURRENTLY UNASSIGNED

OTHShare:
PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$399,000 $319,200 $79,800
$1,250,000 $1,000,000
$250,000
$1,250,000 $1,000,000
$250,000
$250,000 $200,000 $50,000
$375,000 $300,000 $75,000
$88,212,000 $70,569,600 $17,642,400

END OFDEKALB COUNTY

STATE TRANSPORTATION IMPROVEMENTPROGRAM

DODGE COUNTY

PIWJECT: 222410-

TYPE WORK: RECSTIREHABFUND: STATE

.

LENGTH (miles1 km) 12.6120.30

DESCRPT: SR 87/US 23 FM CR 3321EASTMAN TO SR 257/FRAZIER (EXECPTION)

. EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 231930- TYPE WORK: RECSTIREHAB

FUND: STP

. LENGTH(mileslkm) 2.1/3.38

DESCRPT: SR 30/uS 280 FM WEST CL OF MILAN TO EAST CL

EXIST. LANES: 02 PROPOSED LANES: 04

PE:1996 ROW: 2000 . CST: 2002
GAShare:
PE:2000 ROW: LOCL CST:

9116199 Page 90 of275
UNDERWAY $4,084,000 $11,081,000
$11,081,,000
$32,000
AFTER 2002

PROJECT: 245355 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE.

LENGTH (miles1 km) 0.23/0.37

DESCRPT: SR 87/EASTMAN-RHINE HWY @ SUGAR CREEK 1.8 MI S OF EASTMAN

, PE:2000
ROW: -CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 271306- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles 1 km) 0/0.00

DESCRPT: DOWNTOWN EASTMAN LANDSCAPING AND STREETSCAPE

END OFDODGE COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHSllare:

$632,000 $505,600
$126,400



I, . ;

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99

i"q
. ::-

DOOLYCOUNTY

PROJECT: 311665- TYPE WORK: REHAB. BRIDGE

FUND: 1M

I

LENGTH (miles / km) 0.2/0.32
DESCRPT: 1-75 WIDEN BRIDGE &. RAMPS @ SR 27

Page 91 of275

PE: 1997 ROW: 2001 CST:

UNDERWAY $629,000
AFTER 2002

PROJECT: 333190- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 27 @ PENNAHATCHEE CREEK W EDGE OF VIENNA

PE:2000 ROW: . CST:

$20,000 AFTER 2002 AFTER 2002

END OFDOOLYCOUNTY

._-

-

--..S;T. AT.E.T. RA-N- SP-O- RT-A- TI- ON-I- M- PR-O-V~ EM-E-N- T P-R- O

G-R-A- M--

-

-

----_
9/16199

.

Page 92 0[275

D"iJUGHERTY COUNTY

PROJECT: 422540- TYPE WORK: RECSTIREHAB

FUND: NHS

ALBANY TIP # NHS-I

LENGTH (miles / km) 0.25 /0.40

DESCRPT: SR 3ILIBERTY EXWY @ JEFFERSON ST/SR 91 EB RAMP

EXIST. LANES: 00 PROPOSED LANES: 04

PE:2000 ROW: NONE CST: 2002 FED Share: GAShare:

$10,000
$198,000 $158,400
$39,600

. PROJECT: 422550- TYPE WORK: RECSTIREHAB

. FUND: NHS

ALBANY TIP # NHS-2

LENGTH (miles'/ km) 0.5/0.81

DESCRPT: SR 3ILIBERTY EXWY @ SR 91 WB ON & NJEFFERSON OFF RAMPS/ALB

EXIST. LANES: 01 PROPOSED LANES: 04

PE:2000 ROW: NONE CST: 2002 FED Share: GAShare:

$40,000
$1,980,0.00 $1,584,000
$396,000

PROJECT: 422560- .TYPE WORK: RECSTIREHAB

FUND: NHS

ALBANY TIP # NHS-4

LENGTH (miles/ km) 0,2/0.32

DESCRPT: SR 3ILIBERTY PKWY @ CLARK AVE SB EXIT RAMP/ALBANY

EXIST. LANES: 01 PROPOSED LANES: 04

. PE:2000 ROW: NONE CST: 2002 FED Share: GA Share:

$10,000
$234,000 $187,200
$46;800

PROJECT: 422570- TYPE WORK: RECSTIREHAB

FUND: NHS

ALBANY TIP # NHS-3

LENGTH (miles / km) 0.5 /0.81

DESCRPT: SR 3ILIBERTY EXWY@NB& SB RAMPS AT SR 133/MOULTRlE RD

PE:2000 ROW: NONE CST: 2002 FED Share: GAShare:

$13,000
$650,000 $520,000 $130,000

PROJECT: 431455- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ALBANY TIP # B-95-3

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 62 @ COOLEEWAHEE CREEK APP5 Ml W OF JCf SR 91

PE: 1997 ROW: 1999 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$650,000 $520,000 $130,000

PROJECT: 431740- TYPE WORK: RECSTIREHAB

FUND: STP

ALBANY TIP # HIR-99-6

LENGTH (miles / km) 1.312.09

DESCRPT: SLAPPEY BLVD/SR 62 & SR 520BU FM COLQUITT AVE N TO TIFT AVE

EXIST. LANES: 04 PROPOSED LANES: 06

PE:2002 ROW: CST:

$34,000 AFTER 2002 AFTER 2002

PROJECT: 450495- TYPE WORK: RECSTIREHAB

FUND: STP

ALBANY TIP # HIR-95-5

LENGTH (miles / km) 0.62/1.00

DESCRPT: SR 234/GILLIONVILLE RD FM LOCKETT STATION RD TO BEATTIE RD

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 450540- TYPE WORK: RECSTIREHAB

FUND: STP

ALBANY TIP # HIR-95~8

LENGTH (miles / km) 0.68/1.09

DESCRPT: CLARK AVE EXT FM SWIFT AVE TO RIVERSIDE DR & NEW BRIDGE

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 471430- TYPE WORK: ENHANCEMENT

FUND: STP

ALBANY TIP# TEA-I

LENGTH (mileS/km) 4.5/7.25

DESCRPT: MULTI-USE TRAIL IN THE qTY OF ALBANY

PE: 1996 ROW: LOCL CST: 2000 FED Share: GAShare:
PE: 1997 ROW: LOCL CST: 2002 FED Share: GA Share: OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

UNDERWAY
$1,956,000 $1,564,800
$391,200
UNDERWAY
$8,000,000 $6,400,000 $1,500,000
$100,000
$512,000 $409,600
$102,400

STATE TRANSPORTATIONiMPROVEMENTPROGRAM

DOUGHERTY COUNTY

.~ - .

PROJECT: DNR254- TYPE WORK: NEW CONSTRUCTION FUND: REC TRAILS

ALBANY TIP # DNR-l

LENGTH (miles / km) 0 /0.00

DESCRPT: DNR REC TRAILS PROG -FLINT RIVER GREENWAY OXFORD ENVIR REACH

PE:NONE ROW: NONE CST: 2000 FED Share:

9/16/99 Page 93 of275
$125,000 $100,000

END OF DOUGHERTY COUNTY,

OTR Share:

$25,000

stATE TRANSPORTATioNIMPROVEME-"N--T-P-'R-O-G-'RA~-M---'~---
9/16199 Page 94 of275

DOUGLAS COUNTY

PROJECT: 712930- TYPE WORK: RECSTIREHAB'

FUND: 1M'

ATLANTA TMA TIP # DO AR 208

LENGTH (miles / km) 0.47/0.76

DESCRPT: SR 92/FAIRBURN RD & APPROACHES OVER 1-20 IN DOUGLASVILLE

PE: 1997
ROW: 2000
CST:"

UNDERWAY $1,305,000 AFTER 2002

PROJECT: 731790- TYPE WORK: SIGNALS

FUND: STP ...

ATLANTA TMA TIP # DO 259

LENGTH (miles / km) 0.2/0.32

DESCRPT: BILL ARP RD/SR 5 AT STEWART PARKWAY

PROJECT: 731800- TYPE WORK: SIGNALS

FUND: STP

ATLANTA TMA TIP # DO 257

LENGTH (miles / km) 0.2/0.32

DESCRPT: BILL ARP RD/SR 5 AT WESLEY POND RD

PROJECT: 731810- TYPE WORK: SIGNALS

FUND: STP

ATLANTA TMA TIP # DO 264

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: DALLAS HWY/SR 92 AT UPSHAW MILL RD

PROJECT: 731815- TYPE WORK: SIGNALS.

FUND:. STP

ATLANTA TMA TIP # 00 260

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: DALLAS HWY/ SR 92 AT FORREST AVE

PROJECT: 731820- TYPE WORK: SIGNALS

FUND: STP

ATLANTA TMA TIP # DO 261

LENGTH (miles 1 km) 0.2/0.32

.DESCRPT: DOUGLAS BLVD AT BILL ARP RD / SR 5

PROJECT: 731825- TYPE. WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # 00 265

LENGTH(miles 1 km) 0.2/0.32

DESCRPT: SR 5 AT SR 92 REALIGN AND IMPROVE SIGNALIZATION

PROJECT: 753090- TYPE WORK: SIGNALS

FUND: STP

ATLANTA TMA TIP # DO 267

LENGTH (mileslkm) 0 zo.oo

DESCRPT: DOUGLAS BOULEVARD AT STEWART PARKWAY

PROJECT: 753095- TYPE.WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # DO 258

. LENGTH (miles 1 km) 0.2 10.32

DESCRPT: LEE RD/CR 817 AT EAST COUNTY LINE RD & SIDEWALKS

PE;LOCL' ROW: LOCL CST: 2000 FED Share:
OTR Share: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTRShare: PE:LOCL
ROW: LOCL CST: 2001 FED Share:
OTHShare: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:LOCL
ROW: LOCL CST: 2000 . FEDShare:
OTHShare: PE:2000
ROW:LOCL CST: 2000 FED Share:
OTHShare: PE:LOCL
ROW: LOCL CST: 2001 FED Share:
OTHShare: PE:20oo .
ROW: LOCL CST: 2000 . FEDShare:
OTHShare:

$76,000 $60,800 $15,200
$142,000 $113,600
$28,400
$60,000 $48,000 $12,000
$118,000 $94,400 $23,600
$138,000 $110,400
$27,600 $5,000 $225,000 $180,000 $45,000
$60,000 $48,000 $12,000 $5,000 $90,000 S72,OOO S18,000
".

STATE TRANSPORTATION IMPROVEMENT PROGRAM

DOUGLAS COUNTY

PROJECT: 753100- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # DO 262

LENGTH (miles / km) 0.2 /0.32

DESCRPT: CENTRAL CHURCH RD/CR 173 AT KINGS HIGHWAY/CR 810

PE:2000 ROW: LOCL CST: 2000 FED Share:

9/16/99 Page 95 of275
$8,000 $100,000
$80,000

PROJECT: 753105- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # DO 268

LENGTH (miles / km) 0.2 /0.32

DESCRPT: CENTRAL CHURCH RD AT YANCEY RD/COURSEY LAKE RDIREALIGN

OTHShare:
PE:2000 ROW: LOCL CST: 2001 FED Share:

$20,000 $5,000
$90,0.00 $72,000

PROJECT: 753110- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # DO 266

LENGTH (miles / km) 0.2/0.32

DESCRPT: CHAPEL HILL RD/CR 812 AT WEST CHAPEL HILL RD/CR 145

OTHShare:
PE:2000 ROW:LOCL CST: 2001 FED Share:

$18,000 $5,000
$90,000 $72,000

PROJECT: 753115- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # DO 263

LENGTH (miles / km) 0.2/0.32

,DESCRPT: LEE RD/CR 817 AT SOUTH SWEETWATER RD & SIDEWALKS

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$18,000 $8,000
$120,000 $96,000

OTHShare:

$24,000

I~,

PROJECT: 753270- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # DO AR BP071

LENGTH (miles / km) 1.512.42

PE:LOCL ROW: LOCL

DESCRPT: SWEETWATER CK PATH ALONG BLAIRS BR RD FM HOSPITAL TO SR 6

CST:'2000

$426,000

FED Share:

$340,800

PROJECT: 753295- TYPE WORK: REPLACE BRIDGE

FUND: STP

ATLANTA TMA TIP # DO 275

LENGTH (miles/ km) 0.42/0.68,

DESCRPT: ANNEEWAKEE RD/CR 815 BRIDGE @ANNEEWAKEECREEK

OTlf Share:
PE:2000 ROW: 2000 CST: 2000 FED Share:

$85,200
$20,000 $20,000 $1,000,000 $800,000

PROJECT: 762510- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # DO ARBP048A

LENGTH (miles/km) 0/0.00

DESCRPT: SIDEWALKS: EAST COUNTY LINE RD FM MACK RD TO LEE ROAD

OTHShare:
PE: 1995 ROW:LOCL CST: 2001 FED Share:

$200,000 UNDERWAY
$163,000 $130,400

PROJECT: 762512- TYPE WORK: ENHANCEMENT

' FUND: CMAQ

ATLANTA TMA TIP # DO AR BP048B

LENGTH (miles / km) 0/0.00

DESCRPT: LEE RD FM EAST COUNTY LINE RD TO CEDAR TERRACE RD

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$32,600 UNDERWAY
$105,000 $84,000 -

PROJECT: 762514- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # DO AR BP059

LENGTH (miles / km) 0/0.00

DESCRPT: NORTHSIDE CONN FM FORREST AVE TO BROWN ST

OTHShare:
PE:2000 ROW:LOCL CST: 2000 FED Share:

$21,000 . $5,000
$242,000 $193,600

OTHShare:

$48,400

"

40*_

STATE TRANSPORTATION IMPROVEMENT PROGRAM

DOUGLAS couNiY

PROJECT: 762612- TYPE WORK: 'NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # DO AR BP068

LENGTH (miles / km) 2.12/3.41

DESCRPT: W STEW ART MILL & STEWART MILL FM CHAPEL HILL RD TO SR 5

PE:LOCL ROW: LOCL CST: 2000 FED Share:

_
9/16199 Page 96 of275
$233,000 $186,400

PROJECT: 762634- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # DO 276

LENGTH (miles / km) 1.412.25

DESCRPT: PRESTLEY MILL RD/CR 142 FM 1-20 TO SLATER RD

OTHShare:
PE:2000 ROW: 2000 CST: 2000 FED Share:

$46,600
$70,000 $165,000 $1,359,000 $1,087,200

PROJECT: 762636- TYPE WORK:' RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # DO 279

LENGTH (miles/km) 0.2/0.32

DESCRPT: STEWARTS MILLICR 281 @ W STEWARTS MILUCR175 & YANCY RD/C6~9

OTHShare:
PE:2000 ROW: 2000 CST: 2000 FED Share:

$271,800
$5,000 $20,000 $150,000 $120,000

PROJECT: 762638- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # DO 278

LENGTH (miles / km) 0.2 /0.32

DESCRPT: STEWARTS MILL RD/CR 281 @ REYNOLDS RD/CR 171 & ANNEEWAKEE CK

OTHShare:
PE:2000 ROW: 2000 CST: 2000 FED Share:

$30,000
$5,000 $20,000 $1,000,000 $800,000

PROJECT: 770163- TYPE WORK: REPLACE BRIDGE

FUND: STP

ATLANTA TMA TIP # DO 274

LENGTH (miles / km) 0.2/0.32

DESCRPT: POST RD/CR 808 BRIDGE @ DOG RIVER

. OTHShare:
PE:2000 ROW: 2000 . CST:2000 FED Share:

$200,000
$20,000 $20,000 $1,000,000 $800,000

PROJECT: 710975- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # DO AR 177A

LENGTH (miles / km) 0/0.00

DESCRPT: BICYCLEIPEDESTRIAN FAC'S FOR SIGNAGE- RACKS & STRIPING

OTHShare:
PE: 1995 ROW: NONE CST: 2000 FED Share:

$200,000 UNDERWAY
$31,000 $24,800

'PROJECT: 771035- TYPE WORK: 'OTHER

FUND: CMAQ

ATLANTA TMA TIP # DO AR211

LENGTH(miles/km) .0/0.00

DESCRPT: ALTERNATIVE FUEL STATION-I-20 AT CHAPEL HILL ROAD

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 . FED Share: '

$6,200
$250,000 $200,000

PROJECT: 771123- TYPE WORK: ENHANCEMENT

FUND: CMAQ,

ATLANTA TMA TIP # DO AR 171C

LENGTH (miles / km) 0/0.00

DESCRPT: SIDEWALKS ON COUNTY LINE ROAD - PHASE 1

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$50,000
$116,000 $92,800

PROJECT: 771124- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # DO AR 177D

LENGTH (miles / km) 0/0.00

DESCRPT: SIDEWALKS IN DOUGLASVILLE

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$23,200
$84,000 $67,200

OTHShare:

$16,800
,.

STATE TRANSPORTATION IMPROVEMENT PROGRAM

DOUGLAS COUNTY

PROJECT: 771234- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # DO 269

LENGTH (miles / Am) 0 /0.00

DESCRPT: MULTI-USE TRAILS IN DOUGLASVILLE

PE:LOCL ROW: LOCL CST: 2000 FED Share:

9/16/99 Page 97 of275

.\

,

$325,000 $260,000

PROJECT: 81Y064- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANTA TMA TIP # DO 277

LENGTH (miles / Am) 0 /0.00

DESCRPT: U~GRADE 1-20 EB WEIGH STATION -FOR ATL $ -SEE CARROLL

ASSOCIATED PROJECTS: 811064-

OTH Share:
PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$65,000
$5,000,090 $4,500,000
$500,000

END OFDOUGLAS COUNTY

-

'"

...

_._t_-. ~-----

1:1 _ __ _

STATE TRANSPORTATION IMPROVEMENTPROGRAM

91/6/99

Page 98 of275

~NTY

PROJECT: 421640-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE .

LENGTH (miles 1 km) 0.5 10.81

DESCRPT: SR llUS 27 @ WAMBLE CREEK SOUTH OF BLAKELY

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2000 cST: 2000 FED Share: GA Share:

UNDERWAY S10,000
S394,000 $315,200 $78,800

PROJECT: 422215- TYPE WORK: RECSTIREHAB.

"FUND: STATE

LENGTH (mileslkm) 7.3 /11.75

DESCRPT: SR llUS 27 FM CR 279/DAMASCUS-HILTON RD TO BLAKELY BYPASS

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 431320- 42Y215-

.PE: 1996 ROW: 2001 CST:

UNDERWAY $3,885,000 AFTER 2002

PROJECT: 422220- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 7.1 111.43

DESCRPT: SR llUS 27 FR BLAKELY BYPASS TO CLAY COUNTY LINE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 42Y22Q-'

PE: 1993 ROW: 2001 CST:

UNDERWAY $1,275,000 AFTER 2002

PROJECT: 42Y215- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0/0.00

DESCRPT: SR llUS 27 FM CR 279 TO BLAKELY BYPASS - FOR FED PE; 422215

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422215-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 42Y220- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km). 0/0.00

DESCRPT: SR llUS 27 FR BLAKELY BYPASS TO CLAY CO.- FOR FED PE; 422220

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422220-

PE:2000 ROW: NONE CST: NONE

$1,000

END OFEARLYCOUNTY

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99

I:

ti

ECHOLS COUNTY

PROJECT: 42Y420- TYPE WORK: RECSTIREHAB

FUND: NHS

I

LENGTH (miles / km) 0/0.00 DESCRPT: SR 89IUS 441 FROM FLA TO CR 8 IN CLINCH - FOR FED PE; 422420 EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422420-

n

PROJECT: 442985- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26/0.42

I

DESCRPT: SR 135 @ LITTLE RIVER APP 5 MI S OF JCT SR 376

Page 99 of27$

PE:2000 ROW: NONE CST: NONE

. $1,000

PE:2000 ROW: CST:

$35,000 AFTER 2002
AFTER~002

I

PROJECT: 442986- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles / km) 0.23/0.37

ROW:

AFTER 2002

I

DESCRPT: SR 94 @ TOMS CREEK APP 10.3 MI E OF JCT SR II

CST:

AFTER 2002

I

PROJECT: 442987-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.3 /0.48

PE:2000 ROW:

$40,000 AFTER 2002

DESCRPT: SR 94 @ SUWANNOOCHEE CREEK APP 3.5 MI E OF JCT SR 89

CST:

AFTER 2002

[

I

PROJECT: 471470-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

PE:2000 ROW: LOCL

$20,000

DESCRPT: CR 36IWOODPECKER RD @ PERCH CREEK APP 16.5 M1 SE OF TARVER

CST:

AFTER 2002

I

I

END OFECHOLS COUNTY

I

I

I

I

I

I

I

-----,-,,--STATE TRANSPORTATION IMPROVEMENTPROGRAM

EFFINGHAM COUNTY

PROJECT: 0000073 TYPE WORK: ENHANCEMENT

FUND: STP

DESCRPT: EBENEZER BIKEIPED. TRAIL

LENGTH (miles I km) 0 10.00

PE:LOCL ROW: LOCL CST: 2000 FED Share:

9116199 PagelOOof275
$500,000. $400,000

PROJECT: 222270- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (milesI km) 10.2/16.39

DESCRPT: SR 21 FM N OF CR 39 TO CR 255 IN SCREVEN COUNTY & 22R270

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22227X- 22R270-

OTR Share:
PE: 1993 ROW: .CST:

$100,000
UNDERWAY AFTER 2002 AFTER 2002

PROJECT: 511405- TYPE WORK: MAINTENANCE

FUND: NBS

SAVANNAH TIP # 93-H-04

LENGTH (mileslkm) 10.7/17.21

DESCRPT: I-95/SR 405-GATEWAY @ FLORIDA AND SC STATE LINES /51140XlZ

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 51140X-

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$2,040,000 $1,632,000
$408,000

PROJECT: 521702- TYPE WORK: NEW CONSTRUCTION FUND: STATE LENGTH (miles I km) 0/0.00
VESCRPT: SR 21-CONSTRUCTION OF A NOISE WALL FOR SPRINGFIELD BYPASS

PE: 1993 ROW: 2002 CST:

'UNDERWAY $10,000
AFTER 2002

PROJECT: 522170- TYPE WORK: RECSTIREHAB

FUND:STP

LENGTH (miles I km) 2.6/4.19

DESCRPT: SR 17&261US 80 FM SR 17 TO CHERRY ST IN BLOOMINGDALEICHATHAM

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 52217X-

PE: 1993 ROW: 1998 CST: 2000 FED Share: GAShare:

PROJECT: 533145- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23/0.37

DESCRPT: SR 26IUS 80 @ OGEECHEE RIVER OVERFLOW 9 MI S ,OF GUYTON

PE:2000 ROW: CST:

UNDERWAY UNDERWAY $2,675,000 $2,140,000
$535,000
$20,000 AFTER 2002 AFTER 2002

PROJECT: 571408- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0/0.00

DESCRPT: MULTI-USE TRAIL IN SPRINGFIELD

PROJECT: 571450~

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23 10.37

DESCRPT: CR 183/LOG LANDING ROAD @ EBENEZER CREEK 4 MI N OF RINCON

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:2000
ROW: LOCL CST:

$802,000 $641,600
$160,400 $20,000
AFTER 2002

END OF EFFINGHAM COUNTY

----------_._._._-----_._--

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 101 of275

ELBERT COUNTY

PROJECT: 12Y840- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0 10.00

DESCRPT: SR 17 FROM NORTH OF CR 50 TO SO OF CR 367-FOR FED PE/122840

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 122840-

. PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 132410- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1km) 0.58/0.93

DESCRPT: SR 721SR 17 INTERCHANGE JUST WEST OF ELBERTON

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 1999 CST: 2000
GA Share:

UNDERWAY UNDERWAY $7,468,000
$7,468,000

PROJECT: 132990- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.23/0.37

DESCRPT: SR 77 @ FALLING CREEK 6.1 MI S OF ELBERTON

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 142020- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.2310.37

DESCRPT: CR 242IBREWERS BRIDGE RD @ BEAVERDAM CK 2.5 MI N OF ELBERTON

PE: 1995 ROW: LOCL CST: 2000 FED Share: GA Share:

END OF ELBERT COUNTY

UNDERWAY
$571,000 $456,800 $114,200

--_._._ _----------------------_._--------_._---

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 102 0/275

EMANUEL COUNTY

PROJECT: 221900- TYPE WORK: RECSTIREHAB

FUND: STATE

, LENGTH (miles 1 km) 2.2/3.54

DESCRPT: SR 4IUS 1 FM SOUTH TO NORTH CTY LMTS IN OAK PARK & NEW LOC

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22Y900-

PE: 1993 ROW: 2001 CST:

UNDERWAY $1,109,000 AFrER2002

PROJECT: 221910- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 2.3 13.70

DESCRPT: SR 4IUS 1 FROM NCL OAK PARK TO '1-16

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22Y91O-

PE: 1993 ROW: 2001 CST: -

UNDERWAY $160,000
AFTER 2002

PROJECT: '222490- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 9.8/15.78

DESCRPT: SR 4IUS 1 FM N. OF 1-16NORTH TO SR 297 @ SWAINSBORO BYPASS

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22Y490-

PE:.l993 ROW: 2001 CST:

UNDERWAY $2,593,000 AFTER 2002

PROJECT: 22Y490- ' TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km)

0/0.00

DESCRPT: SR 4IUS 1 FM 1-16 TO SR 297 @ SWAINSBORO BYP - FOR FED PE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222490;.

PE:2000 ROW: NONE CST: NONE

.$1,000

PROJECT: 22Y900- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 4IUS 1 FM FM OAK PARK SO.TO NO.CTY LMTS~FOR FED PE;221900

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 221900-

PE:20oo ROW: NONE CST: NONE

$1,000

PROJECT: 22Y91O- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km)

0/0.00

DESCRPT: SR 4IUS 1 FROM NCL OAK PARK TO 1-16 FOR FED PE; 221910

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 221910-

PE:2000 ROW: NONE eST: NONE

$1,000

PROJECT: 23 I960- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.74/1.19

DESCRPT: SR 56 (3) BRIDGES OVER OGEECHEE RVR & OVFL NE OF SUMMERTOWN

PE: 1997 ROW: 2002 CST:

UNDERWAY $2,000
AFTER 2002

PROJECT: 231970- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.23/0.37

DESCRPT: SR 57 OVER SARDIS CREEK 9.7 MILES NW OF SWAINSBORO

PE: 1997 ROW: 2001 CST:

UNDERWAY $10,000
AFTER 2002

PROJECT: 232325 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles Ikm) 0.21/0.34
DESCRPT: SR 26IUS 80 @ E FORK YAM GRANDY CK 2.2 MI SW OF SWAINSBORO

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

J

I

',':\;;.;,

EMANUEL COUNTY

~.

END OF EMANUEL COUNTY

Page 103 of275

jj:,
:1t
I I I
I,',. " I I I I I
I
,I
~

__ -----------_. .-------------------------

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99

Page 104 of275

EVANS COUNTY

PROJECT: 0000074 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: CLAXTON PLANNING FOR MULTI-USE FACILITY AND LANDSCAPING

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$84,000 $67,200

PROJECT: 522105- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 1.5412.48

DESCRPT: SR 30/CLAXTON FM WEST CTY LMTS TO EAST CTY LMTS

EXIST. LANES: 02 PROPOSED LANES: 05

OTHShare:
PE:NONE ROW: 2000 CST:

$16,800
$2,436,000 AFTER.2002

END OFEVANS COUNTY

f~I1

--------~-S-T- AT-E-T- RA=N- SP-O-RT-A- TI-O- N I-M- PR-O_V. EM=E-N- T P-R- OG-R-A- M------9- 1/6- /99'-

Page /05 of275

i
I

FANNiN clJ17NTY

PROJECT: 630870- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 1.15 /1.85

I

DESCRP.T: SR 60 FM CR 63 TO MINERAL BLUFF CL & MP 24.3-25.3 ' EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1999 ROW: 2002 CST:

UNDERWAY $18,000 .'
AFTER 2002

I

PROJECT: 642120- TYPE WORK: RECSTIREHAB

FUND: STP

, LENGTH (miles 1 km) 2~9 14.67

I

DESCRPT: SR 60 SP- PASSING LANES NB-MP.3 TO MP 1.51 SB MP 3.5 TO 5.2
EXIST. LANES: 02 PROPOSED LANES: 03

PE:2000 ROW: CST:

$65,000 AFTER 2002 AFTER 2002

I

PROJECT: 642150- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles Ikm) 3.45/5.55

PE:2000 ROW:

$42,000 AFTER 2002

DESCRPT: SR 60 PASSING LANES BET MINERAL ,BLUFF & McCAYSVILLE (3 LOC)

CST:

AFTER 2002

I

EXIST. LANES: 02 PROPOSED LANES: 03 ASSOCIATED PROJECTS: 644170-

I:

PROJECT: 642160-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.15 10.24

PE: 1995 ROW: 2001

UNDERWAY $7,000

DESCRPT: SR 60 BRIDGE REPLACEMENT OVER COOPER'S CREEK

CST:

AFTER 2002

I:

ASSOCIATED PROJECTS: 642165-

I

PROJECT: 642165-

TYPE WORK: REHAB.BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.15/0.24

PE: 1995 ROW: 2001

UNDERWAY $7,000

DESCRPT: SR 60 OVER SKEENAH CREEK & CHAPEL BRANCH {PIPE ONLY}

CST:

AFTER 2002

I

ASSOCIATED PROJECTS: 642160-

PROJECT: 642280- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1997

UNDERWAY

B

LENGTH (miles 1 km) 0.22/0.35 DESCRPT: CR 220iLOVING RD @ HEMPTOWN CREEK 1.5 MI NE OF MORGANTON

ROW: LOCL CST: 2001

$670,000

FED Share:

$536,000

ti

GA Share:

$134,000

END OF FANNIN COUNTY

I

I

I

B

m

.

w__. _

.~,_,.

_.__ _""

.

'

.

STATE TRANSPORTATION IMPROVEMENTPROGRAM

..._ _._.

_

9116/99 Page 106 of275

FAYETTffCljfJN~'-'------------.----,---------~

PROJECT: 322670- TYPE WORK: ACCELIDECEL LANE

FUND: STP ,

ATLANTATMATIp#FAOI9

i LENGTH(mileslkm) 2.2/3.54

DESCRPT: SR 74 @ 8 INTERSECTIONS BET WISDOM RD & MILAM RDIFULTON

EXIST. LANES: 04 PROPOSED LANES: 05

PE:NONE ROW: 1998 CST: 2000' FED Share: GA Share:

UNDERWAY $1,163,000 $1,046,700
$116,300

PROJECT: 332370- TYPE WORK: TURN LANES

FUND: STP

ATLANTATMA TIP # FA 101

LENGTH(mileslkm) , 0.42/0.68

DESCRPT: SR 92 @ RIVERS ROAD AND WEST BRIDGE ROAD - TURN LANES

PE: 1996 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$130,000 $117,000
$13,000

. PROJECT: 332940- TYPE WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # FA 107

LENGTH(miles 1 km) 0.2 10.32

DESCRPT: SR 54 AT JEFF DAVISIADD SIGNALS AND TURN LANES

PROJECT: 332985- TYPE WORK: SIGNALS

FUND: STP

ATLANTATMA TIP # FA 231

LENGTH (mileslkm) 0.2/0.32

DESCRPT: SR 74 AT DOGWOOD TRAIL

PROJECT: 332990- TYPE WORK: SIGNALS

FUND: STP

ATLANTA TMA TIP # FA 227

LENGTH (mileslkm) 0.2/0.32

DESCRPT: HOOD AVE @ SR 85/ SR 92

PROJECT: 333000- TYPE WORK: IMPROVE INTERSECTION FUND: STP'

ATLANTATMA TIP # FA 110

LENGTH (miles Ikm) 0.2/0.32

DESCRPT: SR 54 AT SANDY CREEK RD/CR 365

PROJECT: 371446- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTATMATIP#FAARI77A

LENGTH (mileslkm) 0/0.00

DESCRPT: REDWINE MULI:r-USE TRAIL -PHASE 1

PROJECT: 371447- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # FAAR 1778

LENGTH (mileslkm) 0/0.00

DESCRPT: REDWINE MULIT-USE TRAIL - PHASE 3 & 4

PROJECT: 371768- ' TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FA AR BP028

LENGTH (miles I km) 0 10.00

DESCRPT: CASTLEWOOD RD/CR 96/CS 564 FM COWETA CO. EAST TO SENOIA RD

PE:2000 ROW: 2000 CST: 2000 FEDSha;'e:
OTR Share: PE:2000
ROW: 2000 CST: 2000 FED Share:
OTH Share: PE:2000
ROW: 2000 CST: 2000 FED Share:
OTRShare: PE:2000
ROW: 2000 CST: 2001 FED Share:
OTH Share: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTH Share: PE:LOCL
ROW:LOCL CST: 2000 FED Share: .
OTH Share: PE:LOCL
ROW: LOCL CST: 2000 . FED Share:
OTH Share:

$25,000 $100,000 $175,000 $140,000
$35,000 $10,000 $30,000 $100,000 $80,000
$20,000 $5,000 $10,000 $70,000 . $56,000
$14,000 $25,000 $50,000 $100,000 $80,000
$20,000
$300,000 $240,000
$60,000
$210,000 $168,000
$42,000
$167,000 $133,600
$33,400

STATE TRANSPORTATION IMPROVEMENTPROGRAM
FAYETTE COUNTY END OF FAYETTE COUNTY

9/16/99 Page 1070/275

,.' ! I.:.~ ''". I
'I';, , ~.
I I
I
I I I I I I I I

_ _ _

,_.

_ ~_M _

'M'

._,

.....

STATE TRANSPORTATION IMPROVEMENTPROGRAM

_
9/16199 Page 108 of275

FLOYD cofj'fiiTt-

PROJECT: 0000112 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: RIDGE AND VALLEY SCENIC BYWAY CORRIDOR MANAGEMENT PLAN

. PE:2000 ROW: NONE CST: NONE

$1,250,000

PROJECT: 0000113 TYPE WORK: ENHANCEMENT

FUND: STP

ROME TIP #

LENGTH (miles / km) 0/0.00

DESCRPT: OOSTANAULA RIVER BRJPED MALL NEAR CO OFC'SILANDSCAPING

PROJECT: 620590- TYPE WORK: RECSTIREHAB

FUND: STP

ROME TIP # L-85-ll

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR llUS 27 IN ROME FM 5TH AVE TO JOHN DAVENPORT DR

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTH Share: PE: 1993
ROW: 1997 CST: 2000 FED Share: GAShare:

$1,250,000 $1,000,000
$250,000 UNDERWAY UNDERWAY $3,702,000 $2,961,600
$740,400

PROJECT: 620900- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

ROME TIP # S-86-24

LENGTH (miles / km) 0.3 /0.48

DESCRPT: SR lOllS OF ROME OVER SR 20

.EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 621690- .

PE: 1984 ROW: 2002 CST:

UNDERWAY $350,000
AFTER 2002

PROJECT: 621550- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 2.95/4.75

DESCRPT: SR201100 FM SR 100 NORTH TO SR 100 SOUTH@COOSAJINCLCLVT

EXIST. LANES: 02 PROPOSED LANES: 04

. PE: 1992 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $790,000
$5,124,000 $4,099,200 $1,024,800

PROJECT: 621600- TYPE WORK: NEW CONSTRUCTION FUND: STATE

ROME TIP # S-89-21

LENGTH (miles / km) 4.24 /6.83

DESCRPT: S ROME BYP FM SR 1 ALONG BOOZE MTN RD TO SR 101 @ CR 96

EXIST. LANES: 00 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 62Y600-

PE: 1992 ROW: 2002 CST:

UNDERWAY $11,250,000 AFTER 2002

PROJECT: 621660- TYPE WORK: NEW CONSTRUCTION FUND: HPP

ROME TIP # S-92-24

LENGTH (miles / km) 4 /6.44

DESCRPT: WEST ROME BYP FM HORSELEG CRK RD TO SR 20 @ CR 262; RW=HPP

EXIST. LANES: 00 PROPOSED LANES: 04

PE:NONE ROW: 2000 CST: 2001 FED Share: GAShare:

$8,250,000 $26,313,000 $21,050,400 $5,262,600

PROJECT: 621670- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ROME TIP # S-92-23

LENGTH (miles / knr) 4 /6.44

DESCRPT: SW ROME BYP FM PROP W ROME BYP @ CR 268 TO SR I @ CR 633&BRD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2000 CST: 2001 FEDShare:. GA Share:

UNDERWAY $8,250,000 $38,824,000 $31,059,200 $7,764,800

PROJECT: 621690- TYPE WORK: RECSTIREHAB

FUND: STP

ROME TIP # S-92-25

LENGTH (miles / km) 1.8412.96

DESCRPT: SR 101 FMCR 740/CS899NORTHTOE 12THSTIROME

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 620900-

PE: 1993 ROW: 2002 CST:

UNDERWAY $1,550,000 AFTER 2002 .

I
I :".
I.i. ,
.'
f
I
~il.
I. I
I-
I I I I
U
I I
m.

--_--_. --_.---_._.-------- ..

_.-

-

-

---~---------------
STATE TRANSPORTATION IMPROVEM

E

N

T

P

R

O

G

R

A

M

9/16/99

Page 109 of275

FLOYD COUN~-------------------------__--

PROJECT: 622135- TYPE WORK: TURN LANES

FUND: NHS

ROME TIP # N-QO-4

LENGTH (miles / km) 0/0.00

DESCRPT: SR 20 TURN LANES FM SR 1 IN ROME TO SR 3 IN BARTOW CO/62Y135

ASSOCIATED PROJECTS: 62Y135-

PE:2000 ROW: NONE CST: 2000 FED Share: GA Share:

$140,000
$4,863,000 $3,890,400
$972,600

PROJECT: 62Y600- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ROME TIP # S-89-21

LENGTH (miles/km) 0/0.00

DESCRPT: S ROME BYP FM SR 1 ALONG BOOZE MTN RD TO SR 101- FOR FED PE

EXIST. LANES: 00 PROPOSED LANES: 04

ASSOCIATED PROJECTS: ..621600-

PE:2000 ROW: NONE , CST:NONE

$1,000

PROJECT: 631480- TYPE WORK: RECSTIREHAB

FUND: STP

ROME TIP # L-88

LENGTH (miles / km) 1.812.90

DESCRPT: SR llUS 27 FROM VETERANS HIGHWAY TO OLD DALTON ROAD

EXIST. LANES: 04 PROPOSED LANES: 06

PE:2001 ROW: CST:

$30,000 AFTER 2002 AFTER 2002

PROJECT: 642395- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23/0.37

DESCRPT: SR 156 @ JOHNS CREEK ON FLOYD-GORDON CO LINE

ASSOCIATED PROJECTS: 64239X-

PROJECT: 642405 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.3 /0.48

DESCRPT: SR 100 @ COOSA RIVER .3 MI SOUTH OF JCT WITH SR 20

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PE:2000 ROW: CST:

$49,000 AFTER 2002 AFTER 2002

. PROJECT: 650460- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ROME TIP # L-89-04

LENGTH (miles / km) 0.17 /0.27

DESCRPT: SR 101 OVER ETOWAH RIVER IN ROME

EXIST. LANES: 04 PROPOSED LANES: 05

PROJECT: 66Y420- TYPE WORK: RECSTIREHAB

FUND: NHS

ROME TIP # L-89-6

LENGTH (miles / km) 0 /0.00

DESCRPT: 'SR 746/SE ROME BYP FM SR 101 TOUS 411 - FOR FED PE; 662420

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 662420-

PROJECT: 671100- TYPE,WORK:' RECSTIREHAB

FUND: PFH

LENGTH (miles / km) 6.27/10.09

DESCRPT: SPRINGS RD/CR 635 FM SR 156 TO CR 213ILOVERS LANE

PE: 1993 ROW: 1999 CST: 2000 FED Share: GAShare:

UNDERWAY

$4,797,000 . $3,837,600
$959,400

PE:2000 ROW: NONE CST: NONE

$1,000

PE:2000 , ROW:NONE'
CST: 2001
FED Share:

$25,000
$1,000,000 $1,000,000

PROJECT: 671110- TYPE WORK: RECSTIREHAB

FUND: PFH

LENGTH (miles / km) 6.02/9.69

DESCRPT: CALHOUN GAP RD FM CR 641 TO CR 4821GORDON

ASSOCIATED PROJECTS: 67111X- .

PE:2000 ROW: NONE CST: 2001 FED Share:

$115,000
$300,000 $300,000

-_._----_._------------_._-------------

. STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

Page 110 0/275

FLOYD COUNTY END OF FLOYD COUNTY

..

- - - - - - - - ~ - - - - - - - - - : - - - - - - - - _ . .'"

_..... .. '"' ,

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99 Page 111 of275

FORSYTH COUNTY
PROJECT: 0000137 TYPE WORK:
DESCRPT: CUMMING SIDEWALKS

ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$500,000 $400,000

PROJECT: 110770- TYPE WORK: SAFETY

FUND: STP

LENGTH (miles / km) 1.4/2.25

DESCRPT: SR 400 SAFETY UPGRADES @ 4 LOql-985 @ SR 347/60113 HALL

ASSOCIATED PROJECTS: 11077X- IIY770-

OTH Share:
PE: 1998 ROW: NONE CST: 2000 FED Share: GA Share:

$100,000 UNDERWAY
$6,200,<100 $4,960,000 $1,240,000

PROJECT: IIY770- TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles / km) 0/0.00

DESCRPT: SR 400 SAFETY @ 4 LOCIFORSYTH & 1-985 @ 3 LOCI FOR 04M $

ASSOCIATED PROJECTS: 110770-

PE: 1998 ROW: NONE CS.T:2000 FED Share: GA Share:

UNDERWAY
$4,000,000 $3,600,000
$400,000

PROJECT: 132630- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 400 AT SR 20 INTERCHANGE RECONSTRUCTION

ASSOCIATED PROJECTS: 122250-

PE: 1992 ROW: 2000 CST: 2002 FED Share: GAShare:

UNDERWAY $3,385,000 $6,201,000 $4,960,800 $1,240,200

PROJECT: 132940- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.5/0.81
DESCRPT: SR 400lUS 19 AT SETTINGDOWN ROAD/CR 176 NE OF CUMMING LUMPSUM PROJECT

PE: 1999 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$361,000 $324,900
$36,100

PROJECT: 132955- TYPE WORK: TURN LANES

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: SR400 TURN LNS FM SR369 THRU DAWSON TO CHESTERRA DRILUMPKIN

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 13295X-

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$1,790,000 $1,611,000
$179,000

PROJECT: 142300- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.2 /0.32
DESCRPT: SR 371 AT KELLY MILL ROAD/CR 5 LUMPSUM PROJECT

PE: 1999 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$394,000 $354,600
$39,400

END OF FORSYTH COUNTY

Fii7fNj{jJJV-c"iJilRTY -

PROJECT: 110780-

TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles i km) 1.412.25

DESCRPT: 1-85 SAFETY UPGRADES @ SR15163IBANKSISR511320/106/17j77lHART

ASSOCIATED PROJECTS: 1I078X-

PROJECT: 122080- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 4.3 /6.92

DESCRPT: SR 17 FM SE OF CR 67ILAVONIA TO SE OF STEPHENS CO LINE & BR

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 12Y080-

. PROJECT: 12Y080- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles / km) 0 /0.00 DESCRPT: SR 17[@I-85 RECST INTERCHANGE~IM]FM CR 67ILAVONIA-STEPHENS C

.EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 122080-

PROJECT: 133001- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR 145 @NORTH FORK BROAD RIVER 1.7 MI WFRANKLIN SPRINGS

9/16/99 Page 112 of275

PE: i998
ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$13,300,000 $11,970,000 $1,330,000

PE: 1993 ROW: 2000 CST: 2002
GA Share:

UNDERWAY $2,402,000 $7,000,000
$7,000,000

PE:NONE ROW: NONE CST: 2002 FED Share: GA Share:

$500,000 $450,000
$50,000

PE:2001 ROW: CST:

$22,000 AFTER 2002 AFTER 2002

PROJECT: 141990- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 145 @ NORTH FORK BROAD RIVER NORTH OF CARNESVILLE

PE: 1995 ROW: 2000 eST: 2001 FED Share: GAShare:

UNDERWAY $23,000
$406,000 $324,800
$81,200

PROJECT: 811063- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles / km) 0 /0.00

DESCRPT: UPGRADE 1-85NB AND SB WEIGH STATIONS INCL SCALE REPLACEMENT

PE:1995 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$5,000,000 $4,500,000
$500,000

END OF FRANKLIN COUNTY

- - - - - - - - . - _ . - - - " . ' _ . _ - ----,~.---._._---------------,
9/16/99
Page 113 of275

FULTON COUNTY-

PROJECT: 713155- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # AR 261

LENGTH (miles 1 km) 6.71 / 10.80

DESCRPT: ATMSI COMMISURVEILLANCE 1-20 FM CAPITOL AVE TO WEST 1285

PE:NONE ROW: NONE CST:2000' FED Share: GAShare:

$6,100,000 $4,880,000 $1,220,000

PROJECT: 713157- . TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # AR 202

LENGTH (miles 1km) 9.7/15.62

DESCRPT: ATMSI COMMUN/SURVEIL'CE 1-20 FM CAPITOL AVE TO WEST 1285

ASSOCIATED PROJECTS: 71315X-

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$8,300,000 $6,640,000 . $1,660,000

PROJECT: 713230- TYPE WORK: REHAB. BRIDGE

FUND: 1M

ATLANTA TMA TIP # FN AR 185

LENGTH (miles/km) 0/0.00

DESCRPT: 1-285 @ RIVERSIDE DRI TURN LANES & RELOCATE RAMPS

PE: 1995 ROW: 2000 CST: 2002 FED Share: GA Share:

UNDERWAY $400,000
$3,662,000 $3,295,800
$366,200

PROJECT: 713330- TYPE WORK: RECSTIREHAB

FUND: 1M

ATLANTA TMA TIP # AT AR 178

LENGTH(mileslkm) 3.12/5.02

DESCRPT: 1-285 SOUTH TO 1-20 WEST RAMP GEOMETRY WEST OF ATLANTA

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1995 ROW: 2000 CST: 2000 FED Share: GA Share:

UNDERWAY $100,000
$2,100,000 $1,890,000
$210,000

. PROJECT: 713370- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # AR279

LENGTH(mileslkm) 9.45/15.21

DESCRPT: ATMSIl-285 SURVEIL FM 1-20 W IN FULTN N TO 1-75 IN COBB

ASSOCIATED PROJECTS: 71337L-

PE:2000 ROW: NONE CST: 2002 FED Share: GA Share:

$5,000
$8,449,000 $6,759,200 $1,689,800

PROJECT: 713371- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # AT AR 216

LENGTH(mileslkm) 10.7/17.26

DESCRPT: ATMS! 1-285 SURVEIL FM 1-85/UNION CITY NORTH TO 1-20 WEST

PE:2002 ROW: NONE CST:

$5,000 AFTER 2002

PROJECT: 713690- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # AT AR214

LENGTH(miles/km) 0.2/0.32

DESCRPT: 1-285 AT BANKHEAD HIGHWAYISR 8IUS 78-278

ASSOCIATED PROJECTS: 750780-

PE: 1999 ROW: 2001 CST: 2002 FED Share: GA Share:

UNDERWAY $1,200,000 $3,700,000 $2,960,000
$740,000

PROJECT: 714105- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ATLANTA TMA TIP# AR302

LENGTH (mileslkm) 3.22/5.18

DESCRPT: 1-75 NOISE BARRIERS FM HOWELL MILL RD TO W. PACES FERRY (W)

PE:2000 ROW: NONE CST: 2002 FED Share: GAShare:

$30,000
$3,000,000 $2,400,000
$600,000

PROJECT: 714115- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ATLANTA TMA TIP # AR'304

LENGTH (mileslkm) 3.57/5.75.

DESCRPT:. 1-20 NOISE BARRIERS FM FULTON IND BLVD TO H.E. HOLMES (N&S)

PE:2000 ROW: NONE CST: 2002 FED Share: GA Share:

$30,000 _
$3,000,000 . $2,400,000
$600,000

~,.~
::.,
:J:

-- r-----------------------------------------------~---

----_.-- _------_.__ _.. .. _-~-_._._-..-;.---_

...._.", ~---,-~-,---

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 114 of275

FULTON COUNty

----.--------

PROJECT: 714190-

TYPE WORK: NEW CONSTRUCTION

FUND: NHS

ATLANTA TMA TIP # AT AR 224A

LENGTH (miles I km) 0 10.00

DESCRPT: NEW 17TH STREET BRIDGE OVER 1-75

PE:2001
ROW: LOCL . CST:

$5,000 AFTER 2002

PROJECT: 714205- TYPE WORK: MAINTENANCE

FUND: NHS

ATLANTA TMA TIP # AR 130

LENGTH (miles I km) 0 10.00

DESCRPT: tUNNEL # 1 SR 13 UNDER 1-851 TUNNEL #2 RAMP FM SR 13 TO 1-85

LUMPSUM PROJECT

PE: 1999 iWW:NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$40,ODO $32,000
$8,000

PROJECT: 714215- .TYPE WORK: MAINTENANCE

FUND: NHS

ATLANTA TMA TIP # AR 130

LENGTH (miles I km) 0.2/0.32

DESCRPT: 1-75 REPLACE DRAINAGE DETENTION BOX AT 1-75 & WALTHALL COURT

LUMPSUM PROJECT

PE: 1999 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY'
$270,000 $216,000
$54,000

PROJECT: 720570 TYPE WORK:' RECSTIREHAB -

FUND: NHS.

ATLANTA TMATIP# AT 004

LENGTH(mileslkm) 0.51/0.82

DESCRPT: DL HOLLOWELL PKWY/SR 8 FM PROCTOR CRK TO E OF SCL RR BRIDGE

PE: 1993 . ROW: 2000 CST: 2001 FED Share: GA Share:

UNDERWAY $1,421,000 $5,365,000 $4,292,000 $1,073,000

PROJECT: 721720- TYPE WORK: REPLACE BRIDGE

FUND: STP

ATLANTA TMA TIP#AT 187

LENGTH (miles Ikm) 0.2/0.32

DESCRPT: NORFOLK SOUTHERN RR OVER SR 3INORTHSIDE DR

PROJECT: 721950- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # FN AR 193

LENGTH (miles I km) 12/19.32

DESCRPT: A!MSI SR 400 COMMUNIC/SURVEILLANCE/ATIS FM 1-285 TO SR 120

PE:LOCL iWW:LOCL
CST: 2000 FED Share:

$'1,000,000 $800,000

OTH Share:
PE:NONE" ROW: NONE CST: 2000 FED Share: GA Share:

$200,000
$10,300,000 $8,240,000 $2,060,000

PROJECT: 721960- TYPE WORK: 'SAFETY

FUND: NHS

ATLANTA TMA TIP # AT AR 218

LENGTH (miles I km) 7.9/12.72

DESCRPT: ATMSI SR 400 COMMUNICNSURVEIL FM S OF 1-85 TO N OF 1-285

PE:2002 ROW: NONE CST: 2002 FED Share: GA Share:

$5,000
$4,000,000 $3,200,000
$800,000

. PROJECT: 722090- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # FN AR 190

LENGTH (mileslkm) 0.2/0.32

DESCRPT: SR 400 AT WINDWARD PARKWAY

PE: 1999 ROW: 2000 CST: 2001 FED Share: GA Share:

UNDERWAY $1,000,000 $8,874,000 $7,099,200 $1,774,800

PROJECT: 722130-

TYPE WORK: NEW CONSTRUCTION

FUND: HPP'

ATLANTA TMA TIP # FN AR 196

LENGTH (miles I km) 0/0.00

DESCRPT: SR 400 FOUR NOISE BARRIERS FM PITTS RD TO CHATTAHOOCHEE RVR

PE: 1999 ROW: NONE CST:2000 FED Share: GA Share:

UNDERWAY
$2,463,000 $1,970,400
$492,600

-----~--,---------,
STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 1/5 of275

FULTON COUNTY

PROJECT:, 722140- TYPE WORK: PLANNING

FUND: HPP

ATLANTA TMA TIP # FN AR 202

LENGTH (miles I km) 0 10.00

DESCRPT: STUDY/CONST MUL TIMODAL TRANSPORTATION CORRIDOR ALONG SR 400

PE:2000 ROW: NONE CST:

$5,000,000 AFTER 2002

ASSOCIATED PROJECTS: 72YI40-

PROJECT: 722150- TYPE WORK: OTHER

FUND: NHS

PE: NONE

ATLANTATMATIP#AR316

LENGTH (mileslkm) 0/0.00

ROW: NONE

DESCRPT: HOV NETWORK PATROL/CONTRACT W/LOCAL LAW ENFORCEMENT OFFICERS CST: 2000

FED Share:

GAShare:

$2,000,000 $1,600,000
$400,000

PROJECT: 722152- TYPE WORK: PLANNING

FUND:, NHS

ATLANTA TMA TIP#AR317 '

LENGTH (mileslkm) 0/0.00

DESCRPT: HOV NETWORK! VIOLATION RATE DATA ACQUISITION & ANAL YSIS(3YR)

PE:2000 ROW: NONE CST: NONE

$900,000

PROJECT: 73 I 510- TYPE WORK: SAFETY

,FUND: CMAQ

ATLANTA TMA TIP# AT AR215

LENGTH (mileslkm) 6/9.66

DESCRPT: ATMS/ SR 154/166 COMM'CTION/SURVEILLANCE FM 1-285 TO 1-75/85

PE:LOCL ROW: NONE CST: 2000 FED Share: GAShare:

$5,155,000 $4,124,000 $1,031,000

PROJECT: 731830- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FS 083

LENGTH (miles I km) 0.2 10.32

DESCRPT: CAMPBELLTON RD/SR 166 @ BOAT ROCKINEW HOPE ROADS

,

,

'

PROJECT: 731835- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FN 121

LENGTH (miles I km) 0.2/0.32

DESCRPT: SR 120/ABBOTTS BRIDGE ROAD AT JONES BRIDGE ROAD

PROJECT: 731860- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FS 138

LENGTH(mileslkm) 0.22/0.35

DESCRPT: SR 70/CASCADE-PALMETTO @ DEEP CREEK 7.5 MI N OF FAIRBURN

PE:2000 ROW: LOCL CST: 2000 FED Share:
OTH Share: PE:2000
ROW: LOCL CST: 2001 FED Share:
OTHShare: PE:2000
ROW: 2001 CST: 2002 FED Share: GAShare:

$5,000
$370,000 $296,000
$74,000 $5,000,
$2,000,000 $1,600,000
, $400,000 $20,000 $10,000
$444,000 $355,200 '$88,800

PROJECT: 731870~ TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTATMA TIP#AR 157

LENGTH(mileslkm) 0.6/0.97

DESCRPT: SR 9 IN ROSWELL @ KING/CHATTAHOOCHEE STS/ OXBO ST & OAK ST

LUMP SUM PROJECT

PE: 1999 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$716,000 $644,400
$71,600

PROJECT: 731875- TYPE WORK: REPLACE BRIDGE

FUND: STP

ATLANTA TMA TIP # AT 186

LENGTH (mileSIkm) 0.21/0.34

DESCRPT: NORTHSIDE DR @ NORFOLK SOUTHERN RR NORTH OF BANKHEAD HWY

PE:LOCL ROW: LOCL CST: 2000 FED Share:

OTHShare:

$1,000,000 $800,000
$200,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 116 of275

FULTON COUNTY

PROJECT: 731890- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # FS 061

LENGTH (mileslkm) 7.04/11.33

DESCRPT: FULTON INDUSTRIAL BLVD/SR 70 FMCAMPBELLTON RD TO FREDERICK

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$1,250,000 $1,000,000

PROJECT: 731895- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # FN AR BP078

LENGTH (miles I km) 1.71/2.75

DESCRPT: HOLCOMB BRIDGE RDISR 140 FM SCOTT RD TO BARNELL RD

OTH Share:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$250,000
$625,000 $500,000

PROJECT: 731900- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # FS ARBP067A

LENGTH (mileslkm) 1.33/2.14

DESCRPT: ROOSEVELT HWY/SR 14 FM CAMP DR TO WELCOME ALL RD

OTHShare:
PE:LOCL RO W:LOCL CST: 2000 FED Share:

$125,000
$625,000 $500,000

PROJECT: 731910- TYPE WORK: MAINTENANCE

FUND: STP

ATLANTATMA TIP # AR l30H

LENGTH (mileslkm) 7.5/12.08

DESCRPT: SR 13IUS 23 FM SR 9/P'TREE ST THRU DEKALB TO GWINNETT CTY LN

LUMP SUM PROJECT

. ASSOCIATED PROJECTS: 73191X-

OTHShare:
PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$125,000
. $3,875,000 $3,100,000
$775,000

PROJECT: 742482- TYPE WORK: . IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # AT AR 116

LENGTH (mileslkm) 0.19/0.31

DESCRPT: SR I66ILAKEWOOD FWY EB EXIT RAMP @ SYLVAN lID

. PE:2001 ROW: NONE CST:

$5,000 AFTER 2002

PROJECT: 742860- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FN088

LENGTH (mileslkm) 2/3.22

DESCRPT: SPALDING DR FROM MT VERNON RD TO SR 140@ INTER 174286X

ASSOCIATED PROJECTS: 74286X~

PROJECT: 742970- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FS 120

LENGTH (mileslkm) 0.2/0.32

DESCRPT: SR I54/CASCADE PALMETTO HWY@WILKERSONMILLRD

PROJECT: 742976- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP# FS 142

LENGTH (mileslkm) 0.210.32

DESCRPT: CR l385IBUFFINGTON ROAD @ MORNING CREEK TRIB. EIUNION CITY

PROJECT: 742990- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # FN i59

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: MCGINNIS FERRY RD/CR l319 AT SARGENT RD/CR 66

PE: 1997 ROW: LOCL CST: 2002 FED Share: GA Share:
PE:2000 ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:2000
ROW: LOCL CST: 2002 FED Share: GA Share:
PE:LOCL ROW: 2000 CST: 2000 FED Share:
OTl/ Share:

UNDERWAY
$2,200,000 $1,760,000
$440,000
$5,000
$250,000 . $200,000
$50,000 $16,000
$313,000 $250,400
$62,600
$100,000 $375,000 $300,000 .
$75,000 ..

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99 Page 1170/275

FULTON COUNTY

PROJECT: 742995- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # FN 160

LENGTH (mileslkm) 0/0.00

DESCRPT: BIRMINGHAM HWY/SR 372 @ PROVIDENCE RD/CR 27

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$313,000 $250,400

PROJECT: 751900- TYPE WORK: REPLACE BRIDOE

FUND: BRIDGE

ATLANTA TMA TIP # AT 071

LENGTH (mileslkm) 0.5/0.81

DESCRPT: SR 14IUS 29/PETERS ST FM FAIR TO NELSON OVER RR & SPRING ST

OTH Share:
PE: 1992 ROW: 1999 CST: 2001 FED Share: GAShare:

$62,600
UNDERWAY UNDERWAY $7,916,000 $6,332,800 $1,583,200

PROJECT: 752015- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # AT 070

LENGTH (mileslkm) 0.1/0.16

DESCRPT: COURTLAND ST OVER CSX RR

PE: 1992 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$795,000 $636,000 $159,000

PROJECT: 752020- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # AT 069

LENGTH (miles I km) 0.5 I 0~81

DESCRPT: PEACHTREE ST @GEORGIA RR & MARTA AT UNDERGROUND ATLANTA

PE: 1992 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$3,509,000 $2,807,200
$701,800

PROJECT: 752030- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1992

ATLANTA TMA TIP # AT 068

LENGTH (mileslkm) 0.5/0.81

ROW: LOCL

DESCRPT: INTERNATIONAL BLVD @ CSX & NORFOLK-SOUTHERN RR @ OMNI&75Y030

CST: 2000

FED Share:

ASSOCIATED PROJECTS: 75Y030-

GA Share:

UNDERWAY
$4,947,000 $3,957,600
$989,400

PROJECT: 752070- TYPE WORK: RECSTIREHAB

FUND: DEMO

I

ATLANTA TMA TIP # AT 079A2

LENGTH (miles I km) 0.49 10.79

DESCRPT: SR 139/MLK DR AT FAIRBURN RD AND BAKERS FERRY ROAD & "Y"

PE:LOCL. ROW: LOCL CST: 2000

$1,002,000

I

ASSOCIATED PROJECTS: 75Y070-

FED Share: OTHShare:

$801,600 $200,400

PROJECT: 752075- TYPE WORK: RECSTIREHAB

FUND: STP

PE:LOCL

I

ATLANTA TMA TIP # AT 079B

LENGTH (miles/km) 0.56/0.90

DESCRPT: SR 139/MLK JR DR FM HE HOLMES RD TO BARFIELD AVE

ROW: LOCL CST: 2000

$1,002,000

FED Share:

$801,600

I

GAShare:

$200,400

PROJECT: 752082- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

PE: 1992

UNDERWAY

ATLANTA TMA TIP # AT 085

LENGTH (miles/km) 0.5/0.81

ROW: NONE

I

DESCRPT: CENTRAL AVENUE OVER CSX RR & MARTA FM ALABAMA TO WALL STS

CST: 2001

FED Share:

$1,051,000 $840,800

GAShare:

$210,200

I

PROJECT: 752086- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

PE: 1992

UNDERWAY _

ATLANTATMA TIP#AT.086A

LENGTH (miles/km) 9.5/0.81

ROW: 2000

$5,000,000

I

DESCRPT: SR 999/CS 3586/SPRING STREET OVER CSX RAILROAD EXIST. LANES: 02 PROPOSED LANES: 04

CST: 2000 FED Share:

$2,737,000 $2,189,600

ASSOCIATED PROJECTS: 752560-

GA Share:

$547,400

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 118 of275

FULTON COUNTY

PROJECT: 752150- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 021

LENGTH (miles 1km) 0.4 10.64

DESCRPT: WINDSOR PARKWAY/CR 361 OVER NANCY CREEK.3 MILE EAST SR 400

PE: i993 .
ROW: LOCL CST:2001" FED Share: GAShare:

UNDERWAY
$963,000 $770,400 $192,600'

PROJECT: 752320- TYPE WORK: REPLACE BRIDGf=:

FUND: BRIDGE

ATLANTA TMA TIP # FN 085

' LENGTH (miles 1 km) 0.4/0.64

DESCRPT: POWERS FERRY RD/CR 300 OVER LONG ISLAND CREEK

\

PE: 1994 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$461,000 $368,800
$92,200

PROJECT: 752520- TYPE WORK: REPLACE BRIDGE'

FUND: BRIDGE

ATLANTA TMA TIP # AT 097

'LENGTH(mileslkm) 0.29/0.47

DESCRPT: CS 1985/MITCHELL STREET @ SOUTHERN RAILROAD.2 MIW OF SR 3E

"PE:'1995
ROW: LOCL
CSTdoOl FED Share:
GAShare:

PROJECT: 752540- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE ~

ATLANTA TMA TIP # AT 081

. LENGTH(mileslkm) 0.2510.40.

DESCRPT: CS 2661IHOLLYWOOD ROAD @ PROCTOR CREEK 1.8 MI N OF JCT US 78

PE: 1994 .
Ii ". ROW: LOCL
CST: 2000 FED Share:
GAShare:

UNDERWAY
$3,410,000 $2,728,000
$682,000
UNDERWAY
$1,000,000 $800,000 $200,000

PROJECT: 752545- TYPE WORK: REPLACE BRIDGE

"FUND: BRIDGE

"'pE: 1995

ATLANTA TMA TIP # AT 096

LENGTH (miles 1 km) 0.27/0.43

ROW: LOCL

DESCRPT: CR 1349/FAIRBURN ROAD @ CSX RAILROAD SOUTH OF CAMPBELLTON RD

CST: 2000

FED Share:

GAShare:

uNDERWAY
$1,143,000 $914,400 $228,600

PROJECT: 752550- TYPE WORK: REPLAcE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # AT 023

LENGTH (miles 1km) 0.22/0.35

DESCRPT: CS 1259ILAKEWOOD Avs @ NORFOLK SOUTHERN RR S. OF MILTON ST

PE: 1996 ROW: LOCL. CST: 2000 FED Share: GA Share:

UNDERWAY
$1,519,000 $1,215,200
$303,800

PROJECT: 752560- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP#AT086B

LENGTH(mileslkm) 0.48/0.77

DESCRPT: SR 999/CS 3586/SPRING STREET @ SOU RR- CSX RR REPLACEMENT

ASSOCIATED PROJECTS: 752086-

PE: 1998 ROW: 2000 CST: 2000 FED Share: GA Share:

UNDERWAY $5,000,000 $11,852,000 $9,481,600 $2,370,400

PROJECT: 752570- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # AT 100

LENGTH(mileslkm) 0.22/0.35

DESCRPT: CR 1349/FAIRBURN ROAD @ CSX RAILROAD NORTH OF CASCADE RD'

PE: 1996 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$834,000 $667,200 $166,800

PROJECT: 752580- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FS 069

LENGTH (miles'lkm) 0.21/0.34

DESCRPT: CR 49510LD FAIRBURN ROAD @ CAMP CREEK .03 MI S CAMP CRK PKY

EXIST. LANES: 02 PROPOSED LANES: 03

.

PE: 1996 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY'
. $1,407,000 . $1,125,600
$281,400

..

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99 Page 119 of275

FuLTON COUNTY

PROJECT: 752620- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 096

LENGTH (miles 1 km) 0.2/0.32

. DESCRPT: CS 3242/PINE GROVE ROAD @ WILLEO CK @ W ROSWELL CLIFULTON

ASSOCIATED PROJECTS: 75262X-

PE: 1996 RO.w:LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$502,000 $401,600 . $100,400

PROJECT: 752850- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # AT 108

LENGTH (mileslkm) 0.42/0.68

DESCRPT: SR 280/JAMES JACKSON PKWY @CHATT. RIVER - SOU RR

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

$54,000 $50,000 $4,000,000 $3,200,000 $800,000

PROJECT: 752860- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # AT 162

LENGTH (miles 1 km) 0.42 /0.68

DESCRPT: SR 154lMEMORIAL DRIVE AT BOULEVARD AVE/CS 520

PE: 1997 ROW: 2000 CST: 2000 FED Share: GA Share:

UNDERWAY $281,000 $285,000 $228,000 $57,000

PROJECT: 752870- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # AT 163

LENGTH (miles / km) 0.42 /0.68

DESCRPT: SR I 54lMEMORIAL DRIVE AT MORELAND AVE & DEKALB CO

ASSOCIATED PROJECTS: 75287X-

PE: 1997 ROW: 1999 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$390,000 $312,000
$78,000

PROJECT: 752960- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 174

LENGTH (miles/km) 0.2/0.32

DESCRPT: CR 186/HEMBREE ROAD @ FOE KILLER CREEK 2 MI SW OF ALPHARETTA

PE:2000 ROW: LOCL CST:

$5,000 AFTER 2002

PROJECT: 752970- TYPE WORK: REPLACEBRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 173

LENGTH (miles / km) 0.2 10.32

DESCRPT: CR 133210LD ROSWELL ROAD @ FOE KILLER CREEK 2.7 MI S OF ALPH

PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

PROJECT: 752980- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # FS 088

LENGTH (miles / km) 0.2 10.32

DESCRPT: FAYETTEVILLE RD/CR 1316 GRADE SEPARATION AT CSX RAILROAD

PE: 1999 ROW:LOCL CST: 2002 FED Share: GA Share:

PROJECT: 753050- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FS 073

LENGTH (miles / km) 1.31 /2.11

DESCRPT: CR 4176/CASCADE RD FM DANFORTH RD TO ALTANTA CITY LIMITS

PE:2000 ROW: LOCL CST: 2000 FED Share:

PROJECT: 753052- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FS 116

LENGTH (miles / km) 2.97/4.78

DESCRPT: FLAT SHOALS RD/CRI384' EM 1-85 TO OLD NATIONAL HWYIADD MEDIAN

OTHShare:
PE:2000 ROW: LOCL CST: 2001 FED Share:

OTH Share:

$5,000
$400,000 $320,000
$80,000
UNDERWAY
$2,500,000 $2,000,000
$500,000
$5,000
$600,000 $480,000
$120,000 $5,000
$1,500,000 $1,200,000
$300,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 120 of275

FULTON COUNTY

PROJECT: 753054- TYPE WORK: ENHANCEMENT

FUND: STP

PE:2000

ATLANTA TMA TIP # FN 103

LENGTH (miles 1 km) 1.16 1 1.87

ROW: LOCL

DESCRPT: GLENRIDGE DRiCR 351 FM ROSWELL RD TO GLENRIDGE CONN & MEDIAN

CST: 2001

FED Share:

$5,000
$600,000 $480,000

PROJECT: 753125- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FN 119

LENGTH (miles 1km) 0.2/0.32

DESCRPT: NESBIT FERRY RD/CR 108 @ BRUMBELOW RD

OTHShare:
PE:2000 ROW:I:.OCL CST: 2000 FED Share:

$120,000 $5,000
$250,OPO $200,000

PROJECT: 753130- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FN 117

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: NESBIT FERRY ROAD/CR 108 AT SCOTT ROAD

OTHShare:
PE:20oo ROW: LOCL CST: 2000 FED Share:

$50,000 $5,000
$280,000 $224,000

PROJECT: 753135- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FN 118

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: NESBIT FERRY ROAD AT ARBOR WOODS DRIVE

OTHShare:
. PE:2000 ROW: LOCL CST: 2000 FED Share:

$56,000. $5,000
$200,000 $160,000

PROJECT: 753140- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FS 084

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: CASCADE RD/CR 4176 @CARLO WOODS DRiCASCADE OVERLOOK RD

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$40,000 $5,000
$350,000 $280,000

PROJECT: 753145- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # FS 076

LENGTH (miles 1 km) 0.2 10.32

DESCRPT: CAMP CREEK PKWY/SR 6 AT BUTNER RD/CR 1374

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$70,000 $5,000
$150,000 $120,000

PROJECT: 753220- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 171

LENGTH (mileslkm) 0.2/0.32

DESCRPT: CR 1324/BETHANY ROAD @ COOPER SANDY CREEK 3.0 MI N OF ALPHAR

OTHShare:
PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

$30,000 $40,000
$802,000 $641,600 $160,400

. PROJECT: 753235- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # FN 1 5 6 .

LENGTH (miles1 km) 0.2/0.32

DESCRPT: PEACHTREE DUNWOODY RD/CR 1431 @JOHNSON FERRY ROAD

PE:2000 ROW: 2000 CST: 2000 FED Share:

OTHShare:

PROJECT: 753240- TYPE WORK: NEW CONSTRUCTION FUND: STP

PE: 2000

ATLANTA TMA TIP # FN 161

LENGTH (miles 1 km) 1.4412.32

ROW: 2000

DESCRPT: ROSWELL RD FM ABERNATHY RD TO HAMMOND DR & JOHNSON FERRY RD

CST: 2000

.

FED Share:

OTHShare:

$58,000 $58,000 $1,200,000 $960,000
$240,000 $388,000 $796,000 $2,755,000 $2,204,000
$551,000

f

--...;..-----,-_.._---------------------------------

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 121 of275

)7..

.~. :.'
I

FULTON CO-UNTY

PROJECT: 753245- TYPE WORK: NEW CONSTRUCTION FUND: STP

PE:2000

$20,000

ATLANTA TMA TIP # FN ARBP091

LENGTH(mileslkm) 0.96/1.55

ROW: 2000

$60,000

.~

DESCRPT: WINDSOR PKWY/CR 361 FM ROSWELL RD TO GA 400

CST: 2000 FED Share:

$660,000 $528,000

PROJECT: 753250- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN AR BP089

LENGTH (miles I km) .2.5 14.03

DESCRPT: MT VERON HWY/CR 1318 FM HEARD'S FERRY RD TO ROSWELL RD

OTHShare:
PE:2000 ROW: 2000 CST: 2000 FED Share:

$132,000
$25,000 $125,000 $350,000 $280,000

PROJECT: 753255- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # FS 130

LENGTH (mileslkm) 2.02/3.25

DESCRPT: FAIRBURN RD FM GARRISON DR TO CSX RR & SIDEWALKS; BIKE

OTHShare:
PE:2000 ROW: 2000 CST: 2000 FED Share:

$70,000
$220,000 $220,000 $1,800,000 $1,440,000

OTHShare:

PROJECT: 753260- ' TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # FN 157

LENGTH (miles I km) 0.3 /0.48

DESCRPT: NORTHSIDE DR @RIVERVIEW RD/CR291 & OLD POWERS FERRY RD/CR293

PE:LOCL ROW: 2000 CST: 2000 FED Share:

$360,000
$75,000 $343,000 $274,400

PROJECT: 753275- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTATMA TIP # FSARBP063

LENGTH(mileslkm) 3.05/4.91

DESCRPT: CASCADE RD/CR 4176 FM DANFORTH RD TO FULTON INDUSTRIAL BLVD

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$68,600
$625,000 $500,000

PROJECT: 753280- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # FS AR BP062

LENGTH (miles I km) 0.42/0.68

DESCRPT: NEW HOPE RD/CR 473 FM DANFORTH RD TO CASCADE RD

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$125,000
$250,000 $200,000

PROJECT: 753285- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTf.\ TMA TIP # FS AR BP070

LENGTH (miles / km) 0.7 /1.13

DESCRPT: WASHINGTON RD/CR 1389 FM ROOSEVELT HWY TO E POINT CITY LINE

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$50,000
$200,000 $160,000

PROJECT: 753300- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # FN AR BP083

LENGTH (miles I km) 0.86/1.38

DESCRPT: HAMMOND DR FM GLENRIDGE DR TO DEKALB COUNTY

OTHShare:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$40,000
$625,000 $500,000

PROJECT: 753305- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # FN AR BP081

LENGTH (miles I km) 1.18 11.90

DESCRPT: DUNWOODY PLACE FM ROSWELL RD TO NORTHRIDGE RD

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$125,000
$350,000 $280,000

OTHShare:

$70,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 122of275

FULTONCOUNTY

PROJECT: 753310- TYPE WORK: NEWCONSTRUCfION FUND: CMAQ

ATLANTA TMA TIP # FS AR BP067B

LENGTH (miles I km) 1.54/2A8

DESCRPT: ROOSEVELT HWY/SR 14 FM WELCOME ALL RD TO BUFFINGTON RD: PH 2

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$625,000 $500,000

PROJECT: 753315- TYPE WORK: NEW CONSTRUCfION :... FUND: CMAQ

ATLANTA TMA TIP # FN AR BP075

LENGTH (miles I km) 0.44 10.71 .

DESCRPT: NORTHRIDGE RD SIDEWALKS FM ROSWELL RD TO SR 400

OTH Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$125,000
$250,000 $200,000

PROJECT: 153320- TYPE WORK: RECSTIREHAB

. FUND: STP

ATLANTA TMATIP# FN 158

LENGTH (miles I km) 0/0.00

DESCRPT: CRABAPPLE RD/CR 1441 @ RUCKER RD/CR 1331

PROJECT: 753325- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN AR BP095

LENGTH(mileslkm) 0.3 10.48

DESCRPT: MANSELL RD FM WESTSIDE PKWY TO OLD ROSWELL RD

OTH Share: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTH Share: PE:LOCL
ROW: LOCL CST: 2000 FED Share:

$50,000
$360,000 $288,000
$72,000
$550,000 $440,000

PROJECT: 75Y03Q- TYPE WORK: REPLACE BRIDGE

FUND: STP

ATLANTA TMA TIP#AT068B

LENGTH (mileslkm) 0.5/0.81

DESCRPT: INTERNATIONAL BLVD @ CSX & NS RR @ OMNI - FOR STP $/ 752030

ASSOCIATED PROJECfS: 752030-

OTH Share:
PE: 1992 ROW: LOCL CST: 2000 FED Share: GAShare:

$110,000 UNDERWAY
$4,947,000 $3,957,600
$989;400

PROJECT: 75Y07Q- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # AT 079Al

LENGTH (miles I km) 0.23/0.37

DESCRPT: SR 139/MLK DR AT FAIRBURN RD & BAKERS FERRY FOR STP/752070

ASSOCIATED PROJECfS: 752070

PE:LOCL ROW: LOCL CST: 2000 FED Share: GAShare:

$202,000 $161,600
$40,400

PROJECT: 762460- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP#.MAR246A

LENGTH(miles/km) 0/0.00

DESCRPT: PHASE I-BUCKHEAD STATION N CONCOURSE (PEDESTRIAN BRIDGE)

PE:2000 ROW: LOCL CST: 2000 FED Share:

PROJECT: 762465- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # MAR 246B

LENGTH (mileslkm), 0/0.00

DESCRPT: PHASE 11 BUCKHEAD STATION N CONCOURSE (PEDESTRAIN BRIDGE)

onrsss.
'PE:LOCL ROW: LOCL CST: 2001 FED Share:

omsso

PROJECT: 762472- TYPE WORK: VEHICLE PURCHASE

FUND: CMAQ

PE: LOCL

ATLANTA TMA TIP#MAR237B

LENGTH(miles/km) 0/0.00

' ROW:LOCL

DESCRPT: MARTA INTELLIGENT TRANSPORTATION SYSTEM (FLEET AVLS)/DEKALB.

CST: 2001

FED Share:

ASSOCIATED PROJECfS: 76247X-

OTHShare:

$2,850,000 $6,925,000 $5,540,000 $1,385,000
$6,925,000 $5,540,000 $1,385,000
$1,000,000 $800,000 $200,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199

Page 123 0/275

i:,~"'

FULTON COUNTY

:aI

PROJECT: 762516- TYPE WORK: ENHANCEMENT

FUND: CMAQ

PE: 1995

UNDERWAY

ATLANTA TMA TIP # AT AR BP014

LENGTH (miles I km) 0/0.00

ROW: LOCL

DESCRPT: MULTIUSE TRAIL FM FREEDOM PK TO CENTENNIAL PK

CST: 2001

$750,000

FED Share:

$600,000

PROJECT: 762518- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # AT ARBP138

LENGTH (mileslkm) 0/0.00

DESCRPT: LINDBERG DR FM PEACHTREE RD TO CHESHIRE BRIDGE ROAD

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$150,000 UNDERWAY
$880,0.00 $704,000

OTH Share:

$176,000

PROJECT: 762520- TYPE WORK: ENHANCEMENT

FUND: CMAQ

PE: 1995

UNDERWAY

ATLANTA TMA TIP # FS AR BP029A

LENGTH (miles I km) 0/0.00

ROW: LOCL

DESCRPT: PARKWAY TRAIL PH I-VIRGINIA AVE TO MARTA RAIL STATION

CST: 2001

$343,000

ni i , "

FED Share:

$274,400

It

OTHShare:

$68,600

PROJECT: 762522- TYPE WORK: ENHANCEMENT

FUND: CMAQ

PE: 1995

ATLANTA TMA TIP # FS AR BP029D

LENGTH (miles I km) 0 10.00

ROW: LOCL

DESCRPT: PKWY TRAIL PH IV/CAMP TRUITT RD TO BRANNON PK TO TUBMAN ELEM

CST: 2001

FED Share:

UNDERWAY
$265,000 $212,000

PROJECT: 762525- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # FS AR BP032

LENGTH (miles I km) 0/0.00

DESCRPT: PHOENIX TRAIL FM COMMERCE GATEWAY TO PHOENIX GATEWAY

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$53,000 UNDERWAY
$1,197,000 $957,600

PROJECT: 762527- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # FS ARBP034

'LENGTH(mileslkm) 0/0.00

DESCRPT: DANFORTH RD FM CASCADE RD TO NEW HOPE RD

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$239,400
'. UNDERWAY
$357,000 $285,600

PROJECT: 762529- . TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # FS AR BP035

LENGTH (miles I km) 0 10.00

DESCRPT: FLAT SHOALS RD FM 1-85 TO OAKLEY RD

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$71,400 UNDERWAY
$357,000 $285,600

PROJECT: 762530- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # AT 159

LENGTH(mileslkm) 0/0.00

DESCRPT: METROPOLITAN AVE FM NORTHSIDE DR TO CITY LIMITS

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$71,400 UNDERWAY
$929,000 $743,200

PROJECT: 762532- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FS AR BP038

LENGTH (miles I km) 0/0.00

DESCRPT: STONEWALL TELL RD FM CAMP DR TO FOREST DOWNS LAKE

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

.. $185,800 $5,000
$200,000 $160,000

OTHShare:

$40,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 124 of175

FULTON COUNTY

PROJECT: 762534- TYPE WORK: ENHANCEMENT

FUND: STP

PE: 2000

ATLANTA TMA TIP # FN AR BP018 ,

LENGTH (mileslkm) 0.46/0.74

ROW: LOCL

DESCRPT: SR 372/BIRMINGHAM HWY FM KENSINGTON FARMS RD TO CRABAPPLE RD

CST: 2000

FED Share:

$5,000
$300,000 $240,000

OTH Share:

PROJECT: 762536- TYPE WORK: ENHANCEMENT

FUND: STP

PE:2000

ATLANTA TMA TIP # FN AR BPO19

LENGTH (miles I km) 0.68 /1.09

ROW: LOCL

DESCRPT: BUICE RD FM PINEWALK DR TO DOLVIN ELEMENTARY SCH & OCEE PARK

CST: 2000

FED Share:

$60,000 $5,000
$ 166,QOO $132,800

PROJECT: 762538- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN ARBP023

LENGTH (miles'/km) 1.612.58

DESCRPT: HEARDS FERRY RD FM RIVER CHASE CT TO MT VERNON HWY

OTH Share:
PE:2000 ROW: LOCL' CST: 2000 FED Share:

$33,200 $5,000
, $250,000 $200,000

PROJECT: 762540- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN AR BP026

LENGTH (miles I km) 0.62/1.00

DESCRPT: SPALDING DR FM ROSWELL RD TO PEACHTREE DUNWOODY RD '

OTIl Share:
PE:2oo0 ROW: LOCL CST: 2000 FED Share:

$50;000 $5,000
$217,000 $173,600

PROJECT: 762542- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN AR BP028

LENdTH (miles I km) 0.9/1.45

DESCRPT: TAYLORRD FM BACCARAT CT TO JONES BRIDGE RD

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$43,400 , $5,000
$125,000 $100,000

PROJECT: 762544- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN AR BPO16B

LENGTH (miles I km) 1.5 12.42

iJESCRPT: MT VERNON HWY FM ROSWELL RD TO PEACHTREE DUNWOODY RD

OTH Share:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$25,000 $5,000
$271,000 $216,800

PROJECT: 762546- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT ARBP021

LENGTH(mileslkm) 0/0.00

DESCRPT: BAKERS FERRY RD FM DOLLAR MILL RD TO FAIRBURN RD

OTHShare:
PE:2oo0 , ROW:LOCL
CST: 2000 FED Share:

$54,200 $41,000
$226,000 $180,800

PROJECT: 762548- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMATIP#AT ARBP023,

LENGTH(mileslkm) 0/0.00

DESCRPT: BOLTON RD FM MARIETTA BLYO TO JACKSON PKWY

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$45,200 $83,000
$392,000 $313,600

PROJECT: 762550- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP# AT ARBP024

'LENGTH (mileslkm) 0/0.00

DESCRPT: BOLTON RD FM JACKSON PKWY TO DL HOWELL PARKWAY,

,OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$78,400 $85,000
$397,000 $317,600

OTHShare:

$79,400

",

- - - - - - - - - - ---_._-_.~,_._-------------------

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 125 of275

I~
.';

FULTON COUNIT

PROJECT: 762552- TYPE WORK: ENHANCEMENT

FUND: STP

PE:2000

$95,000

ATLANTA TMA TIP # AT AR BPI00

LENGTH (mileslkm) 010.00

ROW: LOCL

DESCRPT: BENJAMIN E MAYS DR FM FAIRBURN RD TO BEECHER RD

CST: 2000

$532,000

FED Share:

$425,600

PROJECT: 762554- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT ARBP121

LENGTH (miles I km) 010.00

DESCRPT: HOWELL MILL RD FM NORTHSIDE PKWY TO COLLIER RD

. OTJI Share:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$106,400 $123,000
$682,000 $545,600

PROJECT: 762556- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT ARBP135

LENGTH (mileslkm) 010.00

DESCRPT: WEST PACES FERRY RD FM PEACHTREE RD TO CITY LIMITS

OTJI Share:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$136,400 $155,000
$832,000 $665,600

PROJECT: 762562- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT AR BP098

LENGTH (miles I km) 0 10.00

DESCRPT: WEST END RAIL MULTI-USE TRAIL FM SIMPSON RD TO PRYOR ROAD

OTHShare:
PE: 1999 ROW: 2000 CST: 2002 FED Share:

$166,400
UNDERWAY $100,000
$1,095,000 $876,000

PROJECT: 762563- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP# AT ARBP282

LENGTH(mileslkm) 5.39/8.68

DESCRPT: FAIRBURN RD/CR 1349 FM MLK JR DR TO STONE RD BIKE LANES

OTHShare:
PE:LOCL ROW:LOCL CST: 2000 FED Share:

$219,000
$1,400,000 $1,120,000

PROJECT: 762565- TYPE WORK:' NEW CONSTRUCTION FUND: CMAQ

ATLANTATMA TIP # FSARBP079

LENGTH (mileslkm) 010.00

DESCRPT: DOWNTOWN UNION CITY AT VARIOUS LOCATIONS

OTHShare:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$280,000
;
$525,000 $420,000

PROJECT: 762590-. TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP# AR 157

LENGTH(mileslkm) 0.6/0.97

DESCRPT: SR 54IUNIVERSITY AVElMCDONOUGH AT CAPITOLIRIDGE/GAMMON AVE

LUMP SUM PROJECT

OTHShare:
PE: 1999 ROW: LOCL CST: 2001 FED Share: GA Share:

$105,000 UNDERWAY
$399,000 $359,100
$39,900

PROJECT: 762600- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # AT ARBP280A

LENGTH(mileslkm) 010.00

DESCRPT: CITY OF ATLANTA SIDEWALKS @ 12 SCHOOLSI PH 1

PROJECT: 762601- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTATMA TIP#ATARBP280B

LENGTH (miles Ikm) 010,00

DESCRPT: CITY OF ATLANTA SIDEWALKS @ 12 SCHOOLSI PH 2

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTHShare:

$1,190,000 $952,000
.. $238,000
$1,197,000 $957,600
$239,400

STATE TRANSPORTATION IMPRO"VEMENT PROGRAM

9116/99 Page 1260/275

FULTON COUNTY

. PROJECT: 762602- TYPE WORK: NEW CONSTRUCTION FUND: STP

PE: LOCL

ATLANTA TMA TIP # AT AR BP278

LENGTH (miles I km) 0.67 11.08 .

ROW: LOCL

DESCRPT: DECATUR ST FM MLK MARTA STAT TO MLK VISTORS CTRISTREETSCAPES

CST: 2000

FED Share:

$836,000 I $668,800

PROJECT: 762603- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # AT ARBP283

:'LENGTH (mileslkm) 0.62/1.00

DESCRPT: PIEDMONT RD FM MARTA OVERPASS TO PHARR RD STREETSCAPES

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$167,200
$350,000 $280,000

PROJECT: 762604- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # AT AR BP277 '.

LENGTH (miles I km) 1.53 12.46

DESCRPT: BOULEVARD/CS 520 STREETSCAPE FROM 120 TO FREEOOMPARKWAY

OTH Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$70,000
$2,295,000 $1,836,000

PROJECT: 762605- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # AT ARBP284

"LENGTH (mileslkm) 0.24/0.39

DESCRPT: GRANT ST FM MLK MARTA STATIONIDECATUR ST TO MEMORIAL DR

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$459,000
'$380,000 $304,000

PROJECT: 762606- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # FN AR BP082

LENGTH (miles I km) 2.25/3.62

DESCRPT: ROSWELL RD/SR 9 FM 1-285 TO ATLANTA CITY LIMIT

.OTH Share:
. PE:2000 ROW: 2000 . CST:2000 FED Share:

$76,000
$20,000 $50,000 $900,000 $720,000

PROJECT: 762607- TYPE WORK: ENHANCEMENT '.

FUND: STP

ATLANTA TMA TIP # AT AR BP287

LENGTH (mileslkm) 0.61/0.98 v

DESCRPT: CHEROKEE AVElCS 2227 FM MEM0!UAL DR TO AUGUSTA AVE (ZOO)

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$180,000
$405,000 $324,000

PROJECT: 762608- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT AR BP288

LENGTH (miles I km) 1.6112.59

DESCRPT: 10TH FM JUNIPER TO MONROE & PIEDMONT FM 10TH TO WESTMINSTER

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$81,000 $200,000
$1,800,000 $1,440,000

PROJECT: 762610 TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT ARBP286

LENGTH (mileslkm) 0/0.00

DESCRPT: RANDOLPH AVElLAKE AVE FM EDGEWOOD AVE TO LITTLE FIVE POINTS

OTHShare:
PE:LOCL ROW: LOCL . CST:2oo0 FED Share:

$360,000
$956,000 $764,800

PROJECT: 762613- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP # AT ARBP291B

LENGTH (mileslkm) 0/0.00

. DESCRPT: SE ATLANTA ALONG MANIGAULT; FUNSTON ST; LAKEWOOD AVE

OTHShare:
PE:LOCL ROW: LOCL . CST: 2001 FED Share:

$191,200
$443,000 $354,400

OTHShare:

$88,600

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 127 of275

FULTON COUNTY

PROJECT: 762614- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

. ATLANTA TMA TIP # AT AR BP291A

LENGTH (miles I km) 0/0.00

DESCRPT: SW ATLANTA ALONG OGLETHORPE AVE; ROSE CIR; MCMURRAY DR

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$418,000 $334,400

OTHShare:

$83,600

PROJECT: 762615- . TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

PE:LOCL

ATLANTA TMA TIP # FN AR BP085

LENGTH (miles I km) 0.51 10.82

ROW: LOCL

,t;
iIf-

DESCRPT: TROWBRIDGE RD FM DALRYMPLE RD TO ROSWELL RD

CST: 2000 FED Share:

$250,000 $200,000

PROJECT: 762616- TYPE WORK: NEW CONSTRUCTION . FUND: CMAQ'

ATLANTA TMA TIP # FN ARBP084

LENGTH (mileslkm) 1.37/2.21

DESCRPT: WILLEO RD FM COBB COUNTY TO AZALEA DR

OTH Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$50,000
'$350,000 $280,000

PROJECT: 762620- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP#ARBP003B

LENGTH (mileslkm) 0/0.00

DESCRPT: ATLANTA REGION BICYCLE & MULTI-USE TRAIL PLANNING - PH 2

OTHShare:
PE:NONE ROW: NONE CST: 2000 FED Share:

$70,000
$100,000 $80,000

PROJECT: 762621- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP#ARBP003A

LENGTH (mileslkm) 0/0.00

DESCRPT: ATLANTA REGION BICYCLE & MULTI-USE MAPPING FOR PLANNING-PHI

OTHShare:
PE:NONE ROW: NONE CST: 2000 FED Share:

$20,000
$100,000 $80,000

PROJECT: 762622- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP#ARBP002

LENGTH (miieslkm) 0/0.00

DESCRPT: EDUCATION & OUTREACH FOR WALKING & BIKING TO SCHOOL

OTH Share:
PE:NONE ROW: NONE CST: 2000 FED Share:

$20,000
'$
$205,000 $164,000

PROJECT: 762623 TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA TMA TIP#ARBPOOI

LENGTH(mileslkm) 0/0.00

DESCRPT: EFFECTIVE CYCLING:PH3 CLASSES ON BIKE SAFETY& RESPONSIBILITY

OTH Share:
PE:NONE ROW: NONE CST: 2000 FED Share:

$41,000
$25,000 $20,000

PROJECT: 762624- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # AT ARBP293

. LENGTH(mileslkm) 1.512.42

DESCRPT: PEACHTREE HILLS FM PEACHTREE TO LINDBERGH & SIDEWALKS

OTHShare:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$5,000
$442,000 $353,600

PROJECT: 762625- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # M AR 254

LENGTH (miles/ km) 0/0.00

DESCRPT: MARTA: PED CONNECTION FM FINGER RESIDENTIAL TO N.SPRINGS STA

OTHShare:
PE:2000 . ROW: LOCL CST: 2000 FED Share:

$88,400 . $150,000 _
$850,000 .$680,000

OTH Share:

$170,000

- - - - - - - - - ' -S-T-AT-E-T-RA-N-SP-O-R-TA-T-IO-N-I~-i-p,RO.V.E-M-EN-T-i'iiOGii'AM

9116199 Page 128 of275

FULTON COUNTY

PROJECT: 762630- TYPE WORK: RECST/REHAB

FUND: STP

ATLANTATMATIP#ATI85

LENGTH (mileslkm)

DESCRPT: CHESHIRE BRIDGFlSR 13 @ LINDBERGH DRiSR 236

0/0.00

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$1,000,000 $800,000

PROJECT: 762632- TYPE WORK: RECST/REHAB

FUND: STP

ATLANTA TMA TIP # AT 184

LENGTH (mileslkm) 0/0.00

DESCRPT: PIEDMONT RDISR 237 @ SIDNEY MARCUS & LINDBERGH DR

OTfi Share:
PE:2000 ilOW:LOCL CST: 2000 FED Share:

$200,000 $42,000
$2,500,000 $2,000,000

PROJECT: 770277- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # AT 083

LENGTH (mileslkm) 0.5/0.81

DESCRPT: PRYOR STICS 2044 OVER CSX RR & MARTAFM ALABAMA TO WALL

OTHShare:
PE: 1992 ROW: LOCL CST: 2001 FED Share: GAShare:

$500,000 , UNDERWAY,'
, $807,000 $645,600 $161,400

PROJECT: 770301- TYPE WORK: PLANNING

FUND: OTHER

ATLANTA TMA TIP # AR 344A

LENGTH (miles I km) 0/0.00

DESCRPT: COMMUTER RAIL PROGRAM MANAGEMENT - PHASE 1 '

, PE:20oo ROW: NONE CST: NONE

$1,300,000

PROJECT: 770302- TYPE WORK: PLANNING

FUND: OTHER

ATLANTATMA TIP#AR344B

'LENGTH(mileslkm) 0/0.00

DESCRPT: COMMUTER RAIL PROGRAM MANAGEMENT - PHASE 2

PE:2001 ROW: NONE CST: NONE

$2,000,000

PROJECT: 770303- TYPE WORK: PLANNING

FUND: OTHER

ATLANTA TMA TIP # AR344C

LENGTH (mileslkm) 0/0.00

DESCRPT: COMMUTER RAIL PROGRAM MANAGEMENT - PHASE 3

PE:2002 ROW: NONE CST: NONE

$2,000,000

PROJECT: 770315- TYPE WORK: NEW CONSTRUCTION FUND: HPP

ATLANTA TMA TIP # AR269A

LENGTH(mileslkm) 0/0.00

DESCRPT: COMMUTER RAIL ATLANTA TO DACULA (ATHENS) PHASE I PROPOSED TCM ,

PROJECT: 770316- TYPE WORK: NEW CONSTRUCTION FUND: NHS

ATLANTA TMA TIP # AR 269B

LENGTH (miles I km) 0 10.00

DESCRPT: COMMUTER RAIL ATLANTA TO DACULA (ATHENS) PHASE 2

PROPOSED TCM

'

PROJECT: 77032Q.. TYPE WORK: NEW CONSTRUCTION FUND: HPP

ATL~A TMA TIP # AR'268A

' LENGTH(mileslkm) 0/0.00

DESCRPT: COMMUTER RAIL ATLANTA TO GRIFFIN (MACON) PHASE 1 PROPOSED TCM

PE:2000 ROW: 2000 CST: 2001 FED Share: GA Share:

$6,000,000 , $9,000,000 , $25,000,000 $20,000,000 , $5,000,000

PE:NONE ROW: 2001 CST: 2002 FED Share: GA Share:

$5,000,000 $55,000,000 $44,000,000 $11,000,000

PE:2000 ROW: 2000 CST: 2001 FED Share: GAShare:

$6,000,000 $6,000,000 $12,000,000 $9,600,000 $2,400,000

f

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199

Page 129 of275

.

'-,

FULTON COUNTY

;

I

PROJECT: 770321- TYPE WORK: NEW CONSTRUCTION FUND: NHS

PE:NONE

ATLANTA TMA TIP # AR 268B

LENGTH (miles I km) 0 10.00

ROW: 2001

$5,000,000 _

I

DESCRPT: COMMUTER RAIL ATLANTA TO GRIFFIN (MACON) PHASE 2 PROPOSED TCM

CST: 2002 FED Share:

$30,000,000 $24,000,000

.GA Share:

$6,000,000

I.~I.

PROJECT: 770873- TYPE WORK: SIGNALS

FUND: CMAQ

PE: NONE

ATLANTA TMA TIP # AR 20lB

LENGTH (miles I km) 0/0.00

ROW: NONE

.~.

DESCRPT: ATMS/ ARTERIAL ROUTES IN ATL-INSTALL COMM CABLE & HDWIDEKALB

CST: 2001

$1,000,000

It

FED Share:

$800,000

GA Share:

$200,000

:fl

i!i

PROJECT: 770900- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1996

UNDERWAY

01<.

ATLANTA TMA TIP # FN 095

LENGTH (miles I km) 0.22/0.35

ROW: LOCL

DESCRPT: CS 310llGRIMES BRIDGE ROAD @ BIG CREEK IN SOUTH ROSWELL

CST:20QI

$2,941,000

~jl

FED Share: GAShare:

$2,352,800 $588,200

PROJECT: 770923- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # FN AR 177C

LENGTH (miles I km) 1.2/1.93

DESCRPT: OLD ALABAMA FM RIVERSIDE DR TO MARKET BLVD

PE: 1995 ROW: NONE CST: 2000 FED Share:

PROJECT: 770933~ TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # FN AR 177B

LENGTH (miles I km) 1.3412.16

DESCRPT: HOLCOMB BR RD FM WEST OF BIG CK TO E OF SR 400(INCL BR'S)

OTH Share:
PE: 1995 ROW: NONE CST: 2000 FED Share:

PROJECT: 770954- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # MAR 151E

LENGTH (mileslkm) 0/0.00

DESCRPT: MARTA ADA PARATRANSITIRAIL STATION MODIFICATIONSI PHASE 7

OTH Share:
PE:NONE ROW: NONE CST: 2000 FED Share:

PROJECT: 771090- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 115

LENGTH(mileslkm) 0.2/0.32

DESCRPT: CR 34IFREEMANVILLE ROAD @ CHICKEN CREEK 2.5 MI N ALPHARETTA

OTHShare:
PE: 1998 ROW: LOCL CST:2000 . FED Share: GA Share:

UNDERWAY
$332,000 $265,600
$66,400 UNDERWAY
$385,000 $308,000
$77,000

$1,620,000 $1,296,000
$324,000 UNDERWAY
$550,000 $440,000 $110,000

PROJECT: 771101- TYPE WORK: SAFETY.

FUND: CMAQ

PE:NONE

ATLANTA TMA TIP # FN/SAR 193B

LENGTH(mileslkm) 0/0.00

ROW: NONE

DESCRPT: ATMS/ REPLACEMENT AND MAINTENANCE OF EDP EQUIPMENT - PHASE 2

CST: 2000

FED Share:

GA Share:

PROJECT: 771102- TYPE WORK: SAFETY

FUND: CMAQ

PE:NONE

ATLANTA TMA TIP # FN/S AR 193C

LENGTH (miles I km) 0/0.00

ROW: NONE

DESCRPT: ATMS/ REPLACEMENT AND MAINTENANCE OF EDP EQUIPMENT - PHASE 3

CST: 2001

FED Share:

GA Share:

$750,000 $600,000 $150,000
..
$1,000,000 $800,000 $200,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199 Page 1300{275

FULTON COUNTY

PROJECT: 771'103- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMATIP#AR286

LENGTH (miles/km) 0/0.00

"PE:NONE ' ROW:NONE

DESCRPT: ATMSI REPLACEMENT AND MAINTENANCE OF EDP EQUIPMENT - PHASE 4 '

CST: 2002

FED Share:

GAShare:

$1,000,000 $800,000 $200,000

PROJECT: 771112- TYPE WORK: OTHER

'FUND: CMAQ

' PE:NONE

ATLANTA TMA TIP # AR 238C

LENGTH (miles / km) 0/0.00

ROW: NONE

DESCRPT: VOLUNTEER OZONE ACTION PARTNERS(VOAP)MARKETING'PROG pHASE 3" , CST: 2000

FED Share:

$1,500,000 $1,200,000

'PROJECT: 771113- TYPE WORK: OTHER'

FUND:CMAQ

ATLANTA TMA TIP # AR 220B

LENGTH (titiles / km) 0/0.00

DESCRPT: UNIVERSITY RIDESHARE PROG {PHASE II}

.~

ASSOCIATED PROJECTS: 771032-

OTH Share:
PE:NONE ROW: NONE CST:'2000 FED Share: GAShare:

$300,000
, $1,000,000 $800,000 $200,000

PROJECT: 771117- TYPE WORK: ' RECSTIREHAB

FUND: CMAQ

ATLANTA TMA TIP # MAR 237A

LENGTH(miles/km) 0/0.00

DESCRPT: MARTA INTELLIGENT TRANSPORTATION SYSTEM - FLEET AVLS

'PE:NONE ROW: NONE CST: 2000 , FED Share:

$1,000,000 $800,000

PROJECT: 771120- TYPE WORK: ENHANCEMENT

. ' FUND: CMAQ'

ATLANTA TMA TIP # AT AR 177E

LENGTH (mileS/km) 0/0.00

DESCRPT: SIDEWALKS ON MOROSGO DRIVE

OTH Share:
PE:LOCL ROW: LOCL CST:'2000 FED Share:

$200,000
$75,000 $60,000

OTH Share:

$15,000

PROJECT: 771121- TYPE WORK: ENHANCEMENT

FUND: CMAQ

!

ATLANTA TMA TIP # FN AR 177E

LENGTH (miies/km) 0/0.00

PE:LOCL' ROW: LOCL

DESCRPT: SIDEWALKS ON PEACHTREE-DUNWOODY ROAD

CST: 2000

$125,000

FED Share:

$100,000

PROJECT: 771130- TYPE WORK: ,ENHANCEMENT

FUND: CMAQ

ATLANTATMA TIP # FS AR 177C

LENGTH'(miles/km) 0/0.00

DESCRPT: SIDEWALKS AND BIKE LANES ON US 291MAIN STREET IN UNIONCITY

OTH Share:
PE:LOCL ROW: LOCL , CST: 2000' FED Share:

$25,000
$375,000 $300,000

PROJECT: 771131- TYPE WORK:' 'ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # AT AR 177FLEiVGTH(miles/km) 0/0.00

DESCRPT: BICYCLE PARKING RACKS

OTH Share:
PE:LOCL ROW:LOCL CST: 2000 FED Share:

otnsso

PROJECT: 771140- TYPE WORK: OTHER

FUND:CMAQ

PE:NONE

ATLANTA TMA TIP#AR221B

LENGTH(miles'/km) 0/0.00

ROW: NONE

DESCRPT: START-UP FUNDS FOR TRANSPORTATION MANAGEMENT ASSN-TMA PH-2

CST: 2000

,.

FED Share:

OTH Share:

$75,000
, . $63,000 $50,400 $12,600
$1,000,000 $800,000 $200,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 1310/275

FULTON COUNTY

PROJECT: 771141- TYPE WORK: OTHER

FUND: CMAQ

ATLANTA TMA TIP#AR221C

LENGTH (mileslkm) 0/0.00

DESCRPT: START-UP FUNDS FOR TRANSPORTATION MANAGEMENT ASSN-TMA PH-3

PE:NONE ROW: NONE CST: 2001 FED Share:

PROJECT: 771144- TYPE WORK: RECSTIREHAB

FUND: CMAQ

ATLANTA TMA TIP # AR 297A

LENGTH (miles I km) 0 10.00

DESCRPT: CLEAN AIR CAMPAIGN (AIR QUALITY INFORMATION PROGRAM) YEAR 2

OTH Share:
PE:NONE ROW: NONE CST: 2000 FED Share:

$1,000,000 $800,000
4,
$200,000
$2,500,000 , $2,000,000

. PROJECT: 771145- . TYPE WORK: RECSTIREHAB

FUND: CMAQ

ATLANTA TMA TIP # AR 297B

LENGTH (miles I km) 0/0.00

DESCRPT: CLEAN AIR CAMPAIGN (AIR QUALITY INFORMATION PROGRAM) YEAR 3

OTHShare:
PE:NONE ROW: NONE CST: 2001 FED Share:

$500,000
$2,500,000 $2,000,000

PROJECT: 771146- TYPE WORK: RECSTIREHAB

FUND: CMAQ

ATLANTA TMA TIP # AR 297C

LENGTH (miles I km) 0/0.00

DESCRPT: CLEAN AIR CAMPAIGN (AIR QUALITY INFORMATION PROGRAM) YEAR 4

OTH Share:
PE:NONE ROW: NONE CST: 2002 FED Share:

$500,000
$2,500,000 $2,000,000

PROJECT: 771147- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP#AR287A

LENGTH(mileslkm) 0/0.00

DESCRPT: CLEAN AIR SPECIAL INITATIVE - YEAR I

OTHShare: ,
PE:NONE ROW: NONE CST: 2000 FED Share:

$500,000
$2,000,000 $1,600,000

OTHShare:

$400,000

~...~
.~"":t j

PROJECT: 771148- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AR 287B

LENGTH (miles I km) 0/0.00

DESCRPT: CLEAN AIR SPECIAL,INITATIVE - YEAR 2

PE:NONE ROW: NONE CST: 2001

~
$2,000,000

FED Share:

$1,600,000

PROJECT: 771149- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP#AR287C

LENGTH(mileslkm) 0/0.00

DESCRPT: CLEAN AIR SPECIAL INITATIVE - YEAR 3

OTHShare:
PE:NONE ROW: NONE CST: 2002 FED Share:

$400,000
$2,000,000 $1,600,000

PROJECT: 771200- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 166

LENGTH(mileslkm) 0.2/0.32

DESCRPT: CR 188IUPPER HEMBREE ROAD @FOE KILLER CREEK 2 MI SW OF ALPH

OTHShare:
PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

PROJECT: 771228- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN ARBP014

cLENGTH (miles Ikm) 0/0.00

DESCRPT: MANSELL ROAD/CR 126 FROM BIG CREEK TO MARTA PARKING LOT

PE:LOCL' ROW: LOCL CST: 2000 FED Share:

$400,000 $5,000
$228,000 $182,400 $45,600
.
$981,000 $784,800

OTHShare:

$196,200

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9//6/99 Page 131of175

FULTON COUNTY

PROJECT: 771240- TYPE WORK:' ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FN AR BPO15 .

LENGTH (miles / km) 0/0.00

DESCRPT: AZALEA DRIVEIFROM WILLEO ROAD TO SR 9IROSWELL ROAD

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$812,000 $649,600

PROJECT: 771250- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # FS AR BP028

LENGTH (miles / km) 0 /0.00

DESCRPT: ON-STREET BICYCLE & PEDESTRIAN WALKS & TRAILS/COLLEGE PARK

OTR Share:
. PE:LOCL ROW: LOCL CST: 2000 FED Share:

$162,400
$504,QOO $403,200

PROJECT: 771252- TYPE WORK: ENHANCEMENT

FUND: STP

.ATLANTA TMA TIP # AT AR BP098A .

LENGTH (miles / km) 0/0.00

DESCRPT: ATLANTA-WEST END RAIL-TRAIL

OTH Share:
PE:LOCL' ROW: LOCL CST: 2000 FED Share:

$100,800
$500,000 $400,000

PROJECT: 771254- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT ARBP270

.LENGTH (miles/km) 0/0.00

.DESCRPT: METROPOLITAN PARKWAY STREETS CAPE

OTH Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$100,000
$625,000 $500,000

PROJECT: 771256- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT ARBP017

LENGTH (miles/km) 0/0.00

DESCRPT: PRYOR ROAD MULTI-USE TRAIL

OTHShare:
PE:LOCL. ROW: LOCL CST: 2000 FED,Share:

$125,000
$125,000 $100,000

PROJECT: 771258- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # AT 165

LENGTH (miles/km) 0/0.00

DESCRPT: PIEDMONT AVE STREETSCAPE AND PARK ACCESS

OTH Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$2?,000
$325,000 $260,000

PROJECT: 771260- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMATIP # FS AR BP007 ' . .

LENGTH (miles / km) 0/0.00

DESCRPT: UNION CITY MULTI-USE TRAILS AND PEDESTRIAN FACILITIES

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$65,000
$1,350,000 $1,080,000

PROJECT: 771270~ TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FN 165 .

LENGTH (miles / km) 0.2 /0.32

DESCRPT: CR 85/KIMBALL BRIDGE RD. @ BIG CREEK 2 MISE OF ALPHARETTA

OTR Share:
PE:2000 ROW: LOCL CST: 2002 FED Share: GA Share:

$270,000 $22,000
$433,000 $346,400 $86,600

PROJECT: 771271- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FS 139

LENGTH (miles / km) 0.2 /0.32

DESCRPT: CR 13901RICOROAD @ MOSS CREEK 6 MI NW OF PALMETTO

PE:2000 ROW: LOCL CST: 2002 FED Share: GA Share:

$10,000
$134,000 $107,200
$26,800

I I I
(,
11
ft
~:
JiJt.:-
w
~
I'
I
B
m
m

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99 Page 133 of275

FULTON COUNTY

PROJECT: 771272- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FS 141

LENGTH (mileslkm) 0.21/0.34

DESCRPT: CR 485IENON ROAD @CAMP CREEK 12 MI W OF ATLANTA

PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

$19,000

$387,000 $309,600 $77,400

. PROJECT: 771273- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FS 144

LENGTH (miles I km) 0.210.32

DESCRPT: CR 629/JOHNSON ROAD @ PEEKS CREEK 1 MI E OF PALMETTO

PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

$10,000
$177,000 $141,600
$35,400

PROJECT: 771274- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP#FN 168

LENGTH (mileslkm) 0.21/0.34

DESCRPT: _CR 27IPROVIDENCE ROAD @ COOPER SANDY CREEK 5 MI NW OF ALPHAR

PE:2000 ROW: LOCL CST: 2002 FED Share: GAShare:

$30,000
$598,000 $478,400 $119,600

PROJECT: 771275- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # FS 140

LENGTH (mileslkm) 0.19/0.31

DESCRPT: CR 1392/COCHRAN MILL ROAD @ PEA CREEK 7 MI NW OF PALMETTO

PE:20oo ROW:.LOCL CST: 2002 FED Share: GAShare:

$10,000
$129,000 $103,200 $25,800

PROJECT: 771276- TYPE WORK: REPLACE BRIDGE

FUND: STP

ATLANTA TMA TIP # FS 143

LENGTH (miles/km) 0.19/0.31

DESCRPT:CR 1392/COCHRAN MILL ROAD @ LITTLE PEA CREEK NW OF PALMETTO

PE:2000 ROW:LOCL CST: 2002 FED Share: GAShare:

$10,000
$129,000 $103,200
$25,800

PROJECT: 771285- TYPE WORK: OTHER

FUND: STP

ATLANTA TMA TIP#MAR252B

LENGTH(miles/km) 0/0.00

DESCRPT: MARTA: LAREDO CNG REFUELING STATION: PHASE 2

PROJECT: 771286- TYPE WORK: OTHER

FUND: STP

ATLANTA TMA TIP # MAR255

LENGTH(miles/km) 0/0.00

DESCRPT: MARTA: HAMILTON CNG REFUELING STATION

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:2000
ROW:LOCL CST: NONE

~
$2,500,000 $2,000,000
$500,000 $5,000,000

PROJECT: 771287- TYPE WORK: VEHICLE PURCHASE

FUND: STP

ATLANTA TMA TIP # MAR253

LENGTH (miles/km) 0/0.00

DESCRPT: MARTA: PURCHASE 50-60 CNG BUSES

PE:NONE ROW: NONE CST: 2000 FED Share:

OTHShare:

PROJECT: 771290- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP # AR 30SA

LENGTH (miles I km) 0/0.00

DESCRPT: ATMS/ MAINTENANCE OF METRO ATLANTA ATMS EQUIPMENT - PHASE 1

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$19,550,000 ' $15,640,000
$3,910,000
$2,000,000 $1,600,000
$400,000

- - - - - - - - - _ . _ ._._- - - - - - - - - - - - - - - - - - - - - - - -

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199

Page 134 of275

FULTON COUNTY

PROJECT: 771291- TYPE WORK: SAFETY

FUND: NHS

PE:NONE

ATLANTA TMA TIP # AR 308B

. LENGTH (miles I km) 0 10.00

DESCRPT: ATMS/ MAINTENANCE OF METRO ATLANTA ATMS EQUIPMENT - PHASE 2

ROW: NONE CST: 2001 FED Share: GAShare:

$2,000,000 $1,600,000
$400,000

PROJECT: 771292- TYPE WORK: .SAFETY

FUND: NHS .

ATLANTA TMA TIP#AR308C

LENGTH (mileslkm) 0/0.00

DESCRPT: ATMS/ MAINTENANCE OF METRO ATLANTAATMS EQUIPMENT - PHASE 3

PE:NONE ROW: NONE CST:2002 . FED Share: GAShare:

. $2,000,QOO $1,600,000 $400,000

PROJECT: 771300- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP # FN 023

LENGTH (miles I km) 0 10.00

DESCRPT: ATMS/ ITS OPERATIONS AND SUPPORT IN THE ATLANTA REGION -PH 1

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

..
$6,000,000 $4,800,000 $1,200,000

PROJECT: 771301- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP#AR3IOB

LENGTH (mileslkin) 0/0.00

DESCRPT: ATMS/ ITS OPERATIONS AND SUPPORT IN THE ATLANTA REGION -PH 2

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

$6,250,000 $5,000,000 $1,250,000

PROJECT: 771302- TYPE WORK: SAFETY

FUND: NHS

ATLANTATMA TIP#AR311C

LENGTH (mileslkm) 0/0.00

DESCRPT:. ATMS/ ITS OPERATIONS AND SUPPORT IN THE ATLANTA REGION -PH 3

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$6,500,000 $5,200,000 . $1,300,000

PROJECT: 771305- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP # AR 312A

,LENGTH (miles I km) 0 10.00

DESCRPT: HERO OPERATIONS AND SUPPORT IN THE ATLANTA REGION - PHASE] .

PE:NONE . ROW:NONE
CST: 2000 FED Share:
GA Share:

$2,700,000 $2,160,000
$540,000

PROJECT: 771306- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP # AR313B

LENGTH (mileslkm) 0/0.00

DESCRPT: HERO OPERATIONS AND SUPPORT IN THE ATLANTA REGION - PHASE 2

PE:NONE ROW: NONE .CST: 2001 FED Share: GA Share:

$2,800,000 $2,240,000
$560,000

PROJECT: 771307- TYPE WORK: SAFETY

FUND: NHS

ATLANTA TMA TIP # AR 313C

LENGTH (miles I km) 0/0.00

DESCRPT: HERO OPERATIONS AND SUPPORT IN THE ATLANTA REGION - PHASE 3

PE:NONE ROW: NONE . CST:2002 FED Share: GAShare:

$2,900,000 $2,320,000
$580,000

PROJECT: 771310- TYPE WORK: SAFETY
>.,3

FUND: OTHER

ATLANTA TMA TIP # FN AR200

LENGTH(mileslkm) 0/0.00

PE:2000 ROW:NONE .

$3,166,000 '

DESCRPT: ATMS/ INTELLIGENT TRANSPORTATION 'SYSTEMS INTEGRATION PROGRAM . CST: NONE

:., i'1

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

9/16/99

Page 1350f275

FULTON COUNTY
PROJECT: 771320- TYPE WORK: VEHICLE PURCHASE

\
FUND: NHS

ATLANTA TMA TIP # MAR 246

LENGTH (miles / km) 0/0.00

DESCRPT: PURCHASE OF NEW CNG BUSES FOR MARTA; & DEKALB 77132X

PE:LOCL ROW: LOCL CST: 2000 FED Share:

oTil Share:

PROJECT: 771330- TYPE WORK: PLANNING

FUND: OTHER

PE: 2000

ATLANTA TMA TIP#AR301A

LENGTH (miles/km) 0/0.00

ROW: NONE

DESCRPT: MAG-LEV TRANSPORTATION TECHNOLOGY DEPLOYMENT PROGRAM &77Y330 CST: NONE

..
$25,000,000 .:.$20,000,000
.
$5,000,000 ~.
$3,000,000

ASSOCIATED PROJECTS: 77Y330-

PROJECT: 771331- TYPE WORK: OTHER

FUND: CMAQ

PE:NONE

'. ATLANTA TMA TIP # AR 288

LENGTH (miles / km) 0/0.00

ROW: NONE

DESCRPT: REGIONAL TRANSPORTATION COORDINATOR:ONSITE EMPLOYER-BASE TDM CST: 2001

FED Share:

$450,000 $450,000

.[

PROJECT: 771332- TYPE WORK: PLANNING

FUND: CMAQ

ATLANTA TMA TIP # AR 299

LENGTH (miles / km) 0/0.00

PE:2000 ROW: NONE

$50,000

DESCRPT: CENTRAL ATL. PROGRAM TRANSPORTATION STUDY-WESTSIDE PROJECTS

CST: NONE

If

I

PROJECT: 771333- TYPE WORK: OTHER

f"UND: STP

ATLANTA TMA TIP#AR300A

LENGTH (miles/km) 0/0.00

DESCRPT: PARTNERSHIP FOR SMOG FREE GA (PSG) PH 4

PE:NONE ROW: NONE CST: 2001

$3,000,000

I

.FED Share: OTHShare:

$2,400,000 $600,000

PROJECT: 771334- TYPE WORK: OTHER

FUND: STP

I

ATLANTA TMA TIP#AR300B

LENGTH (miles/km)

DESCRPT: PARTNERSHIP FOR SMOG FREE GA (pSG) PH 5

0/0.00

PE:NONE ROW: NONE CST: 2002

$4,000,000

u

FED Share:

$3,200,000

i

OTHShare:

$800,000

PROJECT: 771335- TYPE WORK: OTHER

FUND: CMAQ

PE:NONE

I

ATLANTA TMA TIP # AR 291A

LENGTH (miles / km) 0/0.00

DESCRPT: STATE EMPLOYEE COMMUTER ASST & TRANSIT INCENTIVE PRGM: PH 2

ROW: NONE CST: 2001

$500,000

.FED Share:

$400,000

ft

I

PROJECT: 771336- TYPE WORK: OTHER

FUND: CMAQ

OTHShare: PE:NONE

$100,000

ATLANTA TMA TIP#AR291B

LENGTH (miles/km) 0/0.00

ROW: NONE

DESCRPT: STATE EMPLOYEE COMMUTER ASST & TRANSIT INCENTIVE PRGM: PH 3

CST: 2002

$500,000

FED Share:

$400,000

I~i'

PROJECT: 771337- TYPE WORK: OTHER

FUND: CMAQ

OTHShare: PE:NONE

. $100,000

ATLANTA TMA TIP#AR285

LENGTH (miles/km) 0/0.00

ROW: NONE

DESCRPT: ALT FUEL VEHICLE INCREMENTAL COST INCENTIVE PRGM

CST: 2001

$500,000

FED Share:

$400,000

OTHShare:

$100,000

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99 Page 136 iJf275

FULTON COUNTY

PROJECT: 771338- TYPE WORK: OTHER

FUND: CMAQ

PEt NONE-

ATLANTA TMA TIP # AR283

LENGTH (miles/km) 0/0.00

ROW: NONE

DESCRPT: ALT FUEL TARGETED FLEET VEHICLE TURNOVER PRGM & TAXIS;SHUTTL

CST: 2001

FED Share:

$500,000 $400,000

- PROJECT: 7.71339- TYPE WORK: OTHER

. FUND: CMAQ

ATLANTA TMA TIP # AR 289

LENGTH (miles /km) 0/0.00

DESCRPT: CLEAN/ALT FUEL TECHNOLOGIES EDUCATION & OUTREACH PRGM

OTHShare:
PE:NONE ROW: NONE CST: 2001 FED Share:

$100,000
$60,000 $48,000

PROJECT: 771340- TYPE WORK: . NEW CONSTRUCTION FUND: STP

ATLANTA TMA TIP # AT AR BP281

LENGTH (miles / km) 1 /1.61

DESCRPT: PRYOR RD STREETSCAPE FM CLAIRE DR TO UNIVERSITY AVE

OTR Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$12,000
- $241,000 $192,800

PROJECT: 771342- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA.TMA TIP # M AR 257

LENGTH (miles / km) 0/0.00

DESCRPT: PED TUNNEL FM SANDY SPRINGS STAnON TO N PARK OFFICE COMPLEX

OTR Share:
PE:2oo0 ROW: LOCL, CST: 2000 FED Share:

$48,200 $1,000,000
$3,000,000 $2,400,000

PROJECT: 771350- TYPE WORK: 'OTHER

FUND: CMAQ

ATLANTA TMA TIP # MAR 250A

LENGTH (miles /km) 0/0.00

DESCRPT:, MARTA AUTOMATED IRAVELER INFO SYSTEM & OTHER ITS: PH 1 ..

OTHShare:
PE:NONE ROW: NONE CST: 2000 FED Share:

$600,000
$2,000,000 $1,600,000

OTH Share:

$400,000

PROJECT: 771351- TYPE WORK: OTHER

FUND: CMAQ



ATLANTA TMA TIP # MAR250B

LENGTH(mileslkm) 0/0.00

PE:NONE ROW: NONE

DESCRPT: MARTA AUTOMATED IRAVELER INFO SYSTEM & OTHER ITS: PH 2

CST: 2001

$2,000,000

FED Share:

$1,600,000

PROJECT: 771352- TYPE WORK: ,OTHER

FUND: CMAQ

ATLANTA TMA TIP # M AR250C

LENGTH(nuleslkm) 0/0.00

DESCRPT: MARTA AUTOMATED IRAVELER INFO SYSTEM & OTHER ITS: PH j

OTHShare:
PE:NONE ROW: NONE CST: 2002 FED Share:

$400,000
$2,000,000 ' $1,600,000

OTHShare:

PROJECT: 771353- TYPE WORK: OTHER,

FUND: CMAQ

PE: NONE

ATLANTA TMA TIP # AR290

LENGTH(mileslkm) 0/0.00

.ROW: NONE

DESCRPT: COMMUTE CONNECTIONS TRANSIT &CARPOOL SUBSIDIES FOR EMPLOYEES CST: 2000

FED Share:

$400,000
$22,000 $22,000

PROJECT: 771354- TYPE WORK: OTHER

FUND: CMAQ

ATLANT A TMA TIP # AR 159B

LENGTH (miles I km) 0 10.00

.,'DESCRPT: REGIONAL RIDESHARE PROGRAM-COMMuTE CONNECTIONS- PH 1

PE:NONE ROW: NONE , CST: 2001 FED Share:

$1,500,000 $1,500,000

I

stATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199

Page 137 of275

I

PULTON COUNTY

PROJECT: 771355- TYPE WORK: OTHI;R

FUND: CMAQ

PE:NONE

I

ATLANTA TMA TIP # AR 159C

LENGTH (miles I km) 0 10.00

DESCRPT: REGIONAL RIDESHARE PROGRAM-COMMUTE CONNECTIONS PH 2

ROW: NONE CST: 2002 FED Share:

"
$1,500,000
$1,500,000

I

PROJECT: 771356- TYPE WORK: NEW CONSTRUCTION FUND: STP

PE: LOCL

ATLANTA TMA TIP# MAR258

LENGTH (mileslkm) 0/0.00

ROW: LOCL

I

DESCRPT: PEDESTRAIN TUNNEL FM MIDTOWN MARTA STAT TO FED RESERVE BANK

CST: 2000

FED Share:

$5,000,QOO $4,000,000

OTHShare:

PROJECT: 771360- TYPE WORK: OTHER

FUND: CMAQ

ATLANTA TMA TIP # AR 292

LENGTH (miles I km) 0/0.00

DESCRPT: EMPLOYER ASSISTANCE TO PROMOTE TRAVEL DEMAND MANAGEMENT

PE:NONE ROW:NONE. CST: 2001 FED Share:

$1,000,000
$150,000 $150,000

PROJECT: 771361- TYPE WORK: PLANNING

FUND: STP

ATLANTA TMA TIP # AR 298

LENGTH (miles I km) 0 10.00

DESCRPT: MIDTOWN PARKING & TRANSIT STUDY

PE:2000 ROW: NONE CST: NONE

$100,000

PROJECT: 771362- TYPE WORK: PLANNING

FUND: CMAQ

PE:2000

$100,000

ATLANTA TMA TIP # AR 293

LENGTH (miles I km) 0 10.00

ROW: NONE

DESCRPT: ID & PRIORITIZATION OF TRANS MANAGEMENT ASSOC & INITIATIVES

CST: NONE

..

If.i

PROJECT: 771363- TYPE WORK: OTHER

FUND: CMAQ

ATLANTA TMA TIP # AR 296

LENGTH (miles I km) 0 10.00

DESCRPT: REGIONAL VANPOOL SUBSIDY PRGM:APPROX 50 COMMUTER VANPOOLS

PE:NONE ROW: NONE CST: 2001 FED Share:

.'
$270,000 $270,000

PROJECT: 771364- TYPE WORK: OTHER

FUND: CMAQ

ATLANTA TMA TIP # AT AR BP290

LENGTH (miles I km) 0 10.00

DESCRPT: PEDESTRAIN SAFETY & AWARENESS CAMPAIGN

PE:NONE ROW: NONE CST: 2000 FED Share:

PROJECT: 771365- TYPE WORK: SAFETY

FUND: STP

ATLANTA TMA TIP # FN 162

LENGTH (miles I km) 0 10.00

DESCRPT: ATMS: MODERNIZING FULTON CO PRGM & UPDATE OF EDP

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

01'8 Share:

PROJECT: 771366- TYPE WORK: OTHER

FUND: CMAQ

PE:NONE

ATLANTA TMA TIP # AR280A

LENGTH (miles I km) 0/0.00

ROW: NONE

DESCRPT: ALT FUEL REVOLVING LOAN PRGM TO FUND FLEET;INFRASTRUCTURE;Pl

CST: 2000

FED Share:

OTHShare:

$100,000 $80,000
$20,000 $180,000
$2,000,000 .;.~
$1,600,000
$400,000
.~
$1,067,000 $853,600
$213,400

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 138 of275

FULTON COUNTY

PROJECT: 771367- TYPE WORK: OTHER

FUND: CMAQ

PE: NONE

ATLANTATMA TIP#AR280B

LENGTH (mileslkm) 0/0.00

ROW: NONE

DESCRPT: ALTFUEL REVOLVING LOAN PRGM TO FUND FLEET;INFRASTRUCTURE;P2

CST: 2001

FED Share:

$1,067,000 $853,600

OTHShare:

PROJECT.~ 771368-

TYPE WORK: OTHER

FUND: CMAQ

PE: NONE;

ATLANTA TMA TIP # AR 280C

LENGTH (miles I kin) 0/0.00

. ROW: NONE

DESCRPT: ALT FUEL REVOLVING LOAN PRGM TO FUND FLEET;INFRASTRUCTURE;P3

CST: 2002

:FEDShare:

$213,400
$1,067,000 $853,600

OTHShare:

PROJECT: 77Y330- TYPE WORK: PLANNING

FUND: STP

ATLANTA TMA TIP # AR301

LENGTH (mi/eslkm) 0/0.00

DESCRPT: MAG-LEV TRANSPORTATION TECHNOLOGY DEPLOYMENT PROG.SEE 771330

PE:2000 ROW: NONE CST: NONE

$213,400 $1,000,000

ASSOCIATED PROJECTS: 771330-

PROJECT: ssuno- TYPE WORK: PLANNING

FUND: HPP

ATLANTA TMA TIP # AR 267

. LENGTH (mileSI km) 0/0.00

DESCRPT: TRANS AL T STUDY FM ATLANTA TO CRAITANOOGA(ATLANTA $)860110

PE:'2000 ROW: NONE CST: NONE

$1,875,000 .

PROJECT: 999995- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP #

LENGTH (miles I km)

I

..

DESCRPT: FUNDING CURRENTLY UNASSIGNED



END OF FULTON COUNTY

PE:NONE

ROW: NONE

CST: 2002

$0

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199 Page 139 of175

GILMER COUNTY

PROJECT: 62214X- TYPE WORK: TURN LANES

FUND: NHS

LENGTH (miles / km) 22.1 /35.52

DESCRPT: SRS15 FM 1-575 THRU GILMER TO TOTEHEROW RD/FANNINISEE PICKEN

PE:NONE ROW: NONE CST: NONE

ASSOCIATED PROJECTS: 622140-

PROJECT: 63 I580- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.3 /0.48

DESCRPT: SR 282 BRIDGE REPLACEMENT OVER TAILS CREEK WEST OF ELLIJAY

PE: 1998 ROW:2001 CST:

UNDERWAY $36,000
AFTERZ002

I:ffi.

PE:2000

$58,000

ROW:

AFTER 2002

CST:

AFTER 2002

END OF GILMER COUNTY

...
.'

,-----------------------------------------~~----

-------------------------------------_.

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199

Page 140 of275

GLASCOCK COUNTY

PROJECT: '245345- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.21 /0.34 DESCRPT: SR 102 @ JOES CREEK 2.2 MI SE OF MITCHELL

PE:2000 ROW: 2002 CST:

$20,000 $10,000 AFTER 2002

;;

PROJECT: 245346- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.29/0.47

DESCRPT: SR 171@ ROCKY COMFORT CREEK AT GIBSON N CITY LIMIT

PE:2000 ROW: CST:

$36,000 AFTER 2002
AFTER~002

PROJECT: 245347- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 171@ ROCKY COMFORT CREEK Off 1.8 MI NE OF GIBSON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 271290- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: CITY OF MITCHELL RR DEPOT REHAB & LANDSCAPING

END OF GLASCOCK COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTH Share:

$200,000 $160,000
$40,000



... .

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 1410/275

GLYNN COUNTY

PROJECT: 0000075 TYPE WORK: ENHANCEMENT

FUND: STP

BRUNSWICK TIP #

LENGTH (miles / km) 0 /0.00

DESCRPT: SPUR 25 CORRIDOR BEAUTIFICATION & PEDIBIKE ROUTE

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$500,000 $400,000

PROJECT: 511 100- TYPE WORK: RECSTIREHAB

FUND: NHS

BRUNSWICK TIP # BATS93-10

LENGTH (miles / km) 7.77 / 12.51

DESCRPT: 1-95 FM US 341 TO ALTAMARA RIVER @ MCINTOSH COUNTY LINE

EXIST. LANES: 04 PROPOSED LANES: 06

OTH Share:
PE: 1993 ROW: 2000 CST:

$100,000
UNDERWAY $8,000
AFTER 2002

PROJECT: 511420- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.63 /1.01
DESCRPT: 1-95 AT SR 520lUS 17/0CEAN HIGHWAY LUMPSUM PROJECT

PE: 1999 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
. $309,000 $278,100
$30,900

PROJECT: 520890- TYPE WORK: RECSTIREHAB

FUND: STP

BRUNSWICK TIP # BATS93-05

LENGTH (miles / km) 1.88 /3.03

DESCRPT: SR 25IBRUNSWICK FM S OF TORRAS CAUSEWAY N TO SR 25 SPUR

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1992 ROW: 1995 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $4,811,000 $3,848,800
$962,200

PROJECT: 522042- TYPE WORK: RECSTIREHAB

FUND: OTHER

BRUNSWICK TIP # BATS96-05

LENGTH (miles / km) 0/0.00

DESCRPT: SR 25IBRUNSWICK REMOVAL OF OLD SIDNEY LANIER BRIDGE

PROJECT: 522730- TYPE WORK: IMPROVE INTERSECTION FUND: STP

BRUNSWICK TIP # BATS94-08

LENGTH (miles / km) 0.27/0.43

DESCRPT: SR 25 @ CS 427/TALMADGE AVE & SR 25C/GLOUCESTER STIBRUNSWICK

EXIST. LANES: 04 PROPOSED LANES: 05

PE: 1991 ROW: NONE CST: 2000 FED Share: . GAShare: OTHShare:
PE: 1995 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$7,924,000 $3,169,600
$792,400 $3,962,000 UNDERWAY
$450,000 $405,000
$45,000

PROJECT: 523190- TYPE WORK: NEW CONSTRUCTION FUND: NHS

BRUNSWICK TIP # 00-01

LENGTH (miles / km) 0.2 /0.32

DESCRPT: SR 520/SR 25IUS 17 FLYOVER BRIDGE AT COLONEL'S ISLAND @RR

PE:2000 ROW:LOCL CST:

$50,000 AFTER 2002

PROJECT: 533140- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

BRUNSWICK TIP # 00-02

LENGTH (miles / km) 0.25 /0.40

DESCRPT: SR 520/JEKYLL ISLAND ROAD @ CEDAR CREEK 1.5 MI SE OF SR 25

PE:2000 ROW: 2002 CST:

$40,000 $10,000 AFTER 2002

PROJECT: 550540- TYPE WORK: RECSTIREHAB

FUND: STP

BRUNSWICK TIP # BATS93-18

LENGTH (miles / km) 0.62 / 1.00

DESCRPT: CR 381/AIRPORT ROAD FROM DEMERE TO DEMERE ROAD & ADD MEDIAN

PE:2002 ROW: LOCL CST:

$60,000 AFTER 2002

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

GLYNN CO'uNTY

. PROJECT: 562120- TY,PE WORK: NEW'CONSTRUCTION' FUND: STATE

BRUNSWICK TIP # BATS96-06"

: LENGTH (miles I km) 1.4512.33

'DESCRPT: SR 520 OVER LATHAM RIVER AT ONE LOCATION ON JEKYLL CAUSEWAY

PE: 1999 ROW: 2000. CST: 2000

9116199' Page 142 0[275
UNDERWAY , $182,000 $2,505,000

GA Share: OTHShare:

PROJECT: 571400- TYPE WORK:' ENHANCEMENT

FUND:STP .

BRUNSWICK TIP #

LENGTH (miles I km) 0/0,00

DESCRPT: ALTAMAHA BLVD PEDIBIKE PATH FM US 17 TO SPUR 25IBRUNSWiCK "

, PE:LOCL'

ROW: LOCL

.

CST: 2000

. FEDShare:

$626,000 $1,879,000
$250,QOO . $200,000

PROJECT: 571422- TYPE WORK:' ENHANCEMENT'

FUND: STP

BRUNSWICK TIP # 00-06

LENGTH (miles / km) 0/0.00

DESCRPT: REHABILITATION OF US COAST GUARD STATION ON SAINT SIMONS ISL

OTH Share:
PE:LOCL ROW: LOCL , CST:2000 FED Share:

$50,000
$500,000 $400,000

OTH Share:

PROJECT: DNR255- TYPE WORK: NEW CONSTRUCTION FUND: REC TRAILS

PE:NONE

BRUNSWICK TIP # '

LENGTH (miles / km) 0 10.00

ROW: NONE

DESCRPT: DNR REC TRAILS PROG ~ALTAMAHA PARK RECREATIONAL TRAIL

CST: 2000

, FEDShare:

$100,000
$125,000 $100,000

END OF GLYNN COUNTY

OTHShare:

$25,000

.'

--------------------------------------,-

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

Page 1430f275

GORDON COUNTY

PROJECT: 610750- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles / km) 0.5 10.81

DESCRPT: 1-75 @SR 156 IN CALHOUN

EXIST. LANES: 03 PROPOSED LANES: 05

PE: 1992 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $2,250,000 $5,900,000 $5,310,000 $590,000

PROJECT: 610755- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 1.53/2.46

DESCRPT: 1-75 @ SR 225 N OF CALHOUN (INCLUDING 1-75 BRIDGE)

8

PROJECT: 620780- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1.6512.66

DESCRPT: SR 3IUS 41 FM S OF SR 156 N TO CALHOUN BYP IN CALHOUN

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 1998 CST: 2000 FED Share: GA Share:
PE: 1992 ROW: 2000 CST:

UNDERWAY UNDERWAY $2,379,000 $1,903,200
$475,800
UNDERWAY $5,513,000 AFTER 2002

PROJECT: 621360- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH(mileslkm) 0.7/1.13

DESCRPT: SR 3IUS 41 FM LINE ST. TO N OF SR I56lREDBUD RD IN CALHOUN

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 621540- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 3.2515.23

DESCRPT: SR53 WB MP 14.67-15.8IEB MP 15.84-16.69IEB MP 18.1-19.37

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 621545-

PROJECT: 621545- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.26/0.42

DESCRPT: SR 53 @ PINE LOG CREEK

ASSOCIATED PROJECTS: 621540-

PROJECT: 632905 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.24/0.39

DESCRPT: SR 53 @ SALACOA CREEK 1 MI WEST OF FAIRMOUNT

PE:NONE ROW: 2000 CST: 2001
GAShare:

$3,630,000 $1,309,000
$1,309,000

PE: 1992 ROW: 1998 CST: 2000 FED Share: GA Share:

UNDERWAY

UNDERWAY

$1,086,000

$868,800 $217,200



PE: 1992 ROW: 1998 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$809,000 $647,200 $161,800

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 632906- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.32 /0.52

DESCRPT: SR 225 @ COOSAWATTEE RIVER 4 MI NE OF CALHOUN

PE:2000 ROW: CST:

$40,000 .AFTER2002 AFTER 2002

PROJECT: 642390- TYPE WORK: REPLACEBRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.27 10.43

DESCRPT: SR 156 @ SALACOA CREEK 6 MI NW OF RANGER

PE:2000 ROW: 2002 CST:

$27,000 '.
$10,000 AFTER 2002

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99 Page 144 of275

GORDON COUNTY

.,

PROJECT: 642391-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26/0.42

. DESCRPT: SR 156 @ OOTHKALOOGA CREEK 1 MI WEST OF CALHOUN

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 671165- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.25 /0.40

DESCRPT: CR 233/KNIGHT BOTIOM ROAD @SALACOA CREEK 4.4 MI W OF RANGER

PE: 1998 ROW: LOCL .. CST:2002 FED Share: GAShare:

END OF GORDON COUNTY

UNDERWAY ..
$273,000 $218,400 $54,600

I

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

Page 1450f275

I

GRADY COUNTY

PROJECT: 431550- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1995

UNDERWAY

LENGTH (miles I km) 0.21 10.34

ROW: 2000

$20,000

I

DESCRPT: SR 111 @ TIRED CREEK & OVERFLOW SOUTH OF CAIRO

CST: 2000 FED Share:

$1,458,000 $1,166,400

GAShare:

$291,600

I

PROJECT: 431800- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1997

UNDERWAY

LENGTH (miles I km) 0.22/0.35

ROW: 2001

$10,000

n

DESCRPT: SR 112/PELHAM ROAD @ SAPP CREEK APP 5 MI N OF CAIRO

CST:

AFTER 2002

R:

PROJECT: 432120- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles I km) 0.21 10.34

ROW:

AFTER 2002

DESCRPT: SR 93- SR 111 @ GIN BRANCH APP 2 MI N OF CAIRO

CST:

AFTER 2002

PROJECT: 471432- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0/0.00

DESCRPT: MULTI-USE TRAILS IN THE CITY OF CAIRO

END OF GRADY COUNTY

PE:LOCL ROW:LOCL CST: 2000 FED Share:
OTHShare:

$334,000 $267,200
$66,800



STATE TRANSPORTATION IMPROVEMENT PROGRAM

9//6/99 Page 146 of275

GREENE COUNTY

PROJECT: 0000151 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: LAKE'OCONEE PARKWAY GATEWAY ENHANCE & STORMWATER MANAGEMENT CST: 2001

FED Share:

$125,000 $100,000

PROJECT: 21092X- TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles / km) 0/0.00

DESCRPT: 1-20@NEWBORN RDISR83124IBUCKHEADI44/GREENEISEE MORGAN 210920

OTH Share:
PE:NONE ROW: NONE CST: NONE

$25,000

ASSOCIATED PROJECTS: 210920-

PROJECT: 231760- TYPE WORK: REHAB. BRIDGE '"

FUND: BRIDGE, '

LENGTH (miles / km) 0.5/0.81

DESCRPT: SR 44- JASPER COPELAND BRIDGE OVER RICHLAND CREEK

PE: i996 ROW: 2000 . CST:2002 FED Share: , GAShare:

" UNDERWAY $213,000 $714,000 $571,200 $142,800

PROJECT: 232290- TYPE WORK: REPLACE BRIDGE' '. FUND: BRIDGE LENGTH (miles / km) 0.23/0.37
DESCRPT: SR 44@ NORm FORK UTILE RIVER 7.8 MI NE OF UNION POINT

, PE:2000 ROW:, , CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 245100- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.43/0.69

DESCRPT: SR 15 OVER HARRIS BRANCH 9.7 MILES NW OF GREENSBORO

PE: 1997 ROW: 2001 CST:

UNDERWAY $50,000
AFTER 2002

PROJECT: 245110- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.5/0.81

DESCRPT: SR 15 OVER FISHING CREEK 7.9 MILES NW OF GREENSBORO

PE: 1997 ROW: 2001 CST:

UNDERWAY $50,000
AFTER 2002

PROJECT: 245120- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.5/0.81

DESCRPT: SR 15 OVER TOWN CREEK 5.2 MILES N OF GREENSBORO

PE: 1997 ROW: 2001 CST:

UNDERWAY $50,000 .
AFTER 2002

PROJECT: 262740- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 4.2/6.76

DESCRPT: LINGER LONGER RD/CR 54155 FM SR 44 TO END(PART NEW CONST&BR)

PE: 1999 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$4,235,000 $3,388,000
$847,000

-e

PROJECT: 271292- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

PE:LOCL ROW: LOCL

,DESCRPT: STREETSCAPES & SIDEWALKS IN THE CITY OF GREENSBORO

CST: 2000

$300,000

FED Share:

$240,000

OTHShare:

$60,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM
GREENE COUNTY END OF GREENE COUNTY

9/16199 Page 147 of275

n

I

I:

I

I



I

I )
I

I

I

mm

.STATE TRANSPORTATION IMPROVEMENT PROGRAM

91/6199 Page 148 of275

GWINNETT COUNTY

PROJECT: 110530- TYPE WORK: RECST/REHAB

FUND: HPP

ATLANTA TMA TIP # GW AR 053A

LENGTH (miles I km) 2/3.22

DESCRPT: 1-85/SR403 AT SR 316 INTERCHANGE

PE: 1997' ROW: 2000 CST: 2002 FED Share: GAShare:

UNDERWAY $2,720,000 $28,600,000 $22,880,000 $5,720,000

PROJECT: 110720- TYPE WORK: SAFETY

FUND: CMAQ

ATLANTA TMA TIP # GW AR 193

LENGTH (miles I km) 9.22 I 14.84

DESCRPT: ATMS/ 1-85 N COMMUNIC/SURVEILANCE FROM SR 316 TO SR 20

PE:2.D02 ROW: NONE CST:

$5,000 AFTER 2002

PROJECT: 110753- . TYPE WORK: SAFETY

FUND: 1M .

ATLANTA TMA TIP # GW AR 210

LENGTH (miles I km) 0.2/0.32

DESCRPT: 1-85 SAFETY UPGRADES AT HAMILTON MILL RD/CR 134

PE: 1997 ROW:NONE. CST: 2000 FED Share: . GA Share:

UNDERWAY
$3,000,000 $2,700,000
$300,000

PROJECT: 110757- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # GW AR 711

LENGTH (miles I km) 0.2 10.32

DESCRPT: 1-85 SAFETY UPGRADES AT SR 317

PE: 1997 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
. $2,000,000 $1,800,000 $200,000

PROJECT: 110800~ TYPE WORK: RECST/REHAB

FUND: NHS

PE:2oo0

$10,000

ATLANTA TMA TIP # GW 284

LENGTH (miles I km) 0/0.00

ROW: LOCL

DESCRPT: 1-85 @ INDIAN TRAIL RD MODIFICATIONS TO PARKAND RIDE LOT

CST: 2000

$500,000



FED Share:

$400,000

GA Share:

$100,000

PROJECT: 122940- TYPE WORK: PLANNING

FUND: HPP

ATLANTA TMA TIP # GW AR233

LENGTH(mileslkm) 0/0.00

DESCRPT: SR 316 CORRIDOR STUDY OF SAFETY ISSUES AND PROBLEMS

PE:2000 ROW: NONE CST: NONE

$500,000

PROJECT: 132890- TYPE WORK: SAFETY

FUND: STP

ATLANTA TMA TIP # GW 279A

LENGTH (miles I km) 0.2/0.32

DESCRPT: CR 1880IPLEASANT HILL RD @ BUFORD HWY & NS RR1GRD SEP PHI

ASSOCIATED PROJECTS:. 13Y890-

PE: 1999 ROW: 2001 CST: 2002 FED Share: GAShare:

UNDERWAY $12,333,000
$9,000,000 $7,200,000 $1,800,000

\
PROJECT: 132985-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # GW288

LENGTH (mileslkm) 0.35/0.56

DESCRPT: SR 20/CUMMING HWY @CHATTAHOOCHEERIVER @ FORSYTH CO LINE

ASSOCIATED PROJECTS; 13298X-

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:

$102,000 $10,000
. $4,402,000 $3,521,600 $880,400

..

PROJECT: 132986- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$25,000

ATLANTA TMA TIP # GW290

LENGTH (mileslkm) 0.21/0.34

ROW: 2001

$10,000

DESCRPT: SR 120IDULUTH HIGHWAY @ SINGLETON CREEK 1.5 MI E OF DULUTH

CST: 2002

$1,071,000

FED Share:

$856,800

GA Share:

$214,200

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 149 0/275

GWINNETT COUNTY

PROJECT: 133090- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANTA 1MA TIP # GW 281

LENGTH (mileslkm) 4/6.44

DESCRPT: ATMS: SR 141 FM HOLCOMB BR RD TO CHATTAHOOCHEE RIVER

PE:2000 ROW: NONE CST: 2000 FED Share:

$49,000

$441,000 $352,800

PROJECT: 133091- TYPE WORK: NEW CONSTRUCTION, FUND: STP

ATLANTA 1MA TIP # GW 282

LENGTH (miles 1km) 8.4 /13.52

DESCRPT: ATMS: PEACHTREE INDUST BLVD FM HOLCOMB BR TO ROGERS BR RDS

OTH Share:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$88,200 $102,000
$914,000 $731,200

OTH Share:

$182,800

PROJECT: 13Y89D- TYPE WORK: SAFETY

FUND: STP

PE: 1999

UNDERWAY

ATLANTA 1MA TIP # GW 279B

LENGTH (miles / km) 0.2 /0.32

ROW: NONE

DESCRPT: PLEASANT HILL RD @ BUFORD HWY & NS RRlGRADE SEPARATE 132890

CST: 2002

$10,000,000

RP'

ASSOCIATED PROJECTS: 13U890-

FED Share: GAShare:

$8,000,000 $2,000,000

n:

PROJECT: 142285- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA 1MA TIP # GW 289

LENGTH (miles / km) 0.25 /0.40

PE:2000 ROW: 2001

$32,000 $10,000

DESCRPT: SR 324/MT GRAVEL SPRING RD @ 1-85 4.5 M1 SE OF BUFORD

CST:200L

$1,345,000

I

FED Share: GAShare:

$1,076,000 $269,000

PROJECT: 150335- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTA 1MA TIP # GW AR BP090

LENGTH (miles 1 km) 0.85 /1.37

DESCRPT: SPALDING DR SIDEWALKS FM SR 141 TO MEDLOCK BRIDGE RD

PE:LOCL ROW:LOCL CST: 2000 FED Share:

$661,000 $528,800

PROJECT: 162520- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA 1MA TIP#GW ARBPOIl

LENGTH (miles/km) 0/0.00

DESCRPT: WP JONES TRAIL/ PLEASANT HILL RD FM RIVER TO BUFORD HWY

OTH Share:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$132,200 UNDERWAY
$345,000 $276,000

PROJECT: 162522- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA 1MA TIP # GW ARBP019

LENGTH (mileslkm) 0/0.00

DESCRPT: BUFORD HWY FM HERAEUS BLVD TO NEAR SR 20

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$69,000 UNDERWAY'
$200,000 $160,000

PROJECT: 162524- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA 1MA TIP # GW AR BP029

LENGTH (miles / km) 0/0.00

DESCRPT: DACULA RD FROM DACULA PARK TO FENCE ROAD

OTHShare:
PE: 1995 ROW: LOCL CST: 2000 FED Share:

, $40,000 UNDERWAY
$321,000 $256,800

PROJECT: 162526- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA 1MA TIP # GW AR BP041

LENGTH (miles / km) 0/0.00

DESCRPT: MILLER RD FM COLE DR TO HAMBRICK DR

OTHShare:
PE: 1995 ROW: LOCL CST: 2001 FED Share:

$64,200 UNDERWAY
$440,000 $352,000

OTHShare:

$88,000

_ _ _ _ _u~

~---------------------------

STATE'TRANSPORTATIONIMPROVEMENT PROGRAM

9116/99

Page 150of275

GWINNETf-COUNTY--

PROJECT: 162540- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

PE: LOCL

ATLANTA TMA TIP # GW AR BP089

LENGTH (miles 1 km}. 1.5212.45

'ROW: LOCi.

DESCRPT:' OLD NORCROSS RD SIDEWALKS FM HERRINGTON RD TO SUGARLOAF PKWY CST: 2000

FED Share:

$872,000 $697,600

',PROJECT: 171330- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTATMA TIP # GW AR 177B

LENGTH (mileslkm) 2/3.22

DESCRPT: ,SR 1411P'TRE,E PKWY FM SPALDiNG DR TO CHATTAHOOCHEE RIVER

OTHShare:
PE: 1995 ROW: LOCL CST: 2000 FED Share:

$174,400 UNDERWAY
$2 IO,GOO $168,000

PROJECT: '171343- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # GW AR 177G '

LENGTH (mileslkm) 0/0.00

DESCRPT: SIDEWALKS ON REAVER RUIN RD FM INDIAN TRAIL RD TO CASTOR RD

OTHShare:
PE:LOCL ROW:LOCL
CST: 2000 FED Share:

$42,000,
$75,000 $60,000

PROJECT: 171344- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # GW AR 177H ;'

LENGTH (mileslkm) 0/0.00

DESCRPT: WESTERN GWINNETT SIDEWALKJBlKEWAY ON PEACHTREE IND BLVD

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$15,000
'$224,000 $179,200

PROJECT: 171345- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # GW AR 1771 '

LENGTH (rnfleslkm) 0/0.00

DESCRPT: SIDEWALKS IN SNELLVILLE

OTHShare:
PE:LOCL ROW: LOCL CST:2000 ' FED Share:

$44,800
$84,000 $67,200

PROJECT: 171350- TYPE woRk: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # GW216

LENGTH (mileslkm) 0.2/0.32

DESCRPT: CR 1959/CENTERVILLE-ROSEBUD RD @BIG HAYNES CREEK

OTHShare:
PE: 1997 ROW: LOCL CST: 2000 FED Share: GA Share:

$16,800 UNDERWAY
$384,000 $307,200
$76,800

PROJECT: 171545- TYPE WORK: MAINTENANCE

FUND: STP'

ATLANTA TMA TIP # AR 13ID

LENGTH(mileslkm) 0/0.00

DESCRPT: BRIDGE PAINTING IN GWINNETT AND HALL COUNTIES/17154X

LUMPSUM PROJECT

ASSOClATEDPROJECTS: 17154X-

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$628,000 $502,400 $125,600

PROJECT: 171558- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # GW ARBPOl5

LENGTH (mileslkm) 1.913.06

Yo DESCRPT: WESTERN GWINNETT BIKEWAY ALONG PEACHTREE INDUSTRIAL BL

PE:LOCL ROW: LOCL CST: 2000 FED Share:

PROJECT: 171560- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # GW AR BPOl4

LENGTH (!!dleslkm) 0/0.00

DESCRPT: SUWANEE CREEK TRAIL EXTENSION

OTHShare:
PE:LOCL' ROW: LOCL CST: 2000 FED Share:

OTHShare:

$1,246,000 $996,800 $249,200
$331,000 $264,800
$66,200

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9116/99 Page 151 of275

GWINNETT COUNTY

PROJECT: 171562- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP#GW ARBPOl6

LENGTH (mileslkm) 1.9/3.06

DESCRPT: P'TREE IND. BLVD FM RIVER WOOD PKWY TO ROGERS BRIDGEjDULUTH

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$988,000 $790,400

PROJECT:. 171572- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # GW 280

.LENGTH (mileslkm) 0/0.00

DESCRPT: STREETSCAPES IN THE CITY OF BUFORD

OTH Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$197,600
$1,025,000 $820,000

PROJECT: 171590- TYPE WORK: RECSTIREHAB

FUND: CMAQ

ATLANTA TMA TIP # GW AR212

LENGTH (mileslkm) 0/0.00

DESCRPT: BUS SYSTEM FOR GWlNNETT COUNTY - TRANSFER TO TRANSIT

OTH Share:
PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$205,000
$9,042,000 $7,233,600 $1,808,400

PROJECT: 171630- TYPE WORK: NEW CONSTRUCTION FUND: STP

ATLANT A TMA TIP # GW AR 228

LENGTH (miles j km) 0/0.00

DESCRPT: SNELLVILLE AREA PARK & RIDErrRANSFER CTR:NEAR US 78 @ SR 124

PE:2002 ROW: LOCL CST:

$100,000 AFTER 2002

PROJECT: 171631- TYPE WORK: NEWCONSTRUCTION FUND: STP

ATLANTATMA TIP # GW AR229

LENGTH (miles Ikm) 0/0.00

DESCRPT: NORCROSS AREA TRANSFER CENTER SITE TO BE DETERMINED'

OTHShare:
PE:2002 ROW: LOCL CST:

$447,600 $100,000
AFTER 2002

PROJECT: 171632- TYPE WORK: VEHICLE PURCHASE

FUND: CMAQ

ATLANTA TMA TIP # GW AR 224

LENGTH (miles / km) 0/0.00

DESCRPT: BUS ACQuiSITION: 8-9 LOCAL CNG BUSES

PROJECT: 171633- TYPE WORK: VEHICLE PURCHASE

FUND: CMAQ

ATLANTA TMA TIP # GW AR225

LENGTH(miles/km) 0/0.00

DESCRPT: ACQUISITION OF 4-5 CNG COMMUTER BUSES & .RELATED EQUIP

PROJECT: 171634- TYPE WORK: VEHICLE PURCHASE

FUND: CMAQ

ATLANTA TMA TIP # GW AR226

LENGTH(mileslkm) 0/0.00

DESCRPT: 2-3 CGN SUPPORT VEHICLES & MISC START UP EQUIPMENT

PROJECT: 171635- TYPE WORK: NEWCONSTRUCTION FUND: STP

ATLANT A TMA TIP # GW AR 234

LENGTH (miles / km) 0/0.00

DESCRPT: mSTICE & ADMINISTRATION TRANSFER CENTER

OTHShare: PE:NONE
ROW: NONE CST: 2002 FED Share:
OTHShare: PE:NONE
ROW: NONE CST: 2002 FED Share:
OTHShare: PE:NONE
ROW: NONE CST: 2000 FED Share:
OTHShare: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTH Share:

$324,600
$3,444,000 $2,755,200
$688,800
$1,969,000 $1,575,200
$393,800
$255,000 $204,000 $51,000
$500,000 $400,000 $100,000

STATE TRANSPORTATION IMpROVEMENTPROGRAM

91/6199 Page 152of275

GWINNETT COUNTY.

PROJECT: 171636- TYPE WORK: VEHICLE PURCHASE

FUND: CMAQ

ATLANTA TMA TIP # GW AR 223

LENGTH (miles / km) 0/0.00

DESCRPT: .PARATRANSIT BUS ACQUISITION: 3-4 CNG BUSES

PE:NONE ROW: NONE CST:io02 FED Share:

. $297,000 $237,600

PROJECT: 171637- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # GW AR 232

LENGTH (miles / km) 0/0.00

DESCRPT: 1-85/SUGARLOAF PKWY AREA PARK-RIDE & TRANSFER CENTER'

OTHShare:
. PE:LOCL ~ ROW:LOCL' CST: 2000 FED Share:

$59,400
$2,016,000 $1,612,800

PROJECT: 171638- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP # GW AR 231

LENGTH (mileslkm) 0/0.00

DESCRPT: SR 316/SR 20/COLLINS HILL RD AREA PARK-RIDE & TRANSFER CNTR .

OTH Share:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$403,200 $100,000
$2,016,000 $1,612,800

OTH Share:

. PROJECT: 171639- TYPE WORK: RECSTIREHAB

FUND: STP

PE:2000

ATLANTA TMA TIP # GW AR227

LENGTH(miles/km) 0/0.00

ROW: LOCL

DESCRPT: GWINNETT PLACE MALL AREA TRANSFER CENTER-WAITING AREA; SDWLK

CST: 2000

FED Share:

$403,200 $100,000
, $2,016,000 $1,612,800

END OF GWINNETT COUNTY ,

OTH Share:

$403,200

',..I,it

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99

Page 153 0/275

I

HABERSHAM COUNTY

PROJECT: 0000138 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

I

DESCRPT: DOWNTOWN CLARKESVILLE BUSINESS DISTRICT STREETSCAPE

CST: 2001 FED Share:

$313,000 $250,400

I

PROJECT: 0000139. TYPE WORK: ENHANCEMENT

FUND: STP

OTJJ Share: PE:LOCL

$62,600

LENGTH (miles / km) 0 10.00

ROW: LOCL

I

DESCRPT: TALLULAH GORGE MULTI-USE TRAIL PHASE 3

CST: 2000 FED Share:

$562,000 $449,600

OTH Share:

$112,400

I

PROJECT: 122440- TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1993

UNDERWAY

LENGTH (miles / km) 1.3712.21

ROW: 2000

$240,000

DESCRPT: SR 17 FR 3-LANE @ SUITON MILL CK TO SR 115

I

EXIST. LANES: 02 PROPOSED LANES: 04

.

CST:

.AFTER 2002

I

PROJECT: 122450-

.TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 2.05/3.30

PE: 1995 ROW: 1997

UNDERWAY UNDERWAY

DESCRPT: SR 105 RELOC FOR PASSING LANES FRM E OF CR 56 TO W OF CR 53

CST: 2002

$2,237,000

I

EXIST. LANES: 02 PROPOSED LANES: 03

FED Share: GAShare:

$1,789,600 $447,400

I

PROJECT: 122455-

TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.41 10.66

PE: 1996 ROW: NONE

UNDERWAY

DESCRPT: SR 105 OVER SOQUEE CREEK...GOES WITH PI 122450

CST: 2002

$1,407,000

.EXIST. LANES: 02 PROPOSED LANES: 03

I

ASSOCIATED PROJECTS: 122450-

FED Share: GAShare:

$1,125,600 $281,400

I

PROJECT: 171380- TYPE WORK: RECSTIREHAB

FUND: PFH

LENGTH (mileslkm) 2.46/3.96

DESCRPT: CR 240/CR 81ILOW GAP RD FM CR 245INEW LIBERTY RD TO RABUN CL

PE: 1996 ROW: LOCL CST: 2000

UNDERWAY ,. $867,000

FED Share:

$867,000

I

PROJECT: 171550- ' TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

I

LENGTH (miles I km) 0/0.00 DESCRPT: STREETSCAPESI TRAILS AND DEPOT REHAB IN CORNELIA

ROW: LOCL CST: 2000

$313,000

FED Share:

$250,400

I END OFHABERSHAM COUNTY

OTHShare:

$62,600

I

I

-' STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 154 of275

HALL COUNTY

PROJECT: 0000140

TYPE WORK: ENHANCEMENT

FUND:' STP

,LENGTH (miles I km) 0/0.00

DESCRPT: GAINESVILLE - ROCK CREEK GREENWAY

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$563,000 $450,400

PROJECT: 11.0400- TYPE WORK: RECSTIREHAB

FUND: NHS '

LENGTH (miles I km) 3.4 15:47

DESCRPT: 1-985 SPLIT DIAMOND INTERCHANGE @ SR 13 & SR 53 & CD SYSTEM '

OTHShare:
PE:1993 ROW: 2000 CST: 2001 FED Share: GA Share:

$112,600
UNDERWAY $12,000,000 , $35,000,ODO $28,000,000 $7,000,000

PROJECT: 110465- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 1.24/2.00

DESCRPT: 1~985 @ SR 11- NB EXIT LOOP & SB EXIT

EXIST. f.-ANES: 02 PROPOSED LANES: 04

PE: 1997' ROW: 2000 CST: 2000 , FEDShare: . GA Share:

UNDERWAY $1,317,000 $11,330,000 -$9,064,000 $2,266,000

PROJECT: 110470- TYPE WORK: TURN LANES

FUND: NHS

, LENGTH (miles/ km) 0.5/0.81

DESCRPT: 1-985 @ SPOUT SPRINGS ROAD '

PE: 1995 ROW: 2000 . CST:2000 FED Share: GAShare:

UNDERWAY $140,000 $439,000 $351,200 $87,800

PROJECT: l1077X- TYPE, WORK: SAFETY

FUND: 1M

LENGTH (miles I km) 0/0.00

DESCRPT: SR 400 SAFETY UPGRADES @ 4 LOq 1-985 @ SR 347/60/13 HALL .

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 110770-

. PE:NONE

ROW: NONE

CST: 2000

$0

PROJECT: 122945- TYPE WORK: TURN LANES

FUND: STP

LENGTH (miles Ikm) 0.1/0.16

DESCRPT: SR 365 TURN LANESFM RAMSEY RD TO LC TURNER RDIHABERSHAM

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 12294X

PE:2000 ROW: NONE CST: 2000 FED Share: GA Share:

'$125,000
$603,000 $542,700
$60,300 '

PROJECT: 132250- TYPE WORK: RECSTIREHAB

FUND: STP

, LENGTH (miles I km) 1.3512.17

DESCRPT: SR 52 FM N/CHAITAHOOCHEEIMP 11.9 TO S/JULIAN WILEY RDIMP13.2-

EXIST. LANES: 02 PROPOSED LANES: 03

PE:1999 ROW: 2002 CST:

UNDERWAY $40,000
AFTER 2002

PROJECT: 132690- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles I km) 0.2 10.32
DESCRPT: SR l1IUS 129 AT JIM HOOD ROADINOPONE ROAD

PE: 1992 ROW: 2000 CST:

UNDERWAY $1,263,000 AFTER 2002

PROJECT: 132995- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.

LENGTH (mileSI km) 0.22/0.35

DESCRPT: SR 52 @ CANDLER CREEK 5.4 MI SOUTH OF LULA '

PE:2001 ROW: CST:

. $20,000 AFTER 2002 AFTER 2002

I'~.. ....

-- ---------- ---:'--.- ---

_-----------------

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199

Page 155 of275

~

HALL COUNTY'

PROJECT: 141820- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 2.4/3.86

I

DESCRPT: SR 323/GILLSVILLE HWY FM MP 0.4 TO MP 2.79 N/SR 82IMP 2.79 EXIST. LANES: 02 PROPOSED LANES: 03

PE:2001 ROW: CST:

$60,000 AFTER 2002 AFTER 2002

I

PROJECT: 141840- TYPE WORK: TURN LANES

FUND: STP

PE: 1994

UNDERWAY

LENGTH (miles 1 km) 1.412.25

ROW: 1999

UNDERWAY

I

DESCRPT: SR 283IMT VERNON RD FM S OF CR 51 TO N OF CR 45

CST: 2000 FED Share:
GAShare:

$778,000 $700,200
$77,800

PROJECT: 142290- TYPE WORK: REPLACE BRIDGE'

FUND: BRIDGE

LENGTH (miles 1 km) 0.27/0.43

DESCRPT: SR 52 @ CHAITAHOOCHEE RIVER 3 MI NW OF LULA

PE:2001 ROW: CST: .

$31,000 AFTER 2002 AFTER 2002

PROJECT: 142291- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

. PE:2000

$66,000

LENGTH (miles 1 km) 0.36/0.58

ROW:

AFTER 2002

DESCRPT: SR 284 @ CHAIT RIV (LAKE LANIER) 4 MI NORTH OF GAINESVILLE
1t.

CST:

AFTER 2002

ait

PROJECT: 142292- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22 10.35

DESCRPT: SR 323 @ NORTH OCONEE RIVER 7.5 MI SOUTH OF LULA

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 142293- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 323 @ N OCONEE RIVER OVERFLOW 7.5 MI SOUTH OF LULA

~..
la
'~Ji if(;

PROJECT: 142294- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.23 10.37

.DESCRPT: SR 332 @ WALNUT CREEK 1.7 MI SW OF CANDLER

PE:2000 ROW: CST:

$20,000 AFTER2002 AFTER 2002

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 150200- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles Ikm) . 2.1/3.38

DESCRPT: SR 53 FM SR 369IBROWNS BRIDGE RD TO SR 53 CONN

EXIST. LANES: 02 PROPOSED LANES:.04

PE: 1993 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $381,000
$6,686,000 $5,348,800 $1,337,200

PROJECT: 162430- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 8.4 1 13.52

DESCRPT: SR 347IFRIENDSHIP & THOMPSON MILL RD FM 1-985 TO SR 211.

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1994 ROW: 2001 CST:

UNDERWAY $4,000,000 AFTER 2002

rs

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199 Page 156 of275

HALL COUNTY

PROJECT: 171552- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: RESTORATION OF FLOWERY BRANCH DEPOT

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$250,000 $200,000

PROJECT: 171620- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: CR 17fF. GAILEY ROAD @ EAST FORK LITTLE RIVER SW OF CLERMONT

OTII Share:
PE:2000 ROW: LOCL CST:

$50,000 $20,000
AFTER 2002

. END OF HALL COUNTY

s-

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199 Page 1570/275

HANCOCK COUNTY

PROJECT: 22230X- TYPE WORK: RECSTIREHAB

FUND: STP



LENGTH (miles/km) 0/0.00

DESCRPT: SR 15-NB MP 28.1-29.6/WASHINGTON/SB MP 1.0-2.5/HANCOCK CO

PE:NONE ROW: NONE CST: NONE

ASSOCIATED PROJECTS: 222300-

PROJECT: 271280- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km)

0/0.00

DESCRPT: BRIDGE PAINTING IN HANCOCK AND RICHMOND COUNTIESj27Y280

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 27128X- 27Y280-

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$405,000 $324,000
$81,000

PROJECT: 27Y280- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km). 0/0.00

DESCRPT: BRIDGE PAINTING IN HANCOCK AND RICHMOND COUNTIESI27Y280

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 271280-

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$160,000 $144,000 $16,000

END OF HANCOCK COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99 Page 158 of275

, HARALSON COUNTY

PROJECT: 0000114 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles 1 km) 0/0.00

DESCRPT: ,TALLAPOOSA STREETS CAPE

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$313,000 $250,400

PROJECT: 611300- TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles 1 km) 1.2/1.93

DESCRPT: 1-20 SAFETY UPGRADES@SR 100IWACoisRlISRI13/SR61 & CARROLL

ASSOCIATED PROJECTS: 61130X-

OTII Share:
PE: 1998 ROW: NONE . CST:2000 FED Share: ,GAShare:

$62,600 UNDERWAY
$4,146,0.00 $3,731,400
$414,600

. PROJECT: , 611322-

TYPE WORK: MAINTENANCE

,FUND: NHS

LENGTH (miles 1 km) 0/0.00

DESCRPT: GA VISITOR CTR ON 1-2Q-ADD TO PARKING AREA & LANDSCAPING

LUMPSUM PROJECT

PE: 1999 ROW: NONE CST: 2000 FEDShare: . . GAShare:

UNDERWAY'
$634,000 $507,200 $126,800

PROJECT: 621320- TYPE WORK: RECSTIREHAB

FUND: STATE,

LENGTH (miles Ikm) 10.5/16.91

DESCRPT: SR I FM BUCHANAN BP TO S/SR 100IPOLK..INCL BR @ TALLAPOOSA

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 62132X 621475-

PE':t'993 ROW: 1995 CST: 2000
GAShare:

UNDERWAY UNDERWAY $36,500,000
$36,500,000

PROJECT: 621580- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 1.2/1.93

DESCRPT: SR 120 FM W OF BUCHANAN BYP TO LAKE OLYMPIA (MP 9.6 TO 10.8)

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 62158X-

PE: 1992 ROW: 2002 ,CST: 2002 FED Share: GAShare:

UNDERWAY $75,000
$900,000 $720,000 $180,000

PROJECT: 631143- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 4.64 17.47 ~.

DESCRPT: CR 3421CASHTOWN RD FM CR 346IMORGAN RD N TO CR 345

PE: 1992 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$2,122,000 $1,697,600
$424,400

PROJECT: 631145- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 5.28 /8.50

DESCRPT: CR 3421440 FM CR 345 N TO CR 168IPLEASANT HILL RDIPOLK CO

ASSOCIATED PROJECTS: 63114X-

PE: 1992 ROW: 2001 CST:

UNDERWAY $114,000
AFTER 2002

PROJECT: 631170- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (niiles / km) 1.5 12.42

DESCRPT: SR 8 EB MP 15.8-17.31 CENTER TL MP 14.0-14.9

EXIST. LANES: 03 PROPOSED LANES: 05

PE: 1992 ROW: 1995 CST: 2001 FED Share: GAShare:

UNDERWAY UNDERWAY
$1,422,000 $1,137,600
$284,400

.

PROJECT: 631175- TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1992

UNDERWAY

, LENGTH (miles / km) 0.2/0.32

ROW: 2000

$10,000

DESCRPT: S~ 8 INTERSECTION AT FLORIDA AVENUEIFERN ST/CS 629/BREMEN

CST: 2001

$300,000

FED Share:

$240,000

GA'Share':

$60,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

HARALSON COUNTY

PROJECT: 631180- TYPE WORK: REHAB. BRIDGE

. FUND: STP

LENGTH (miles 1 km) 1.812.90

DESCRPT: SR 100 FM TALLAPOOSA TO CEDARTOWNIPOLK--WDN 10 BOX CLVTS

ASSOCIATED PROJECTS: 63118X-

PE: 1992 ROW: 2000 CST: 2002 FED Share: GAShare:

9116199 Page 159 of275
UNDERWAY $8,000
$703,000 $562,400 $140,600

PROJECT: 631200- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 0.79/1.27

DESCRPT: SR 100 FM MARBLE ON NL TO MANNING & EX ALIGN TO SR 1001 & RR

PE:2000 ROW: 2002 CST:

$128,000 $5,320,000 AFTER 2002

PROJECT: 632915- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.23 10.37

DESCRPT: SR 120 @ LmLE RIVER IN EAST BUCHANAN

PE:2000 ROW: 2002 CST:

$20,000 $10,000 AFTER 2002

PROJECT: 641920- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 3.32/5.35

DESCRPT: SR 120- EB MP 1.36-2.821WB MP 4.62 TO 6.48

EXIST. LANES: 02 PROPOSED LANES: 03

PE:2000 ROW: 2002 CST:

$64,000 $267,000 AFTER 2002

PROJECT: 642000- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) . 2.8';4.51

DESCRPT: SR 100- NB & SB PASSING LANES NORTH OF TALLAPOOSA

EXIST. LANES: 02 PROPOSED LANES: 03
r~:

PE:2000 ROW:2002' CST:

$71,000 $63,000 AFTER 2002

~'--

PROJECT: 642350- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles 1 km) 2.8 14.51
DESCRPT: STOUFFEL RD FM SR 100 TO SR 81 GOLF COURSE TO SR 8 - NEW LOC

PE:2000 ROW: 2001 CST: 2001 FED Share: GAShare:

$100,000 $2,000,000 $3,000,000 $2,400,000
$600,000

Pll.OJECT: 642380- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE '

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 100 AT WALKER CREEK 3 MI S OF TALLAPOOSA

PE:2000 ROW: 2002 CST:

$10,000 $100,000 AFTER 2002

PROJECT: 642420- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (mileslkm) 2.11 13.40
DESCRPT: SR 997 FM PLEASANT RDG@HurCHESON/CARROLL TO SR 8@CASHTOWN RD EXIST. LANES: 00 PROPOSED LANES: 02 ASSOCIATED PROJECTS: 64242X-

PE:2000 ROW: 2002 CST:

PROJECT: 662660- TYPE WORK: .RAILROAD CROSSING FifND: STP LENGTH (miles 1 km) 0.2/0.32
DESCRPT: CR 28IMCPHERSON ST@ NORFOLK SOU RR#719249J [MP .26] LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2000 . FED Share: GA Share:

$100,000 $2,000,000 AFTER 2002
"
$100,000 $90,000 $10,000

STATE"TRAJVSPORTATION IMPROVEMENT PROGRAM

9/16199 Page 160 of275

HARALSON COUNTY

PROJECT: 671200- TYPE WORK: ENHANCEMENT

FUND:' STP

LENGTH (miles /km) 0/0.00
DESCRPT: STREETSCAPES & SIDEWALKS IN THE CITY OF BREMEN

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$431,000 $344,800

END OFHARALSON COUNTY

OTHShare:

$86,200

"

- - - - - - - - - - - - ---_......_----_."_._._-~-----------------

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page 161 of275

"iiARRIS COUNTY

PROJECT: 0000097

TYPE WORK: ENHANCEMENT

FUND: STP

.LENGTH (miles / km) 0/0.00

DESCRPT: HAMIL TON-PALMETO CREEK WALKING & BIKE CENTER

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$223,000 $178,400

PROJECT: 322820- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1.49/2.40

DESCRPT: SR llUS 27 PASSING LANE N OF HAMILTON - SB MP 15.10-13.61

EXIST. LANES: 02 PROPOSED LANES: 03

OT/l Share:
PE: 1999 ROW: 2000 CST: 2001 FED Share: GA Share:

$44,600
UNDERWAY $63,000 $946,000 $756,800
$189,200

PROJECT: 332310- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR llUS 27 @MULBERRY CREEK.7 MI N OF JCT SR 208

PE:.1995 ROW: 2000 CST: 2000 FEDS4are: GA Share:

UNDERWAY $40,000
$1,393,000 $1,114,400
$278,600

PROJECT: 332860- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 5.32/8.57

DESCRPT: SR 85 FM MULT-LN NR ELLERSLIE TO WAVERLY HALL SE CITY LMTS

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1998 ROJv.2001 CST:

UNDERWAY $2,361,000 AFTER 2002

PROJECT: 332870- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 2.09/3.36

DESCRPT: SR 85 FM SOUTH CL OF WAVERLY HALL TO NORTH CITY LIMITS

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 332880- TYPE Wo.RK: RECSTIREHAB

FUND: STP

LENGTH (miles/km) 7.18/11.56

DESCRPT: ~R 85 FM N OF WAVERLY HALL TO SR 85 EIW SPLIT @ TALBOT CL

EXIST. LANES: 02 PROPOSED LANES: 04

. PE: 1998 ROW: 2001 CST: 2002 FED Share: GA Share:
PE: 1998 ROW: 2002 CST:

UNDERWAY $1,045,000 $1,937,000 $1,549,600 $387,400
UNDERWAY $1,573,000 AFTER 2002

PROJECT: 333155- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR llUS 27 @MOUNTAIN CREEK 1.6 MI N OF SR 190

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 333156- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26/0.42

DESCRPT: SR 103 @FLAT SHOALS CREEK 11.2 MI W OF SR 116

PROJECT: 343030- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 0.39/0.63

DESCRPT: SR 219 AT HOPEWELL CHURCH ROAD/CR 388 IN WHITESVILLE

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:
PE:1998 ROW: 2000 CST: 2000 FED Share: GA Share:

$31,000 $10,000 $1,340,000 $1,072,000 $268,000
UNDERWAY $50,000
$109,000 $87,200
. $21,800

STATE TRANSPORTATION IMPROVEMENTPROGRAM

HARRIS COUNTY

PROJECT: 343040- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 0.32/0.52

DESCRPT: SR 219 AT LICK SKILLET ROAD (CR 389) INTERSECTION

; . PE: 1998 ROW: 2000 . CST:2000 FED Share: GAShare:

9116/99 Page 1620/275
UNDERWAY $50,000
$132,000 $105,600 $26,400

PROJECT: 343370- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (mileslkm) 0.21/0.34

DESCRPT: SR 116 @ LITTLE PALMETTO CREEK HAMILTON - NE SECTION

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 343371- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 116 @PALMETTO CREEK 1.4 MI E OF SR I

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

PROJECT: 343372- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 116 @ BETHLEHEM CREEK 6 MILES NE OF HAMILTON

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

PROJECT: 371770- TYPE WORK: . ENHANCEMENT

FUND: STP

PE: LOCL

LENGTH (miles 1 km) 0/0.00

ROW: LOCL

DESCRPT: CO~DORFROM NEW DEAL SETTLEMENT TO CHAT-FLINT HERITAGE HWY

CST: 2000

FED Share:

END OFHARRIS COUNTY

OTH Share:
I ...

$20,000 $10,000 $786,000 $628,800 $157,200
$20,000 $10,000 $318,000 $254,400 $63,600
$301,000 $240,800
$60,200

..

j!
:l
.~

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16199

Page 163 of275

HART COUNTY

PROJECT: 0000166 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: HARTWELL STREETSCAPE

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$1,125,000 $900,000

END OF HART COUNTY

OTH Share:

$225,000

~r
ti
I:
I I I I I I I
.-

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 164 of275

HENRY COUNTY

PROJECT: 312113- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # HEAR2lS

'LENGTH(mileslkm) 0.2/0.32

DESCRPT: 1-75 SAFETY UPGRADES @ LOCUST GROVE ROADIBILL GARDNER PKWY

PE: 1997 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
' $1,200,000 $1,080,000 $120,000

PROJECT: 312116- TYPE WORK: SAFETY

FUND: 1M '

ATLANTA TMA TIP # HEAR219

LENGTH (mileslkm) 0.2/0.32

DESCRPT: 1-75 SAFETY UPGRADES AT SR 138

PE: 1997 ROW: NONE CST:2000. FED Share: GA Share:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 312118- TYPE WORK: SAFETY

FUND: 1M

ATLANTA TMA TIP # HE AR 217

, LENGTH (mileslkm) '0.2/0.32

DESCRPT: 1-75 SAFETY UPGRADES AT SR 155

PE: 1997 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$1,200,000 $1,080,000
$120,000

PROJECT: 312150- TYPE WORK: RECSTIREHAB

FUND:NHS

ATLANTA TMA TIP # HE AR 215

LENGTH (miles I km) 0.55 10.89

DESCRPT: 1-75 @HUDSON BRIDGE RDIEAGLES LANDING PKWY/CR 659-BR REPL

PE: 1999 ROW: NONE CST: 2002 FED Share: GA Share:

UNDERWAY
$10,500,000 $8,400,000 $2,100,000

PROJECT: 312160- TYPE WORK: RECSTIREHAB

FUND: NHS

ATLANTA TMA TIP#HEAR216

LENGTH (mileslkm) 0.510.81

DESCRPT: 1-75 @ JODECO ROADICR 824 BRIDGE REPLACEMENT FOR SAFETY

PE: 1999 ROW: NONE , CST: 2002 FED Share: GAShare:

UNDERWAY
$10,500,000 $8,400,000 $2,100,000

PROJECT: 323070- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # HE 145

LENGTH (miles I km) 0.210.32

DESCRPT: SR 138 AT MILLERS MILL ROAD/CR 665

LUMP SUM PROJECT

PE: 1999 ROW: LOCL ,CST:2001 FED Share: GA Share:

UNDERWAY
$360,000 $324,000 $36,000

PROJECT: 323075- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # HE 143

LENGTH (mileslkm) 0/0.00

DESCRPT: SR 138 AT SR 155

PROJECT: 332467- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # HE 128

LENGTH (miles I km) 0.22/0.35

DESCRPT: SR 155 @ LITTLE COTTON INDIAN CRK 5 MI N OF MCDONOUGH

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare: PE: 1999
ROW: 2001 CST: 2002 FED Share: GAShare:

$525,000 $420,000
$105,000 UNDERWAY
$50,000 $608,000 $486,400 $121,600

PROJECT: 332945- TYPE WORK: SIGNALS

FUND: STP

ATLANTA TMA TIP # HE 122

LENGTH (mileslkm) 0.42/0.68

DESCRPT: SR 81 AT KEYS FERRY RD

PE:LOCL ROW: LOCL CST: 2001 FED Share:
OTH Share:

$34,000 $27,200
$6,800

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 165 of275

HENRYCOUNTY
. PROJECT: 332970- TYPE WORK: ATLANTA TMA TIP # HE 123 DESCRPT: SR 81 AT NEW HOPE RD

SIGNALS

FUND: STP

LENGTH (miles I km) 0.2/0.32

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$36,000 $28,800

PROJECT: 332975-. TYPE WORK: SIGNALS

.FUND: STP

ATLANTA TMA TIP # HE 124

LENGTH (mileslkm) 0.210.32

DESCRPT: SR 81 AT RACETRACK RD

OTHShare:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$7,200
$34,000 $27,200

PROJECT: 332980- TYPE WORl(: SIGNALS

FUND: STP

ATLANTA TMA TIP # HE 120

LENGTH (mileslkm) 0.210.32

DESCRPT: SR 155 AT FAIRVIEW RD

OTR Share:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$6,800
$43,000 $34,400

PROJECT: 333126- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

ATLANTA T~ TIP # HE 154

LENGTH (mileslkm) 0.23/0.37

DESCRPT: SR 155 @ WALNUT CREEK AT MCDONOUGH CITY LIMITS

OTRShare:
PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

$8,600
$20,000 $10,000 $813,000 $650,400 $162,600

PROJECT: .333127- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

ATLANTA TMA TIP # HE 155

LENGTH (mileslkm) 0.25/0.40

DESCRPT: SR 155 @ BIG COTTON INDIAN CREEK 6 MI N OF MCDONOUGH

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

$28,000 $10,000 $1,183,000 $946,400 $236,600

PROJECT: 333295- TYPE WORK: RECST/REHAB

FUND: STP

ATLANTA TMA TIP # HE 146

LENGTH (mileslkm) 0/0.00

DESCRPT: SR 155 @ MILLERS MILL RD/CR 665

PROJECT: 343260- TYPE WORK: SIGNALS

FUND: STP

ATLANTA TMA TIP # HE 121

LENGTH (miles 1km) 0.2/0.32

DESCRPT: SR 155 @ HAMPTONILOCUST GROVE RD

PROJECT: 343265- TYPE WORK: MAINTENANCE

FUND: STP

ATLANTA TMA TIP # HE 126A

LENGTH(mileslkm) 9.08/14.62

DESCRPT: CR 650lHAMPTONILOCUST GROVE RD FM SR 20 TO 1-75

PE:LOCL ROW:LOCL CST: 2000 FED Share:
OTHShare: PE:LOCL.
ROW: LOCL CST: 2001 FED Share:
OTHShare: PE:2001
ROW: LOCL CST:
GAShare:

$522,000 $417,600 $104,400
$37,000 $29,600
$7,400 $5,000 AFTER 2002
$0

PROJECT: 343500- TYPE WORK: RECST/REHAB

FUND: STP

ATLANTA TMA TIP # HE 144

LENGTH(mileSlkm) 0/0.00

DESCRPT: OLD CONYERS RD/CR 69 @ FLAT ROCK RD/CR 100

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTI/ Share:

$400,000 $320,000
$80,000

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _" w ~

._.

._._ .,... _~ - - =

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99

Page 166 0/275

HENRY COUNTY

PROJECT: 351230- TYPE WORK: SIGNALS

~FUNiJ: STP

ATLANTA TMA TIP # HE 125

LENGTH (tidleslkm) 0.2/0.32

DESCRPT: WALT STEPHENS RD AT SPEER RD

. PE:LOCL
ROW: LOCL
CST: 2001 , FEDShare:

$43,000 $34,400

PROJECT: 351235- TYPE WORK: RECSTIREHAB

. FUND: STp

ATLANTA TMA TIP # HE 148

"

LENGTH (mileSI km) 0/0.00

DESCRPT: JODECO RD/CR 824 @ FLOYD RD

OTH Share:
PE:LoCL ROW: LOCL " .. , CST: 2000 FED Share:

$8,600
$200,000 $160,000

PROJECT: 351240- TYPE WORK: RECSTIREHAB

.'FUND: STP

ATLANTA TMA TIP # HE 147

LENGTH (miles I km) 0/0.00

. DESCRPT: FAIRVIEW RD/CR 676 @ THURMAN DRICR 25

OTHShare:
" PE:LOcL Row:LoCL': ' CST: 2000 FED Share:

$40,000
$338,000 ' $270,400

PROJECT: 363860- TYPE WORK: RECSTIREHAB ..

.FUND: STP

ATLANTA TMA TIP # HE 119

:'

LENGTH (miles I kin) 0 10.00

DESCRPT: JODECO RD EXPAND PARK & RIDE LOT & RELOCATE OCTAGON RD

OTHShare: , PE:2000' ROW: 2000 CST: 2000
FED Share:

$67,600
$5,000 $360,000 $1,200,000 $960,000

PROJECT: 363875- TYPE WORK: ENHANCEMENT

FUND: CMAQ

, ATLANTA TMA TIP # HEARBP006 '

LENGTH (mileslkm) 0/0.00

DESCRPT:FAIRVIEW RD FM EAST ATLANTA RD TO FAIRVIEW ELEMENTARY

OTHShare:
PE: 1995 " ROW: LOCL CST:ioOI FED Share:

$240,000 UNDERWAY
$329,000 $263,200

PROJECT: 363876- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

ATLANTATMA TIP # HE ARBPOl8C

LENGTH (mileslkm) 2.413.86

DESCRPT: MCDONOUGH EW ONE WAY PAIR FM JONESBORO RD TO KEYS FRY RD

OTHShare:
PE:LOCL ROW: LOCL . CST: 2001 FED Share:

otusso

PROJECT: 363877- TYPE WORK: NEW CONSTRUCTION FUND: CMAQ

PE: LOCL '

ATLANTA TMA TIP # HE AR BPO18B

LENGTH (miles I km) 2.4 13.86

ROW: LOCL '

DESCRPT: MCDONOUGH NS ONE WAY PAIR FM GRIFFIN ST TO MACON ST&SIDEWALK ' CST: 2001

FED Share:

$65,800
$180,000 $144,000 $36,000
$225,000 $180,000

PROJECT: 371440- TYPE WORK: ENHANCEMENT

FUND: CMAQ'

ATLANTA TMA TIP # HE AR 177A

LENGTH (mileslkm) 0/0.00

DESCRPT: SCHOOL BICYCLE RACK PROGRAM FOR-HENRY COUNTY

OTH Share:
'PE::1995 ROW: NONE "CST:2000 FED Share:

$45,000 UNDERWAY
$15,000 $12,000

PROJECT:' 371442- TYPE WORK: ENHANCEMENT

' FUND: CMAQ'

ATLANTA TMA TIP # HE'AR 177B

LENGTH (miles I km) 0 10.00

DESCRPT: BICYCLEIPEDESTRIAN SCHOOL SIGNAGE PROGRAM - pHASE I

OTHShare:
. PE: 1995 .ROW: NONE
CST: 2000 FED Share:

$3,000 UNDERWAY
$15,000 $12,000

OTH Share:

$3,000

I

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99

Page 1670/275

I

HENRY COUNTY

PROJECT: 371444- TYPE WORK: ENHANCEMENT

. FUND: CMAQ

PE: 1995

UNDERWAY

~.

ATLANTA TMA TIP # HE AR 177C

LENGTH (miles I km)

DESCRPT: SCHOOL BIKE RACK PROGRAM - PHASE 2

0 10.00

ROW: NONE CST: 2000

$15,000

I:

FED Share:

$12,000

I

PROJECT: 371445- TYPE WORK: ENHANCEMENT

FUND: CMAQ

OTHShare: PE:LOCL

$3,000

ATLANTATMA TIP # HEAR 177D

LENGTH (mileslkm) 0/0.00

ROW: LOCL

I

DESCRPT: FLIPPEN ROAD BIKE LANES - PHASE 1

CST: 2000 FED Share:

$189,000 $151,200

!~l~,

END OF HENRY COUNTY

OTHShare:

$37,800

(
I
I I I I I

- - - - - _.._--_._,._----------....------~-----------_. STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 168 of275

HOUSTON CiJU'7VTY
PROJECT: 0000125 TYPE WORK:
DESCRPT: PERRY STREETSCAPE

ENHANCEMENT

. FUND: STP

LENGTH (miles 1 km) 0/0.00

PE:LOCL . ROW:LOCL
CST: 2001 FED Share:

$875,000 $700,000

PROJECT: 0000126 TYPE WORK: ENHANCEMENT

FUND: STP

WARNER ROBINS TIP # 2000-2

LENGTH (miles 1 km) 0/0.00

DESCRPT: CENTERVILLE SIDEWALK SAFETY IMPROVEMENTS

OTH Share:
PE:LOCL ROW: LOCL CST:2001' FED Share:

$175,000
$163,000 $130,400

PROJECT: 322570- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (mileslkm) 3.2/5.15
DESCRPT: SW PERRY PARKWAY {BYPASS} FM SR 127 SE TO L WALKERPKY/GIP EXIST. LANES: 00 PROPOSED LANES: 04

OTH Share:
PE: 1993 ROW: LOCL CST: 2001 FED Share: GA Share:

$32,600 UNDERWAY
$5,232,000 $4,185,600 $1,046,400

PROJECT: 322960- TYPE WORK: RECSTIREHAB

FUND: NHS

WARNER ROBINS TIP # 1998-2

LENGTH (miles (km) 2.71/4.36

DESCRPT: SR247IUS 129 FM GREEN STREET/GATE 1 TO US 41 IN BIBB

EXIST. LANES: 04 PROPOSED LANES: 06

ASSOCIATED PROJECTS: 32296X- 322965-

PE:2001 ROW: CST:

$500,000 AFTER 2002 AFTER 2002

PROJECT: 322965- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

WARNER ROBINS TIP # 1998-1

LENGTH (miles 1 km) 0.27 10.43

DESCRPT: SR 247IUS 129 NBL @ ECHECONNEE CREEK HOUSTON-BIBB CO LINE

EXIST. LANES: 04 PROPOSED LANES: 06

ASSOCIATED PROJECTS: 322960-

PE:2001 ROW: 2002 . CST:

$15,000 $12,000 AFTER 2002

PROJECT: 331860- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 2.65 14.27

DESCRPT: SR 127 FM NORTH PERRY BYPASS TO E OF LAKE JOY ROAD

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 331865-

PE: 1994 ROW: 2001 CST: 2002 FED Share: GA Share:

UNDERWAY $1,536,000. $7,540,000 $6,032,000 $1,508,000

PROJECT: 331865- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

WARNER ROBINS TIP # WRI-1993(5)

LENGTH(mileslkm) 0.03/0.05

DESCRPT: SR 127 AT MOSSY CREEK /SEE 331860

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 331860-

PE: 1994 ROW: 2000 CST: 2002 FED Share: GA Share:

UNDERWAY $1,bOO
$891,000 $712,800 $178,200

PROJECT: 332770- TYPE WORK: RECSTIREHAB

FUND: STP

WARNER ROBINS TIP # 1985-10

LENGTH (mileslkm) 1.25/2.01

DESCRPT: CR 535IHOUSTON LAKE RD FM SR 247CIWATSON BLVD TO THOMSON RD

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: LOCL CST:

$20,000 AFTER 2002

PROJECT: 342340- TYPE WORK: IMPROVE INTERSECTION FUND: STP

WARNER ROBINS TIP # WR1985-6

LENGTH (mileS"1 km) 4.8/7.73

DESCRPT: SR 247C FM HOUSTON LAKE RD TO SR247-IMPROVE INTERSECTIONS

PE: 1992 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$478,000 $430,200
$47,800

STATE TRANSPORTATION IMPROVEMENTPROGRAM

HOUSTON COUNTY

PROJECT: 350840- TYPE WORK: RECSTIREHAB

FUND: STP

WARNER ROBINS TIP # WR 1991-2

LENGTH (miles 1 km) 2.81 14.52

DESCRPT: HOUSTON LAKE RD/CR 535 FM SR 96 TO RICHARD RUSSELL PKWY

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2000 CST: 2000 FED Share: GAShare:

9i16199 Page 169 0/275
. UNDERWAY $2,000,000 $8,588,000 $6,870,400 $1,717,600

PROJECT: 351070- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

WARNER ROBINS TIP # WR 1-1996( 1)

LENGTH (miles 1 km) 0.26 10.42

DESCRPT: CR 156IMOODY ROAD @ BAYGALL CREEKIWARNER ROBINS

PE: 1996 ROW: LOCL CST:iooo FED Share: GA Share:

UNDERWAY
$564,000 $451,200 $112,800

PROJECT: 371730- TYPE WORK: RECSTIREHAB

FUND: HPP

WARNER ROBINS TIP # 2000-1

LENGTH (miles 1 km) 0 10.00

DESCRPT: RESURFACE DAVIS DRI GREEN ST & N HOUSTON RD IN WARNER ROBINS

PE:2000 ROW: NONE CST: 2002 FED Share:

$8,000
$367,000 $293,600

OTHShare:

$73,400

I

PROJECT: 371740- TYPE WORK: RECSTIREHAB

FUND: HPP

WARNER ROBINS TIP # 1997-1

LENGTH (miles Ikm) 2/3.22

PE:2000 ROW: NONE

$64,000

DESCRPT: CORDER RD FM PINEVIEW DR TO RUSSELL PKWY IN WARNER ROBINS

CST: 2002

$3,124,000

I;

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share: GAShare:

$2,499,200 $624,800

i

PROJECT: 371772- TYPE WORK: ENHANCEMENT

FUND: STP

WARNER ROBINS TIP # 1999-1

LENGTH (miles 1 km) 1.2/1.93

PE:LOCL ROW: LOCL

DESCRPT: LANDSCAPING OF SR 247 FM CANNON ROTO GREEN STIWARNER ROBINS

CST: 2000

$69,000

FED Share:

$55,200

I

OTHShare:

$13,800

END OFHOUSTON COUNTY
I

e~
'c.il
I

I

I

mi<~ ,

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 1700/275

JACKSON COUNTY

PROJECT: 0000167 TYPE WORK: . ENHANCEMENT

FUND: STP

LENGTH (mileslkm) 0/0.00 .

DESCRPT: HOSCHTON RR DEPOT REHAB

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$40,000 $32,000

PROJECT: 110520- TYPE WORK: . NEW CONSTRUCTION FUND: 1M LENGTH (mileslkm) 0/0.00
. DESCRPT: 1-85 CONSTRUCT NEW REST AREAS TO REPLACE # 75 AND # 76 .

OTH Share:
PE: i997 ROW: 2000 CST: 2001 FED Share: GAShare:

$8,000
UNDERWAY , $423,000 $14,261,000 $12,834,900 $1,426,100

PROJECT: 110750- TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles I km) .1.2 I 1.93

DESCRPT: 1-85 SAFETY UPGRADE @ SR 21 IIBARROWISR 53/82198/JACKSON

ASSOCIATED PROJECTS: 11075X-

PE: 1997 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$12,385,000 $11,146,500
$1,238,500

PROJECT: 121600- TYPE WORK: RECSTIREHAB

FUND:NHS

LENGTH (miles I km) 3.5 15.64

DESCRPT: SR II FM SCL PENDERGRASS TO SR 332/ PART NEW LOCATION

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 1998 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$8,000,000 $6,400,000 $1,600,000

PROJECT:. 122150- TYPE WORK: RECSTIREHAB .

. FUND:NHS

LENGTH (miles I km) 7.4111.91

DESCRPT: SR lilUS 129 FM SR 332 @ TALMO/JACKSON CO TO SR 323/HALL CO

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 12215X- 121340-

PE: 1992 ROW: 2000 CST:

UNDERWAY $4,700,000
. AFTER 2002

PROJECT: 122170- TYPE WORK: RECSTfREHAB

FUND: STP .

LENGTH (mileslkm) 6.7/10.79

DESCRPT: SR 15 ALTIUS 129 FM SR 330 TO JEFFERSON BYP @CR 104

EXIST. LANES: 02 PROPOSED LANES: 04

PE:1992 ROW: 2002 CST:

UNDERWAY $2,741,000 AFTER 2002

PROJECT: 122300- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 6.71110.80

DESCRPT: SR 15IUS 441 FM S OF CLARKE COUNTY LINE TO SR 335

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 2001 CST:

UNDERWAY $3,985,000 AFTER 2002

PROJECT: 122310- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 5.19 18.36

DESCRPT: SR 15IUS 441 FM SR 335 TO COMMERCE BYPASS

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 2001 CST:

UNDERWAY $6,050,000 AFTER2002.

PROJECT: 122400- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) I 11.61

DESCRPT: SR 53 NEAR HOSCHTON NB FM MP 6.8-8.4 [N&S OF CR 421]

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1996 ROW: 1997 CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY
$446,000 $356,800
$89,200

------------,-,._-_._._STATE TRANSPORTATION IMPROVEMENTPROGRAM

JACKSON COUNTY

PROJECT: 122510- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.15 /0.24

DESCRPT: SR 15 ALT IN JEFFERSON AT BIG CURRY CREEK

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1993 ROW: 2001 CST:

9/16199 Page 171 of275
UNDERWAY . $20,000 AFTER 2002

PROJECT: 132040- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles / km) 6.9/11.11
DESCRPT: JEFFERSON BYP FM SR15 ALT SE CLIARCADE NW TO SRll NEAR CR229 EXIST. LANES: 00 PROPOSED LANES: 04

PROJECT: 132860- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles/km) 3.9/6.28

DESCRPT: SR 53 FM 1-85 TO LANIER RACEWAYIROAD ATLANTNCR 681/HALL CO

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 13286X-

PROJECT: 171002- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2 /0.32

DESCRPT: CR 367IWHITES BOTTOM ROAD @ WALNUT CREEK NE OF BRASELTON

EXIST. LANES: 01 PROPOSED LANES: 02

PROJECT: 171004- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.5 /0.81

DESCRPT: CR 86/JEFFERSON RIVER RD @ CURRY CREEK 3.6 MI E OF ARCADE

PROJECT: 171005- TYPE. WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2/0.32

DESCRPT: CR 248lHARMONY CHURCH RD @ POND FORK CREEK NE OF TALMO

END OFJACKSON COUNTY

PE: 1993 . ROW: 1997
CST: 2000 FED Share:
GA Share:
PE:2001 ROW: CST:
PE: 1994 ROW: LOCL CST: 2002 FED Share: GAShare:
PE: 1997 ROW: LOCL CST: 2001 FED Share: GAShare:
PE: 1997 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY $18,059,000 $14,447,200 $3,611,800
$750,000 AFTER 2002 AFTER 2002
UNDERWAY
$353,000 $282,400 . $70,<$00
UNDERWAY
$612,000 $489,600 $122,400
UNDERWAY
$263,000 $210,400 .
$52,600

STATE TRANSPORTATION IMPROVEMENTPROGRAM

, 9/16/99 Page 172 of275

JASPERCiJiJ!rrr

PROJECT: 0000152 TYPE WORK: ENHANCEMENT

FUND: STP

.. PE:LOCL .

LENGTH (miLes / km) 0 /0.00

ROW: LOCL

DESCRPT: MONTICELLO STREETSCAPElWELCOME CTRffRAILHEADIMUSEUMIBIKEWAY CST: 2001

FED Share:

$1,000,000 $800,000

END OF JASPER COUNTY

OTHShare:

$200,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99

"$ i:. '

JEFF DAVIS CO"UNTY

PROJECT: 523260- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

Page 173 of275

.PE:2000

$150,000

LENGTH (miles / km) 0.43 /0.69

ROW: 2001

$10,000

I

DESCRPT: SR 19IUS 23 NBL @ OCMULGEE RIVER 5.8 MI NW OF HAZLEHURST

CST: 2002 FED Share: ,

$6,726,000 $5,380,800

GAShare:

$1,345,200

Ijf'.

PROJECT:. 533177- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles / km) 0.23/0.37

ROW: 2002

$10,000

DESCRPT: SR 1351US 221 @HURRICANE CREEK 6.8 MI SW OF HAZLEHURST

CST:

AFTER 2002

END OFJEFF DAVIS COUNTY

I-
llii
Ir, '.i.

-----



,

N

_

'STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 174 0/275

~JE~F;F;E=R;S'O;N~C~O~U~N~TrYr,----........- - - - - - - - . - - - - . - - - - - - - - - - - - -

PROJECT: 221890- TYPE WORK: RECSTJREHAB

FUND: HPP

LENGTH (mileslkm) 10.5/16.91

DESCRPT: SR 4IUS 1 FM CR 41 TO 112 MILE N OF SANDY RUN CKJRICHMOND

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22189X-

PE:NONE ROW: 1997 CST: 2000 FED Share: GA Share:'

UNDERWAY $17,979,000 $14,383,200
$3,595,800

PROJECT: 222295- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles/km) 9.4/15.13

DESCRPT: SR 88/SR 540,FM SR 171 AT GRANGE TO SR 296 SW OF WRENS

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: 1999 CST: 2001
GA Share:

UNDERWAY UNDERWAY $18,363,000
$18,363,000

PROJECT: 22229X TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 0/0.00

DESCRPT: SR 88 FM CR 1061WASHINGTON TO SR 171 1222290

ASSOCIATED PROJECTS: 222290-

P'E:NONE ROW: NONE CST: NONE

PROJECT: 22Y120- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: SR 4IUS 1 FM WADLEY BYP TO LOUISV'LE BYP- FOR FED PE; 222120

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222120-

PE:2000 ROW: NONE eST: NONE

$1,000

PROJECT: 22Y150- TYPE WORK: RECSTIREHAB '

FUND: NHS

LENGTH (miles I km) 0 10.00

DESCRPT: SR 4IUS llL'VILLE BYP FM US 1 BUS TO CR 325-FOR FED PE;222150

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222150-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 22Y160- ' TYPE WORK: RECSTIREHAB

, FUND: NHS

LENGTH (miles I km) 0 10.00

DESCRPT: SR 4IUS 1 FM LOUISVILLE BYP TO CR 138 - FOR FED PE; 222160

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222160-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 22Y170- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0 10.00

DESCRPT: SR 4IUS 1 FM CR 138 TO SR 88/FALL LINE FWY-FOR FED PE;222170

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222170-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 231230- TYPE WORK: RECSTIREHAB '

FUND: STP

,

LENGTH (mileslkm) 3.615.80

DESCRPT: SR 24IUS 221 EB MP 12.6-13.8IWB 1O.0-11.3IEB 3.2-4.3

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1997 ROW: 2002 CST:

UNDERWAY $15,000
AFTER 2002

PROJECT: 231980- TYPE WORK: REPLACE BRIDGE

FUND: STP

LENGTH (miles I km) 0.53/0.85

DESCRPT: SR 24IUS 221 @ ROCKY COMFORT CREEK WEST SIDE OF LOUISVILLE

PE: 1997 ROW: 2001 CST:

UNDERWAY $50,000
AFTER 2002

I I
I I I"
I I I I I I I I I I I
D
n
" .~-. U"'~'

STATE TRANSPORTATION IMPROVEMENT PROGRAM

JEFFERSON COUNTY

PROJECT: 232265- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.22/0.35 DESCRPT: SR 4IUS 1 @ BIG CREEK 9 MI N OF LOUISVILLE

PE:2000 ROW: 2002 CST:

9116199 Page 175 of275
$20,000 $10,000 AFTER 2002

PROJECT: 232280- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.3/0.48

DESCRPT: SR 78IUS 221- US 319@WILLIAMSON SWAMP CK SO SIDE BARTOW

PE:2000 ROW: CST:

$93,000 AFTER 2002 AFTER 2002

PROJECT: 232281- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.27/0.43

DESCRPT: SR 4 BUS- US I BUS @ WILLIAMSON SWAMP CREEK CITY OF WADLEY

PE:2000 ROW: CST:

$49,000 AFTER 2002 AFTER 2002

PROJECT: 245390- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23 10.37

DESCRPT: SR 17 @ BIG C~EK 3 MI SE OF LOUISVILLE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

END OF JEFFERSON COUNTY

- - - - - - - - ...,-,_. ------,---------------,._~_._ STATE TRANSPORTATION IMPROVEMENTPROGRAM

JO'NES COUNTY
PROJECT: 322540- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles / km) 5.6/9.02
DESCRPT: GRAY NORTH BYPASS/SR 899 FROM SR 22 SW TO SR 22 NE OF GRAY EXIST. LANES: 00 PROPOSED LANES: 02

PE: 1999 ROW: 2002 CST:

9/16/99 Page 178 of275
UNDERWAY $823,000
AFTER 2002

PROJECT: 322790- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 3.8 /6.12

DESCRPT: SR 44IUS 129 SB MP 12.67-14.171NB MP' 1.0-2.21 NB MP 10.7-12

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1997 ROW: 2002 CST:

UNDERWAY $67,000
AFTER 2002

, : pilf.JJECT: 332960- TYPE WORK: MAINTENANCE

FUND: STP

. LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 49 ON SOUTHBOUND SIDE@ MP 2.0-2.1-~SLIDE REPAIR

PROJECT: 333100- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 22IUS 129 - DRAINAGE IMPROVEMENT NEAR JEFFERSON STREET

PE: 1998 ROW: 2000 CST: 2001 FED Share: GAShare:

. UNDERWAY $769,000 $993,000 $794,400 $198,600

PE:2001 ROW: CST: .

$5,000 AFTER 2002 AFTER 2002

PROJECT: 343080- TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1997 . UNDERWAY

LENGTH (miles / km) 1.8/2.90

RaW: 1997

UNDERWAY

DESCRPT: SR 18 WESTBOUND FROM MP 24.39IJONES TOMP 0.71IWILKINSON

CST: 2000

$867,000

..

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 34308X-

FED Share: GAShare:

$693,600 $173,400

PROJECT: 343400- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 18 '@ WALNUT CREEK 6 MI W OF GRAY

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER200i

PROJECT: 371490- TYPE WORK: REPLACE BRIDGE

FUND: PFH

LENGTH (miles / km) 0.2 /0.32

DESCRPT: CR 69IUNION HILL CH ROAD @ LITTLE CEDAR CREEK

END OF JONES COUNTY

PE:2000 ROW: NONE CST: 2002 FEDSJiare:

$267,000 $267,000

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9//6/99

Page /79 of275

.I~.i'

LAMAR COUNTY

PROJECT: 0000127 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

I

LENGTH (miles / km) DESCRPT: BARNESVILLE STREETSCAPE PHASE II

0/0.00

ROW: LOCL CST: 2000 FED Share:

$875,000 $700,000

I.

PROJECT: 321370- TYPE WORK: RECSTIREHAB

FUND: STP

OTll Share: PE: 1992

$175,000 UNDERWAY

LENGTH (miles / km) 4.2 /6.76

ROW: 2001

$240,000

DESCRPT: SR 18 SB 13.7-15.2IMONROE/EB 2.3-3.6IWB 3.38-5.IITL 5.10-5.6

CST:

AFTER 2002

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 32137X-

PROJECT: 322530- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH r'lniles / km) 1.9/3.06
DESCRPT: BARNESVILLE BYP [[RUCK BYP] FM SR 7IUS 341 N. TO SR 18IUS41 EXIST: LANES: 00 PROPOSED LANES: 02

PE: 1997 ROW: 2001 CST: 2002 FED Share: GA Share:

UNDERWAY $220,000
$2,404,000 $1,923,200
$480,800

PROJECT: 331820- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 4.7517.65

DESCRPT: SR 36/NB MP 9.93-11.58ISB 13.62-15.651N&S 17.59-.06/BUTTS

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 33182X-

PE: 1992 ROW: 2001 CST:

UNDERWAY $752,000
AFTER 2002

PROJECT: 333220- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.35/0.56
DESCRPT: SR 7IUS 341 ATSR 36ITHOMASTON RD & THOMASTON STREET LUMP SUM PROJECT

PE: 1999 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$359,000 $323,100
$35,900

PROJECT: 343390- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

:

LENGTH (miles / km) 0.22/0.35

DESCRPT: SJ:t 36 @ EDIE CREEK 6 MI N OF BARNESVILLE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 343391- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 36 @ BUCK CREEK 9.5 MI N OF.BARNESVILLE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 371776- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles/km) 0/0.00

DESCRPT: STREETSCAPES IN THE CITY OF BARNESVILLE

END OF LAMAR COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$875,000 $700,000
$175,000

;..-~.:

,

-

-

-

-

-

-

-

-

-

-S-TA-T-E-T-RA-N-S-PO-R-oT-A-TI-O-N-IM-P,R.._O~ VE

ME

N

T

PR

O

G

...- -
RAM

-

-

-

9116199

..

Page 1800/275

U{]RENSCOUNIT ----.-------------------~---:'---

PROJECT: 210650-

TYPE WORK: REHAB. BRIDGE

: FUND: 1M

. LENGTH (miles 1kin) 2.22/3.57

DESCRPT: 1-16 ACROSS OCONEE RIVER AND OVERFLOWS (10 BRIDGES)

PE: 1994 ROW: NONE " CST:2000 FED Share: GA Share:

UNDERWAY
$9,329,000 $8,396,100
$932,900

PROJECT: 210940- TYPE WORK: SAFETY

FUND: 1M

'LENGTH(mileslkm) 1/1.61

DESCRPT: 1-16SAFETY UPGRADES @ SR 26/338/257/19 & SR 1121BLECKLEY

ASSOCIATED PROJECTS: 21094X-

.PE: 1998 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$8,288,000 $7,459,200
$828,800

PROJECT: 21'0950- TYPE WORK:' 'SAFETY

FUND: 1M

,LENGTH (miles / km) 1.2 / 1.93

DESCRPT:

1-16 SAFETY

U, PGRADES @ I'LOCILAURENSI

3 TREUTLENI ,

2

EMANUEL'

ASSOCIATED PROJECTS: 2I095X-

PE: 1998 ROW: NONE CST: 2000 . FED Share: GAShare:

uNDERWAY
$8,085,000 $7,276,500
$808,500

. PROJECT: 221540- TYPE WORK: . RECSTIREHAB

FUND: STP

'LENGTH (miles 1 km) 0.9/1.45

DESCRPT: SR 19 WB MP MP29.38/w CL DUDLEYTO WITURKEY CRKIMP 30.73

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1997 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $5,000
' '$844,000 $675,200 $168,800

. PROJECT: 221810- TYPE WORK:: 'RECSTIREHAB

FUND: STP '

LENGTH (miles 1 km) .2.62 14.22
DESCRPT: SR 19/DUBLIN FM MULTI-LN @ INDUSTRIAL BLVD NW TO S-I641&CLvr

EXIST. LANES: 02 PROPOSED LANES: 05

PE:1992 ROW: 1997 CST: 2000 fED Share: GA Share:

UNDERWAY UNDERWAY $3,436,000 $2,748,800
$687,200

PROJECT: 231430- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 9.8/15.78

DESCRPT: SR 29IUS 441 FROM CR 471 TO SR 112/WILKINSON -23143X"

0

",

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 23143X-

PROJECT: 232000- TYPE WORK: RECSTIREHAB

FUNb;STP

LENGTH (miles / km) 3 /4.83

DESCRPT: SR 31IUS 319 NB MP 31.0-32.41 SB 38.8-3.4/JOHNSON-23200X

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 23200X-

PE:1993 ROW: 2001 CST:

' UNDERWAY $5,860,000 AFTER 2002

PE:2002 ROW: CST:

s : $25,000 AFTER 2002 AFTER 2002

. PROJECT: 232270- TYPE WORK: REPLACE BRIDGE

' FUND: BRIDGE

LENGTH (miles / km) 0.22 10.35

DESCRPT: SR 26IUS 80 @ PUGHES CREEK 2.8 MI SE OF BREWTON

'PE:2000 ROW: 2002 (;ST:2002 FED Share: GAShare:

$20,000 $10,000 $401,000 $320,800 '~ $80,200

PROJECT: 245395- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileS1 km) 0:22/0.35

DESCRPT: SR 19 @ WHITEWATER CREEK 13.2 MI SE OF RENTZ

PE:2000 ROW: CST:

. $20,000 AFTER 2002 AFTER 2002

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

LAURENS COUNTY

PROJECT: 245396-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) . 0.22/0.35

DESCRPT: SR 19@ BIG FLAT CREEK to MI E OF RENTZ

PE:2000 ROW: CST:

9/16/99 Page 181 of275
$20,000 AFTER 2002 AFTER 2002

PROJECT: 245397- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 19@LITTLEFLATCREEK 7.5 MI S OF DUBLIN

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 245398- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 199 @ PUGHES CREEK 6.9 MI SE OF EAST DUBLIN

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 262570- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 0.3 10.48

DESCRPT: RELOCATE SR 257 ALONG JOINER ST/CS 702 IN DUBLINIINCL CLVT

PE: 1996 ROW: 1999 CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY
$700,000 $560,000 $140,000

PROJECT: 26Y027- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0 10.00

. DESCRPT: SR 31IUS 441 FM CR 272 TO SOUTH OF 1-16 - FOR FED PE; 262027

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 262027-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 26Y064- TYPE WORK: . RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0 /0.00

DESCRPT: SR 31IUS 441 FROM SR 46 TO CR 272 - FOR FED PE; 262064

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 262064-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 271000- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH(mileslkm) 3.42/5.51

DESCRPT: NATHANIEL DRIVE FROM SR 26 TO SR 199 IN EAST DUBLIN

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1994 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$5,623,000 $4,498,400 $1,124,600

PROJECT: 271294- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles 1 km) 0/0.00

DESCRPT: CITY OF DUBLIN MULTI-USE PATHS

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$1,089,000 $871,200

l ~.

U

END OFLAURENS COUNTY

OTH Share:

$217,800

STATE TRANSPORTATION IMPROVEMENTPROGRAM

LEE COUNTY

PROJECT: 431730- TYPE WORK: RECST/REHAB

FUND: STP

ALBANY TIP # HIR-99-5

LENGTH (miles I km) 5.94/9.56

DESCRPT:. SR 91IPHILEMA RD FM CR 5/GRAYES SPGS RD NE TO SR 32

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: 2001 CST:

9116/99 Page 182 of275
$113,000 $1,300,000 AFTER 2002

. p,ROJECT: 462395- TYPE WORK: RECST/REHAB

. FUND: STATE

LENGTH (miles I km) 9.3/14.97

DESCRPT: SR 3IUS 19 FM NORTH OF CR 151 NW TO SUMTER CL @ SMITHVILLE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 46Y395-

PROJECT: 46Y395- TYPE WORK: RECST/REHAB

FUND: NHS

LENGTH (miles Ikm) 0/0.00

DESCRPT: SR 3IUS 19 FM CR 151 TO SUMTER CL - FOR FED PE; 462395

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 462395-

END OF LEE COUNTY

PE: 1992 ROW: 2001 CST:

UNDERWAY $1,938,000 .AFTER ,2002

PE:2000 ROW: NONE CST: NONE

$1,000

"'"

STATE TRANSPORTATION IMPROVEMENT PROGRAM

LIBERTY COcfNTY

PROJECT: 511140- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (mileslkm) 13.3/21.41

DESCRPT: 1-95 FM MCINTOSH CO LINE TO SOUTH OF JERICO RIVER

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1993 ROW: 2000 CST: 2000 FED Share: GA Share:

9116/99 Page 183 of275
. UNDERWAY $53,000 $39,000,000 $31,200,000
$7,800,000 .

PROJECT: 511142- TYPE WORK: REHAB. BRIDGE

FUND: NHS

LENGTH (miles I km) 0.4/0.64

DESCRPT: 1-95 AT SOUTH AND NORTH NEWPORT RIVERS & MCINTOSH COUNTY

EXIST. LANES: 04 PROPOSED LANES: 06

ASSOCIATED PROJECTS: 51114X-

PE: 1993 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$10,450,QOO $8,360,000 $2,090,000

PROJECT: 511152- TYPE WORK: REHAB. BRIDGE I

FUND: NHS

LENGTH (miles I km) 0.05 10.08

DESCRPT: 1-95 @ JERICO RIVER.LlBERTYIBRYAN

EXIST. LANES: 04 PROPOSED LANES: 08

PE: 1993 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$5,236,000 $4,188,800 $1,047,200

PROJECT: 521190- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.32/0.52

DESCRPT: SR 196/@ BAKER SWAMP SLOUGH

EXIST. LANES: 02 PROPOSED LANES: 05

PE: 1984 ROW: 1987 CST: 2001 FED Share: GAShare:

UNDERWAY UNDERWAY
$574,000 $459,200 $114,800 .

END OFLIBERTYCOUNTY



STATE TRANSPORTATION IMPROVEMENTPROGRAM

91/6/99 Page /84 of275

LINCOLN COUNTY

PROJECT: 0000153 TYPE WORK: ENHANCEMENT

FUND: STP

t~.

LENGTH (mileslkm) 0/0.00

. DESCRPT: DOWNTOWN LINCOLNTON STREETSCAPE

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$188,000 $150,400

PROJECT: 231360- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 kny 2.29 13.69

DESCRPT: SR 47 NB FM .2 MI S OF CR 260 TO .5 MIN OF CR 80

EXIST. LANES: 02 PROPOSED LANES: 03

OTH Share:
PE:1997 ROW: 2001 CST: "

$37,600
UNDERWAY $97,000
AFTER 2002

PROJECT: 232310- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

. LENGTH (miles 1 km) 0.34/0.55

DESCRPT: SR 47 @ LITTLE RIVER 10.5 MI SE OF LINCOLNTON

PE:2000 ROW: CST:

, $254,000 AFTER 2002 AFTER 2002

END OFLINCOLN COUNTY



---------------------_._---------_._--------

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page 1850/275

LOWNDES COUNTY

PROJECT: 0000083 TYPE WORK: ENHANCEMENT

.FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: VALDOSTA MULTI-USE TRAIL

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$949,000 $759,200

PROJECT: 410680- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles / km) 0.2/0.32

DESCRPT: PEDESTRIAN FENCING ON BR OVER 1-75- EXIT 2-5-19-20 /41068X

ASSOCIATED PROJECTS: 41068X-

OTH Share:
PE:2002 ROW: NONE CST: 2002 FED Share: . GA Share:

$189,800 $5,000
$120,ODO $108,000 $12,000

PROJECT: 410720- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles / km) 30 /48.30

DESCRPT: 1-75 GUARDRAIL FROM NORTH OF SR 133 TO KINARD BR RD/COOK CO

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 4 I072X-

PE:NONE ROW: LOCL CST: 2000 FED Share:

$4,000,000 $4,000,000

PROJECT: 422280- TYPE WORK: RECSTIREHAB

. FUND: STP

LENGTH (miles / km) 7.38 / 11.88

DESCRPT: SR 125 FM CR 867 TO N. OF HIGHTOWER RDIMOODY AFB N GATE

EXIST. LANES: 04 PROPOSED LANES: 05

PE: 1993 ROW: 1995 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $10,305,000
$8,244,000 $2,061,000

PROJECT: 431480- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 7.33/11.80

DESCRPT: CR 868(OLD US 41) FM SR 7/N ASHLEY ST TO SR 122

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 431485-

PE:2000 ROW: LOCL . . CST:

$237,000 AFTER 2002

PROJECT: 431680- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.66 / 1.06
DESCRPT: SR 7IUS 41 AT CR 570 AND CR 868lHAHIRA RD

PE: 1997 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$660,000 $594,000
$66,000

PROJECT: 442645- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2/0.32

DESCRPT: CR 781/STATEN ROAD@ WITHLACOOCHEE RIVER

PE:2000 ROW: LOCL CST:

$117,000 AFTER 2002

PROJECT: 442780- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) . 0.21 /0.34

DESCRPT: CR 777/CAT CREEK ROAD @ CAT CREEK OVERFLOW SW OF BARRETTS

PE: 1997 ROW: LOCL CS'T:2001 FED Share: GAShare:

UNDERWAY
$338,000 $270,400 $67,600

PROJECT: 442790- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22 /0.35

DESCRPT: CR 777/CAT CREEK ROAD@ CAT CREEK APP 3 MI SW OF BARRETTS

PE: 1997 ROW: LOCL CST: 2001 FED Share: GA Share:

UNDERWAY
$536,000 $428,800 $107,200

.:0.\
f:.',

- ._---------_.__--- ---------~S-T- AT-E-T- RA-N- SP-O- RT-A- TI, O- N I- M..P...ROVEMENT PROGRAM

..
9/16/99

Page 186 of275

LOWNDESCOUNTY-

PROJECT: 442960- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.31/0.50 DESCRPT: SR 122 @ WITH LACOOCHEE RIVER APP 4.5 M1 E OF HAHIRA'

, PE:2000 ROW: CST:

$36,000 AFTER 2002 AFTER 2002

PROJECT: 442961- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.25/0.40

DESCRPT: SR 122 @ CAT CREEK APP 9 MI E OF HAHI~

,

PE:2000 ROW: CST: '

$20,000 AFTER 2002
AFTER200~

PROJECT: 450200 TYPE WORK:' RECSTIREHAB

FUND: STP

LENGTH (miles / km) 2/3.22

DESCRPT: N. FORREST ST IN VALDOSTA FM HILL AVE/SR 38 TO INNER PERiMET

EXIST. LANES: 02 PROPOSED LANES: 05

PROJECT: 450440- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 2.87 14.62

DESCRPT: GORDON STREET/CR 555/CR 720 FM BAYTREE RD TO N FORREST ST

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: LOCL CST: 2002 FED Share: GA Share:
PE:2000 . ROW: LOCL CST:

$127,000
$3,036,000 $2,428,800
$607,200
. $86,000
AFTER 2002

PROJECT: 450510- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) 2.47/3.98

DESCRPT: MT ZION CHURCH RD/CR 188 FM OAK ST TO FORREST ST

EXIST. LANES: 02 PROPOSED LANES: 04

. PE:2000 ROW:LOCL CST:

. $60,000 AFTER 2002

PROJECT: 450520- TYPE WORK: RECSTIREHAB ' F U N D : STP
LENGTH (miles! km) 3.5915.78
DESCRPT: GORNTb ROAD AND PARK AVE FROM BAY TREE ROAD TO LEE STREET
EXIST. LANES: 02 PROPOSED LANES: 04

;'E:'2000 ROW: LOCL 'CST:

. $135,000 AFTER 2002

END OF LOWNDES COUNTY

---_._.__.'-,---_.

. ." ~

-

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199
Page 187 of275

LUMPKIN 'cOUNTY

PROJECT: 0000141 TYPE WORK: ENHANCEMENT

FUND: STP

DESCRP~ DAHLONEGASTREETSCAPES

LENGTH (miles / km) 0/0.00

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$250,000 $200,000

PROJECT: 122370- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1.612.58

DESCRPT: SR 52 WB BETWEEN CR 252 TO JUST NORTH OF CHESTATEE RIVER

EXIST. LANES: 02 PROPOSED LANES: 03

OTJI Share:
PE: 1992 ROW: 2001 CST:

$50,000
UNDERWAY $89,000
AFTER 2002

PROJECT: 132290- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 4.7217.60

DESCRPT: CR I88ILONG BRANCH RD/SR 984 FM END SR 400 TO SR 52

PE:2000 ROW: CST:.

$40,000 AFTER 2002 AFTER 2002

PROJECT: 142345-

!
TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 4.7217.60

DESCRPT: CR 188ILONG BRANCH RD FM END SR 400 @ SR 60 TO SR 52

LUMP SUM PROJECT

PROJECT: 171554- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: GATEWAYS IN THE CITY OF DAHLONEGA

END OF LUMPKIN COUNTY

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:
PE:LOCL ROW: LOCL CST:2000. FED Share:
OTHShare:

$620,000 $496,000 $124,000
$500,000 $400,000 $100,000

fi:
i~ ..
Mj#

----_._ ----,--,-----------_.-------------STATE TRANSPORTATION IMPROVEMENTPROGRAM

MACON'ClJ[jNfy

PROJECT: 332300- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1995

'LENGTH (miles I Am) 0.24/0.39

ROW: 2000

, DESCRPT: SR 49/0GLETHORPE ROAD @ FLINT RIVER OVERFLOW WEST MONTEZUMA

CST: 2000

FED Share:

GA Share:

9/16/99 Page 1880/275
UNDERWAY $6,000
$1,072,000 $857,600 $214,400'

PROJECT: 333070- TYPE WORK:' RECST/REHAB

FUND: STP .

LENGTH (miles / km) 0 /0.00

DESCRPT: SR 127 @ SR 1281 SR 128 @ SR 901 SR 224 @ SR 26 & SIGNING

PE:2000 ROW: 2002 . CST:2002 FED Share: GA Share:

$10,000 $10,000 ' . $292,ODO , $233,600 $58,400

PROJECT: 343340- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE'

LENGTH (miles / kin) 0.27/0.43

DESCRPT: SR 240 @ BUCK CREEK APP 5 MI S OF IDEAL

PE:2000 ROW: 2002 CST: ..

$20,000 $10,000 AFTER 2002

PROJECT: 343350- TYPE WORK: ' REPLACE BRIDGE

FUND: BRIDGE

LENGTH(miles / km) 0.23 /0.37

DESCRPT: SR 329 @ HOGCRA WL CREEK NEAR DOOLY CO LINE

PE:2000", " ROW: 2002 CST:

. $20,000 $10,000
AFTER 2002

PROJECT: 343351- TYPE WORK: REPLACE BRIDG"E I

FUND: BRIDGE

LENGTH (miles/km) 0.27/0.43

DESCRPT: SR 240:@ BUCK CREEK APP 5 MI S OF IDEAL GA.

PE:2000 ROW: CST:

. $20,000 AFTER 2002 AFTER 2002

END OFMACON COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 189 of175
-. - - - , . ; , . - . - - - - - - - - - - - - - - ~M~A~D:I;S:O"N;'C;O~U"N":T;Y;";"\l~~--'--------'--'-'

PROJECT: 121925 TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 4.917.89

DESCRPT: SR 72 FM CR 393 TO CR 392/COLBERT-DANIELSVILLE RD

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 121927-

PE: 1993 ROW: 1996 CST: 2000
GA Share:

UNDERWAY UNDERWAY' $9,450,000
. $9,450,000

PROJECT: 121927- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 1.5 12.42

DESCRPT: 'SR 72 FM CR 392 TO 1-000 IT E OF SR 172

EXIST. LANES: 02 PROPOSED LANES: 04

. ASSOCIATED PROJECTS: 121925-

PE: 1993 ROW: 1995 CST: 2000
GA Share:

UNDERWAY UNDERWAY $3,900,0.00
$3,900,000

PROJECT: 122100- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 2.8/4.51

DESCRPT: SR 72 FM SR 172 EAST TO WES'T CITY LIMITS OF COMER

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECTS: 12YI00-

PE: 1993 ROW: 2002 CST:

UNDERWAY $2,378,000 AFTER 2002

'~:
~~.l

PROJECT: 122180-

TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles Ikm) 5.1/8.21

PE: 1992 ROW: 2000

UNDERWAY $1,986,000

DESCRPT: SR 8 FM CR 228 @ DIAMOND HILL TO NCR 392IDANIELSVILLE &CLVT

CST:

AFTER 2002

,.:g
~.

EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 122185-

PROJECT: 122190- TYPE WORK: RECSTIREHAB

' FUND: STP

LENGTH (mileslkm) 3.9/6.28

DESCRPT: SR 8IUS 29 FM SR 106 TO CR 228 @ DIAMOND HILL/INCL CLVT

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2002 CST:

UNDERWAY $1,834,000 AFTER 2002

PROJECT: 122650- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 9.2/14.81

DESCRPT: SR 72 FM WEST CITY LIMITS OF COMER TO E OF BROAD RVRlELBERT

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 12265X 12Y650-

PROJECT: 12YIOO- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 72 FM SR 172 E TO W CITY LIMITS/COMER- FOR FED PEl 122100

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECTS: 122100-

PROJECT: 12Y650- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0 /0.00

DESCRPT: SR 72 FM WCL OF COMER TO BROAD RVRlELBERT -FOR FED PE/122650

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 122650-

PROJECT: 132400- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1.2 11.93

DESCRPT: SR 106 M.P. 1.35 N. OF SR 106 TO MP 2.55 N OF CR 177

EXIST. LANES: 02 PROPOSED LANES: 03

n
~j .

PE: 1993 ROW: 2002 CST:

UNDERWAY ~ $3,565,000 AFTER 2002

PE:2000 ROW: NONE CST: NONE

$1,000

PE:2000 ROW: NONE CST: NONE

$1,000

PE: 1996 ROW: 2001 CST:

UNDERWAY. $77,000
AFTER 2002

STATETRANSPORTATIONIMPR(:)VEMNTPROGRAM

9/16199' Page 190 of275

MADISON COUNTY

PROJECT: 170787- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (miles / km) 0.2/0.32

DESCRPT: CR 221IMCCARTY-DODD ROAD @ BRUSH CREEK 2~2 MI NE OF COLBERT

PE:2000 ROW: LOCL CST:

$14,000 . AFTER 2002

END OFMADISON COUNTY

J,..
).

I"

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199

Page 191 of275

.1~.i.

MARION COUNTY
PROJECT: 332280- TYPE WORK: REPLACE BRIDGE

FUND:. BRIDGE

PE: 1998

UNDERWAY

I"

LENGTH (miles 1 km) 0.21/0.34 DESCRPT: SR 41/BROAD STREET @ CEN. OF GA. RAILROAD IN BUENA VISTA

ROW: 2000 CST: 2001 FED Share:

$333,000 $938,000 $750,400

GA Share:

$187,600

i

Jl

PROJECT: 342895- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1994

UNDERWAY

LENGTH (miles Ikm) 0.21/0.34

ROW: LOCL

~

DESCRPT: CR 1281DOYL~ ROAD @ OOCHEE CREEK 2.3 MI N OF SR 26

CST: 2000 FED Share:
GA Share:

$361,000 $288,800
$72,200

PROJECT: 343010- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1km) 0.23 10.37

DESCRPT: SR 355 OVER JUNIPER CREEK AT TALBOT COUNTY LINE

PE: 1997 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $57,000
$1,127,000 $901,600 $225,400

PRO.fECT: 343355- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

D~SCRPT: SR 137 @ OOCHEE CREEK 2.5 MI E OF JCT SR 41

PE:2000 ROW: 2002 CST:

$20,000 $10,000 AFTER 2002

PROJECT: 343356- TYPE WORK: . REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.23 10.37

DESCRPT: SR 137 @ BUCK CREEK.7 MI W OF JCT SR 240 .

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

END OFMARION COUNTY

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 192 0/275

MCDUFFIE COUNTY

PROJECT: 227815- TYPE WORK: REPLACE BRIDGE

FUND: 'BRIDGE

LENGTH (miies 1 km) 0.23/0.37

DESCRPT: SR 10lUS 78 @ HART CREEK 9.5 MI N OF THOMSON

PE:2000 " ROW: CST: ,"

$20,000 AFTER 2002 AFTER 2002.

PROJECt: 227816- TYPE WORK: REPLACE BRIDGE

FUND:' BRIDGE

LENGTH (miles 1 km) 0.24/0.39 " DESCRPT: SR 10lUS 78 @ BIG CREEK 8 MI NOFTHOMSON: ." -: ~

, 'PE:'2000 ROW: CST:

$20,000 AFTER 2002 ,AFTER 2002

," ,.'

PROJECT: 22Y250- TYPE WORK: RECSTIREHAB

FUND: NHS

, LENGTH (miles 1 km) 0/0,00

DESCRPT: SR 17110FM SR 43 TO CR 6/SMITH MILL RD -"FOR FED PE; 222250

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECfS: 222250-

PROJECT: 22Y255- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (mileS 1 kin) , 0 10.00

DESCRPT: SR 17110FM CR 6/SMITH MILL RD TO WASH.BVP-FOR FEDPE;222255

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECfS: 222255-

,,

PROJECT: 232320- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE '

LENGTJ:I(miles Ikm) 0.23/0.37

DESCRPT: SR 47IUS 221 @HEADSTALLCREEK5.3 MI S OF DEARING . ,

PE:2000 ROW: NONE CST:NONE

$1,000

PE:2000 ROW: NONE eST: NONE ,

" $1,000

PE:2000 ROW: CST:"

, $20,000 AFTER 2002 AFTER 2002

END OF MCDUFFIE COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

MCINTOSH COUNTY

PROJECT: 511110- TYPE WORK: RECSTIREHAB

. FUND: NHS

LENGTH (mileslkm) 4.21/6.78

DESCRPT: 1-95 FM ALTAMAHA RIVER @ GLYNN CL TO I-MILE NORTH OF SR 251

EXIST. LANES: 02 PROPOSED LANES: 06

ASSOCIATED PROJECTS: 511112-

PE: 1993 ROW: 2001 CST:

9/16/99 Page 193 of275
UNDERWAY $17,000
AFTER 2002

PROJECT: 511120- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 8.4/13.52

DESCRPT: 1-95 FM I-MILE NORTH OF SR 251 TO SR 57 - PHASE 1

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1993 ROW: 2001 CST:

UNDERWAY $11,000
AFTER 2002

PROJECT: 511365- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles / km) 0.2/0.32 .

DESCRPT: 1-951 SCALE REPLACEMENT & UPGRADE 2 WEIGH STATIONS # 5E & 6E

PROJECT: 542070- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH.(miles / km) 2.5 /4.03

DESCRPT: SR 251 FM MCINTOSH IND PK(MP 11) TO US 17/SR 25(INCL BRS)

EXIST. LANES: Q2 PROPOSED LANES: 05

PE: 1995 ROW: 2000 CST: 2000 FED Share: GAShare:
PE:2000 ROW: 2001 CST:

UNDERWAY $100,000
$8,754,000 $7,878,600
$875,400
$106,000 $866,000 AFTER 2002

PROJECT: 542420- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

.DESCRPT: SR 57 @ YOUNGS SWAMP .12 MI W OF JCT 1-95

PE:2000 ROW: CST:

$38,000 AFTER 2002 AFTER 2002

PROJECT: 542421- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23/0.37

DESCRPT: SR 57 @ JACKIE CAMP SWAMP 3 MI W OF JCT 1-95

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 571412- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: TRAIL HEAD CENTER IN DARIEN & MULTI-USE TRAILS

PROJECT: 571414- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles / km) 0 /0.00
DESCRPT: MULTI-USE TRAIL FM BEACH RD TO SAPELO ISLAND LIGHTHOUSE

END OFMCINTOSH COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTHShare:

$1,211,000 $968,800 $242,200
$268,000 $214,400 $53,600

STATE TRANSPORTATION IMPROVEMENT PROGRAM

MERIWETHER COUNTY

PROJECT: 321880- TYPE WORK: REHAB. BRIDGE

FUND: STP

LENGTH (miles I km) 0.25/0.40 DESCRPT: SR 41 REPL SCL RR BR OVER SR41.W OF WARM SPRlNGSIINCL DETOUR EXIST. LANES: 02 PROPOSED LANES: 05

PROJECT: 332800- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) 6.99 I I 1.25

DESCRPT: SR 18/74/109 AT FIVE LOCATIONSIUPSON - 33280X \

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 33280X-

PE: 1992 ROW: 2000 CST: 2002 FED Share: GA Share: OTHShare:
PE: 1999 ROW: 2001 CST: 2002 FED Share: GA Share:

9116/99 Page 194 of275
UNDERWAY $505,000
$2,996,000 $2,396,800
$579,200 $20,000
UNDERWAY $138,000
'$4,036,000 $3,228,800
$807,200

PROJECT: 333180- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.21/0.34.

DESCRPT: SR 85 - SR 74 @ PAPPYS CREEK.5 MI N OF WOODBURY

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

$20,000 $10,000 $270,000 $216,000 $54,000

PROJECT: 333181- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

I

LENGTH (miles I km) 0.26 10.42

DESCRPT: SR 85 - SR 74 @ RED OAK CREEK 3.5 MI N OF WOODBURY

! PE:.20oo ROW: 2001 CST: 2002 , FEDShare: GAShare:

$20,000 $10,000 $859,000 $687,200 $171,800

PROJECT: 333182 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.26 10.42

DESCRPT:SR 85 - SR 74 @ WHITE OAK CREEK .4 MI N OF ALVATON

PE:2000 ROW: 2001 CST:.2002 FED Share: GAShare:

$20,000 $10,000 $870,000 $696,000 $174,000

PROJECT: 333183- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles /km) 0.22/0.35

DESCRPT: SR 85 ALT @ CSX RAILROAD IN WARM SPRINGS

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

$20,000 $10,000 $386,000 $308,800 $77,200

PROJECT: 333184- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 85 ALT @POUND CREEK 2 MI S OF WOODBURY

PE:2000 ROW: 2001 CST:

$20,000 $10,000 AFTER 2002

r.- .

PROJECT: 333200- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR 85 @ CANE CREEK 1.7 MI S OF WOODBURY

PE:2000 ROW: 2001 CST:

$20,000 $10,000 AFTER 2002

PROJECT: 333201- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.27/0.43

DESCRPT: SR 85 @ CSX RAILROAD IN WOODBURY

PE:2001 ' ROW: CST:

$40,000 AFTER 2002 AFTER 2002 ,

I

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page 195 of275

I.:~
'" " ~
-'
.

MERIWETHER COUNTY
PROJECT: 333202- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles / km) 0.21/0.34

ROW: 2001

$10,000

I

DESCRPT: SR 18IUS 27 ALT. @ KENDALL CREEK 2 MI S OF GREENVILLE

CST: 2002 FED Share:

$270,000 $216,000

GAShare:

$54,000

I

PROJECT: 363850- TYPE WORK: RECSTIREHAB

FUND: STATE

PE:NONE

LENGTH (miles / km) 0.25 /0.40

ROW: 2000

$131,000

I

DESCRPT: WARM SPRINGS SOUTH BYPASSIE ST/SR 976 FM SR 85W TO SR 41 EXIST. LANES: 02 PROPOSED LANES: 04

CST: 2001

$175,000

GAShare:

$175,000.

I

END OFMERIWETHER COUNTY

I

m
If
I
~

STATE TRANSPORTATION IMPROVEMENTPROGRAM

MILLER-COUNTY

PROJECT: 422210- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 9.3/14.97

DESCRPT: SR llUS 27 FR W CL @ COLQUITT TO CR 279IDAMASCUSHlLTON RD

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422215- 42Y21O-

PE: 1993 ROW: 2001 CST:

9116199 Page 196 0/275
UNDERWAY $2,857,000 AFTER 2007

PROJECT: 42Y210- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: SR llUS 27 FR W CL @ COLQUITT TO CR 279 - FOR FED PE; 422210

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 422210-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 431190- TYPE WORK: RECSTIREHAB

FUND: STP

. LENGTH(mileslkm) 7.3/11.75

DESCRPT: SR 310 FM DECATUR CO LINE TO SR l/COLQUITT

PE: 1992 ROW: 2001 CST:

UNDERWAY $212,000
AFTER 2002

PROJECT: 432140- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.24/0.39

DESCRPT: SR 91 @ AYCOCK CREEK APP 4 MI S OF COLQUITT

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 432141- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23 10.37

DESCRPT: SR 91 @ CYPRESS CREEK 2.5 MI W OF COLQUITT

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 471434- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0 10.00

DESCRPT: CITY OF COLQUITT STREETSCAPE

END OF MILLER COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
ottrsso

$236,000 $188,800
$47,200



----------------------_ _ ._-~...- .....- . --"'" -----------_.

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

9116/99

Pagel 97 0(275

MITCHELL COUNTY

PROJECT: 422690- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

,LENGTH (miles 1 km) 0,22/035

DESCRPT: SR 3IUS 19- SR 300 SBL @ WETHINGTON SLOUGH S OF BACONTON

PE:2000 ROW: CST:

$20,0'00 AFTER 2002 AFTER 2002

PROJECT: 422691- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 022/035

DESCRPT: SR 3IUS 19- SR 300 SBL @ RACCOON CRK SOUTH OF BACONTON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 442975- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 023/037

DESCRPT: SR 93 @ LOST CREEK APP 1.5 MI N OF COTTON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 442976- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH(miles 1 km) 0.22/035

DESCRPT: SR 93 @ SPENCE MILL CREEK .2 MI N OF GRADY CO LINE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 462614- TYPE WORK: RAILROAD CROSSING FUND: STP LENGTH (miles 1 km) 0.2/032
DESCRPT: CS 817/SCOTT STREET @AGLRRR#7230641 [MP .02] LUMPSUM PROJECT
END OF MITCHELL COUNTY

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

..
$100,000 $90,000 $10,000

,
~

..

s .~

:f ! ~'

STATE TRANSPORTATION IMPROVEMENT PROGRAM

MONROE COUNTY

PROJECT: 310710- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH(mileslkm) 1.08/1.74 DESCRPT: 1~75@PATE RD/CR 286 TO FULL DIAMOND INTERCHANGE

PE: 1997 ROW: 2000 CST: 2001 FED Share: GAShare:

9116/99 Page 198 of275
UNDERWAY $700,000
$4,740,000 $3,792,000
$948,000

PROJECT: 311618- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles I km) .0/0.00

DESCRPT: 1-75 WATER AND SEWER LINES TO REST AREA NO 22

LUMP SUM PROJECT

PE: 1997 ROW: NONE CST: 2000 FED Share:

UNDERWAY
$3,500,000 $3,500,000

PROJECT: 311740- TYPE WORK: REHAB. BRIDGE

FUND: 1M

.LENGTH (miles I km) 0.25/0.40

. \

DESCRPT: 1-475/SR 408 NBL @ 1-751 ADD ONE LANE & REPLA BRIDGE DECK

EXIST. LANES: 02 PROPOSED LANES: 03

PROJECT: 343167- TYPE WORK: REPLACE BRIDGE

: FUND: BRIDGE

LENGTH (milesI km)0.23 10.37

DESCRPT: SR 42 @ ECHECONNEE CREEK 6 MI E OF CULLODEN .

PE: 1994 ROW: 2000 CST: 2001 FED Share: GAShare:
PE: 1999 ROW: 2002 CST:

UNDERWAY $50,000
$430,000 $387,000 $43,000
UNDERWAY $50,000
AFTER 2002

PROJECT: 370811- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles/ km) 0.25/0.40

DESCRPT: CR 163lWESTBROOKS RD OVER TOWALIGA RIVER

PE: 1993 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$410,000 $328,000 $82,000

..

PROJECT: 370813 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.21/0.34

. PE: 1999 ROW: LOCL

UNDERWAY

DESCRPT: CR1581ROCKY CREEK ROAD @ LITTLE TOWALIGA RIVER W OF 1-75

CST: 2002

$228,000

FED Share:

$182,400

GAShare:

$45,600

PROJECT: 371778- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0 10.00

DESCRPT: CITY OF FORSYTH REHABILITATION OF RAILROAD BUILDINGS

END OFMONROE COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$165,000 $132,000
$33,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

MONTGOMERYCOUNTY

PROJECT: 522520- . TYPE WORK: RECSTIREHAB

FUND: STP

LENGT:H (miles / km) 2.4/3.86

DESCRPT: SR 15 BTWN HIGGSTON & TARRYTOWN/NB MP 5.0-6.4ISB 8.7-9.7

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1995 ROW: 2001 CST: 2002 FED Share: GA Share:

9/16199 Page 199 of275
UNDERWAY $5,000
$1,057,000 $845,600 $211,400

PROJECT: 532330- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: CR 169ITHOMPSON POND ROAD @ TIGER CREEK 4 MI SE OF TARRYTOWN

PE:2000 ROW: LOCL CST:

$20,000 AFTER 2002

PROJECT: 542410- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22 /0.35

DESCRPT: SR 56 @ MILLIGAN CREEK IN CITY LIMITS OF UVALDA

PE:2000 ROW: 2002 CST:

$20,000 $10,000 AFTER 2002

PROJECT: 550610- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 0.65 /1.05

DESCRPT: SR 292NIDALIA FM MORN'SIDE - LOWERY WIRIGT ON WILSON/55061X

ASSOCIATED PROJECTS: 55061X-

PROJECT: 570760- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: CR 12 @ TIGER CREEK 3 MI SE OF TARRYTOWN

PE: 1995 ROW: LOCL CST: 2001 FED Share: GAShare:
PE:2002 ROW: LOCL CST:

UNDERWAY
$2,000,000 $1,600,000
$400,000
$20,000
AFTER 2002

PROJECT: 571418- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/-0.00

DESCRPT: CITY OF AILEY RAILROAD DEPOT REHABILITATION

PROJECT: 571455- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: CR 1 @ TIGER CREEK 1 MI E OF TARRYTOWN

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:2000
ROW: LOCL CST:


$156,000 $124,800
. $31,200 $20,000
AFTER 2002

END OFMONTGOMERY COUNTY

o. v

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 200 of275

MORGAN COUNTY

PROJECT: 210920- TYPE WORK: SAFETY

FUND: 1M

PE: 1998

LENGTH (miles / km) I /1.61

ROW: NONE

DESCRPt: 1-20 SAFETY UPGRADES@NEWBORN RDISR83/SR24IBUCKHEADISR44GREEN

CST: 2000

".

FED Shore:

. ASSOCIATED PROJECTS: 21092X-

GA Shore:

UNDERWAY
$11,550,000 $10,395,000
$1,155,000

PROJECT: 245i50- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (iniles / km) 5 /8.05

DESCRPT: SR 83 RELOC/CR244 FM SR 83IBOSTWICK TO SR 24/APALACHEE

PE:2000 ROW: 2001 .CST:

$50,000 $80,000 AFrER2002

PROJECT: i45285- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21/0.34

DESCRPT: CR 2511SEVEN ISLAND ROAD @SUGAR CREEK 1.8 MI S OF BUCKHEAD

PROJECT: 271260- TYPE WORK: ENHANCEMENT

FUND: STP

. LENGTH (miles / km) 1.83 12.95

DESCRPT: SR 24IUS 441 FM 1-20 TO WARD RD IN MADISON & STILANDSCAPING

END OFMORGAN COUNTY

PE: 1999 ROW: LOCL CST: 2001 FED Shore: GAShore:
PE:LOCL ROW: LOCL CST: 2000. FED Shore:
orusso

UNDERWAY $568,000 $454,400 $113,600
$1,681,000 $1,344,800
$336,200

.

..

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99

Page 201 of275

I

MURRA Y COUNTY

PROJECT: 620399- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1996

UNDERWAY

LENGTH (miles / km) 0.17/0.27

ROW: 1996

UNDERWAY

.1

DESCRPT: SR 52 @CSX RR IN CHATSWORTH

CST: 2000 FED Share:

$1,017,000 $813,600

GA Share:

$203,400

I

PROJECT: 621260- TYPE WORK: NEW CONSTRUCTION FUND: STP .

PE: 1992

UNDERWAY

LENGTH (miles / km) 1.2/1.93

ROW: 2001

$51,000

I

DESCRPT: SR 282 RELOCATION FM SR 61IUS 411 E TO CR 309 EXIST. LANES: 00 PROPOSED LANES: 02

CST:

AFTER 2002

I~

PROJECT: 631550- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 4/6.44

DESCRPT: SR 225/SPRING PLACE BYP - NEW HOPE RD TOSR 225 S OF MILL CK

~.::
it

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: 2000 CST:

UNDERWAY $2,856,000 AFTER 2002

,If.

PROJECT: 632780- TYPE WORK: IMPROVE INTERSECTION FUND: STP

i

LENGTH (miles / km) 0.42/0.68

PE: 1997 ROW: LOCL

UNDERWAY

E,r'

DESCRPT: SR 2/SR 61/ US 411 @ DUVALL ROAD/CR 34 LUMP SUM PROJECT

CST: 2000 FED Share:
GAShare:

$167,000 $150,300
$16,700

PROJECT: 642370- TYPE WORK: NEW CONSTRUCTION . FUND: STP LENGTH (miles / km) 0.15 /0.24
DESCRPT: CR 19/0LD FEDERAL ROAD GRADE SEPARATION AT CSX RAILROAD

PE:2000 ROW: LOCL 'CST:

$15,000 AFTER 2002

PROJECT: 642410- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 282 @ ROCK CREEK 5.3 MI S OF CHATSWORTH

PE:2001 ROW: CST:

$20,000 AFTER2002 AFTER 2002

PROJECT: 671212- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: MURRAY COUNTY BIKE LANES PHASE 1

PE:LOCL ROW:LOCL CST: 2000 FED Share:

OTHShare:

PROJECT: 671230- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH(miles/km) 0/0.00

DESCRPT: RELOCATE CR 23; CG>NSTRUCT A CANOEIKA YAK RAMP & PARKING AREA

. PE:2000 ROW: CST:

$233,000 $186,400
$46,600 $50,000 AFTER 2002 AFTER 2002

END OFMURRA Y COUNTY

.......

.

D

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99

Page 202 of275

MUSCOGEE COUNTY

PROJECT: 0000099 TYPE WORK:' ENHANCEMENT

FUND: STP

COLUMBUS TMA TIP#

LENGTH (mileslkm) 0/0.00

DESCRPT: WARM SPRINGS RAIL LINE BlKE/PED TRAIL

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$1,250,000 $1,000,000

PROJECT: 3 I 1445- TYPE WORK: RECSTIREHAB

FUND: NHS

COLuMBus TMA TIP # 91-ST-2001

LENGTH (miles 1 km) 2.83/4.56

DESCRPT: 1-18'5/COLUMBUS FM SR 520 TO ST MARYS ROAD

EXIST. LANES: 04 PROPOSED LANES: 06

ASSOCIATED PROJECTS: 311630-

OTH Shore:
PE: 1992 ROW: 2000 CST: 2000 FED Share: GA Share:

$250,000
UNDERWAY $319,000
$13,966,000 $11 , 172,800
$2,793,200

PROJECT: 311630- TYPE WORK: RECSTIREHAB

FUND: 1M

COLiJMBUS TMA TIP # 91~ST-2001

LENGTH (miles I km) 1.61/2.59

DESCRPT: 1-185 INTERCHANGE AT SR 1

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 311445-

-rs. 1994
ROW: 2000 CST: 2000 FED Share: GAShare:

UNDERWAY $2,107,000 $7,210,000 $6,489,000
$721,000

PROJECT: 321810- TYPE WORK: REHAB. BRIDGE

FUND: NHS

COLUMBUS TMA TIP # 86-UD-3001

LENGTH (miles /km) 0.2510.40

DESCRPT: SR llUS 27/4TH AVE / VETERANS PKWY FM 13TH ST TO 19TH ST

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1992 ROW: 1998 CST: 2001 FED Share: GAShare:

UNDERWAY UNDERWAY $5,454,000 $4,363,200 $1,090,800

. PROJECT: 332780- TYPE WORK: RECSTIREHAB

FUND: STP

COLUMBUS TMA TIP # ST-2006-LR

LENGTH(miles/km) 0.71/1.14

DESCRPT: ST MARY'S RD FM FARR ROAD TO NORTHSTAR DRIVE

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: LOCL CST:

$125,000 AFTER 2002

.

PROJECT: 332820- TYPE WORK: RECSTIREHAB

FUND: STP

COLUMBUS TMA TIP# 98-SR-Ol

LENGTH (mileslkm) 4.1616.70

PE: 1998 ROW: 2002

UNDERWAY $12,000,000

DESCRPT: SR1.'HAMILTON RDFM OLD MOON RD TO FORTUNE HOLE RDIHARRIS CO

CST:

AFTER 2002

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 33282X-

PROJECT: 350690- TYPE WORK: RECSTIREHAB

FUND: STP

COLUMBUS TMA TIP # 86-SR-I00l

LENGTH (miles Ikm) 1.04/1.67

DESCRPT: SR 22 SPURIMACON RD @ AUBURN AVE & BOXWOOD RD IN COLUMBUS

PE: 1992 . ROW: 1997 CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY
$868,000 $694,400 $173,600

PROJECT: 350730- TYPE WORK:' RECSTIREHAB

FUND: STP

PE: 1993

COLUMBUS TMA TIP # 86-SR-2007

LENGTH (miles 1 km) 1.9/3.06

ROW: 1998

DESCRPT: TALBOrrON RD/SR 982/COLUMBUS PM 7TH AVE TO WOODRUFFIHILTON-Y

CST: 2001

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

ASSOCIATED PROJECTS: 35Y730-

GA Share:

UNDERWAY UNDERWAY $5,064,000 $4,051,200 $1,012,800

PROJECT: 350780- . TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1992

COLUMBUS TMA TIP # 79-SR-2003

LENGTH (miles 1 km) 2.14/3,45

ROW: 2000

DESCRPT: FORREST RD FM MACON{+MACON IMPROV} TO WOODRUFF FAlFLOYD RD-Y CST: 2002

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

ASSOCIATED PROJECTS: 35Y780-

GA Share:

UNDERWAY $947,000
$6,073,000 $4,858,400 $1,214,600

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 203 of275

MUSCOGEE COUNTY

PROJECT: 350785- TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1992

COLUMBUS TMA TIP # 79-SR-2016

LENGTH (miles I km) 1.9/3.06

'ROW:NONE

DESCRPT: FORREST RDISR 983 FM WOODRUFF FARMIFLOYD RD TO SCHATULGA &Y

CST: 2002

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

ASSOCIATED PROJECTS: 35Y785-

GAShare:

UNDERWAY
$4,825,000 $3,860,000
$965,000

PROJECT: 350790- TYPE WORK: RECSTIREHAB

FUND: STP

COLUMBUS TMA TIP # 79-SR-2020

LENGTH (miles I km) 0.91 11.47

DESCRPT: ST MARYS RD/CS 2108/COLUMBUS FM BUENA VISTA TO ROBIN RD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW:LQCL CST: 2001 FED Share: GAShare:

UNDERWAY
$1,939,000 $1,551,200
$387,800

PROJECT: 350796- TYPE WORK: RECSTIREHAB

FUND: STP

COLUMBUS TMA TIP # 86-SR-2010

LENGTH (miles / km) 1.8512.98

DESCRPT: BUENA VISTA RD/COLUMBUS FM WYNNTON RD SE TO ILLGES RD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: LOCL CST:20Q2 FED Share: GAShare:

UNDERWAY
$4,484,000 $3,587,200
$896,800

~;" .," "

PROJECT: 350860- TYPE WORK: RECSTIREHAB

FUND:, STP ,

COLUMBUS TMA TIP # 91-SR-2001

LENGTH (mileslkm) 1.2512.01

PE: 1993 ROW: LOCL

UNDERWAY

DESCRPT: FARR RD/CS392 FM OLD CUSSETA RD/CR 62 TO ST MARYS RD/CS2108

CST: 2002

$3,224,000

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

$2,579,200

GAShare:

$644,800

PROJECT: 350870- TYPE WORK: RECSTIREHAB

FUND: ,NHS

COL.UMBUSTMA TIP # 93-BR-I002

LENGTH (mileslkm) 3.43/5.52

DESCRPT: SR 22 SPIMACON RD FM WOODRUFF FARM RD/CR 99 TO SR 221US 80

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 350875-

PE: 1992 ROW: 1999 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $8,565,000 $6,852,000 $1,713,000

PROJECT: 350875- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

COLUMBUS TMA TIP # 93-BR-I001

LENGTH (mileslkm) 0.02/0.03

DESCRPT: SR 22 SPIMACON RD @ BULL CREEK

EXIST. LANES: 02 PROPOSED LANES: 04
. .ASSOCIATED PROJECTS: 350870-

PROJECT: 350880- TYPE WORK: RECSTIREHAB

FUND: NHS

COLUMBUS TMA TIP # 92-SR-200 1

LENGTH (miles I km)' 1.67 12.69

DESCRPT: SR 22 SP FM REESE RD/CS 2111 TO WOODRUFF FARM RD/CR 99

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$471,000 $376,800
$94,200

PE: 1992 ROW: 1999 CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY $4,081,000 $3,264,800
$816,200

PROJECT: 351000- TYPE WORK: IMPROVE INTERSECTION FUND: STP

PE: 1996

UNDERWAY

COLUMBUS TMA TIP # 79-SR-2004

LENGTH (miles I km) 0.2/0.32

ROW: LOCL

DESCRPT: SR 22SP AT BROWN AVENUE AND PEACOCK AVENUE

CST: 2000

$320,000

FED Share:

$288,000

r~

L

PROJECT: 351020- TYPE WORK: RECSTIREHAB

FUND: STP'

GA Share: PE: 1998

$32,000 UNDERWAY.

COLUMBUS TMA TIP # 86-SR-2002

LENGTH (miles I km) 0.3 10.48

ROW: LOCL

Ui" ~

DESCRPT: CS 1425154THSTREETFMGROVEAVETOBEALLWOODCONN. EXIST. LANES: 02 PROPOSED LANES: 04

CST: 2002 FED Share:

$685,000 $548,000

GA Share:

$137,000

STATE TRANSPORTATioN IMPROVEMENTPROGRAM

9116/99 Page 204 of275

MUSCOGEE COUNTY

PROJECT: 35i030- TYPE WORK: RECSTIREHAB

FUND: STP

COLUMBUS TMA TIP # MN-2005

LENGTH (miles I km) 2.8/4.51

DESCRPT: CS 22621MOON ROAD FROM WILBUR ROAD TO HAMILTON ROAD

EXIST. LANES: 02 PROPOSED LANES: 04 '

PE:2000 , ROW: LOCL
CST:

$500,000 AFTER 2002

PROJECT: 351190- TYPE WORK: RECSTIREHAB

FUND: STP ,

COLUMBUS TMA TIP # BV-2002

LENGTH (mileslkm) 0.41/0.66'

DESCRPT: BUENA VISTA ROAD FM 1-185 TO DOGWOOD DRIVE

EXIST. LANES: 05 PROPOSED LANES: 06

PE:2002 " . ROW: LOCL
CST: 2002 FEDShare: '
GAShare:

$100,000
$700,900 $560,000 $140,000

PROJECT: 351200- TYPE WORK: RECSTIREHAB

FUND: sre , , '

COLUMBUS TMA TIP # 98-SR-1660

LENGTH (miles Ikm) 2.06/3.32

'DESCRPT: MILLER RD/CS 1660 FM WARM SPRINGS RD TO MACONRDISR 22 SPUR

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1999 ROW: LOCL CST: 2002 FED Share:' GAShare:

UNDERWAY
$6,000,000 $4,800,000 $1,200,000

, ,PROJECT: 35Y730- TYPE WORK: .. RECSTiREHAB

ic.iND: sui,' "" ,

COLUMBUS TMA TIP # 86-SR-2oo7 , ' . ,

LENGTH (miles I km) 0/0.00'"

DESCRPT: TALBOITON RD FM 7TH AVE TO WOODRUFFIHILtON- FOR Q23 $ 350730

EXIST. LANES: 02 PROPOSED LANES: 04

'ASSOCIATED PROJECTS: 350730-

PE:NONE ROW: NONE " CST:2ool
FED Share: GAShare:

$2,526,000 $2,020,800
$505,200

PROJECT: 35Y780- TYPE WORK: RECSTIREHAB' FUND: STP

COLUMBUS TMA TIP # 79-SR-2003

LENGTH (miles I km) 0/0.00

DESCRPT:FORREST RD FM MACON RD TO WOODRUFF FARM RD- Q23's 350780

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 350780-

./ "

PE:NONE ROW: 2000 . 'CST:NONE

$3,828,000 -

.

PROJECT: 35Y785- TYPE WORK: RECSTIREHAB

FUND: STP

PE:NONE

COLUMBUS TMA TIP # 79-SR-2016

LENGTH (miles I km) , 0/0.00'

ROW: 2000

DESCRPT: FORREST RD FM WOODRUFF FARMIFLOYD TO SCHATULGA-Q23 $; 350785

eST: NONE

EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 350785-

. .',

PROJECT:' 371750- TYPE WORK: NEW CONSTRUCTION FuND: HPP

COLUMBUS TMA TIP # 98-NB-1998

LENGTH (miles/km) 0/0.00

DESCRPT: i-185 NOISE BARRIERS FM MACON RD TO COLLEGE DR

PE: 1998' . ROW:NONE . . 'CST:2000 , FED Share: GAShare:

UNDERWAY
$459,000 $367,200 $91,800

PROJECT: 371762- TYPE WORK: ,ENHANCEMENT

FUND: STP

COLUMBUS TMA TIP # 98-NRVRWLK '

LENGTH (miles I km) 0/0.00

DESCRPT: RIVERW ALK TRAIL ALONG CHAITAHOOCHEE RIVER PHASE n

END OFMUSCOGEE COUNTY ,i

PE:LOCL ROW:LOCL " CST: 2000 , FED Share:

$1,250,000 $1,000,000

OTHShare:

$250,000 e

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

Page 205 of275

.'~I;

NEWTON COUNTY

PROJECT: 0000168 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles I km) 0/0.00

ROW: LOCL

I

DESCRPT: COVINGTON WEST STREETSTREETSCAPE

CST: 2001 FED Share:

$164,000 $131,200

I'

PROJECT: 210530- TYPE WORK: RECSTIREHAB

FUND: 1M

OTHShare: PE: 1993

$32,800 UNDERWAY

LENGTH (miles I km) 0.71 11.14

ROW: 2000

. $4,129,000

I

DESCRPT: 1-20@ SR 142-121COVlNGTON (lNCL RELOC OF FRONTAGE RD/CR 12) EXIST. LANES: 02 PROPOSEDLANES: 04

CST: 2002 FED Share:

$4,223,000 $3,800,700

ASSOCIATEDPROJECTS: 231220-

GA Share:

$422,300

PROJECT: 210810- . TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 1.8212.93

DESCRPT: 1-20FM ALCOVY ROAD INTCHTO SR 142 INTCH IN COVINGTON

EXIST. LANES: 04 PROPOSEDLANES:06

PE: 1998 ROW: 2000 CST: 2002 FED Share: GA Share:

UNDERWAY $110,000
$5,883,000 $4,706,400 $1,176,600

PROJECT: 210860- TYPE WORK: NEW CONSTRUCTION FUND: NHS

PE: 1997

UNDERWAY

LENGTH(mileslkm) 0.48/0.77

ROW: NONE

DESCRPT: 1-20AT EXIT 45NALCOVY ROAD - LIGHTING

CST: 2000

$338,000

::H>li.

LUMPSUM PROJECT

11

FED Share: GA Share:

$270,400 $67,600

PROJECT: 210870- TYPE WORK: NEW CONSTRUCTION FUND: NHS LENGTH (miles I km) 0.24/0.39
DESCJlPT: 1-20AT EXIST 46/SR 142 - LIGHTING LUMP SUM PROJECT

PE: 1997 ROW;'NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$266,000 $212,800 $53,200

PROJECT: 231210- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I kin) 4 /6.44

DESCRPT: SR 1621SALEM RD FM BROWNBRDGE RD TO SIFLATSHOALSIROCKDALE

EXIST. LANES: 02 PROPOSEDLANES: 06

ASSOCIATEDPROJECTS: 23121X-

PE: 1999 ROW: 2002 CST:

UNDERWAY $600,000



AFTER 2002

PROJECT: 231220- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1.0711.12

DESCRPT: SR 142 FM S OF SR 121US 278 NORTH TO N OF CR 12 IN COVINGTON

EXIST. LANES: 02 PROPOSEDLANES:04

ASSOCIATED PROJECTS: 210530-

PE: 1997 ROW: 2000 CST: 2002 FED Share: GA Share:

UNDERWAY $293,00Q
$3,750,000 $3,000,000
$750,000

PROJECT: 231625- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) 1.3312.14

DESCRPT: SR 81 PASSING LANE SW OF PORTERDALE FM MP 5.33 TO MP 4.0

EXIST. LANES: 02 PROPOSEDLANES: 03

PE: 1999 ROW: 2001 CST:

UNDERWAY $176,000
AFTER 2002

. PROJECT: 231630- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km)
DESCRPT: SR 12IUS278 FM nrsr E OF MILL ST E TO SR 142/S-774
EXIST. LANES: 02 PROPOSEDLANES: 04
ASSOCIATEDPROJECTS: 231635-

3.4515.55

.t ....:.~
:3

PE: 1998 ROW: 2002 CST:

UNDERWAY $367,000
AFTER 2002

STATE TRANSPORTATION IMPROVEMENTPROGRAM

NEWTON COUNTY

PROJECT: 231690- - TYPE WORK: . RECSTIREHAB

FUND: STP

LENGTH (miles / km) 3.3 /5.31

DESCRPT: SR 36 @ 3 LOCATIONS BETWEEN BUTTS COUNTY LINE AND CR 188

EXIST. LANES: 02 PROPOSED LANES; 03

PE: 1999 ROW: 2001 CST:

9/16199 Page 206 of275
UNDERWAY $28,000
AITER2oo2

PROJECT: 232330- \ TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.8 /1.29
DESCRPT: SR 36 AT FLAT SHOALS/STEELE RD/CR 181 & HENDERSON MILLICRS06 LUMPSUM PROJECT

PROJECT: 242230- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1.21 /1.95

DESCRPT: SR 142 FM 1-20 TO ALCOVYRD,IN COVINGTON

EXIST. LANES: 02 PROPOSED LANES; 04

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:
. PE:1997 ROW: 2000 CST:

UNDERWAY
$341,QOO $306,900
$34,100
UNDERWAY $31,000
AFTER 2002

PROJECT: 245190- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 0.56/0.90

DESCRPT: SR 212 @ CR 19 IN OAK HILL- INTERSECTION IMPROVEMENTS

PE:2000 ROW: 2002 CST:

$15,000 $304,000 AFTER 2002

PROJECT: 271012- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2 /0.32

DESCRPJ": CR 90lHIGHTOWER TRAIL RD @ GUM CREEK 6 MI N OF COVINGTON

EXIST. LANES: 01 PROPOSED LANES: 02

PE: 1997 ROW: LOCL . CST:2001 FED Share: GAShare:

UNDERWAY
$346,000 $276,800
$69,200

..

PROJECT: 271304- TYPE WORK: ENHANCEMENT

FUND: STP

. LENGTH (miles / km) 0/0.00

. PE:LOCL ROW: LOCL

DESCRPT: STREETSCAPES IN THE CITY OF COVINGTON-PHASE I

CST: 2000

.. $959,000

FED Share:

$767,200

END OFNEWTON COUNTY

OTHShare:

$191,800

/

E
I:,'~ I. I I I I I
Jf:
ilk
I I I I I I
I
~
... ~
~:'1: :;: ;.'
t& . ~ -""
~~
tt U
L~
l:j

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 207 of275

OCONEE COUNTY

PROJECT: 0000169 TYPE WORK: ENHANCEMENT

FUND: STP

ATHENS TIP #

LENGTH (miles I km) 0 10.00

DESCRPT: US 441/SR 53 INTERCHANGE LANDSCAPING

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$75,000 $60,000

PROJECT: 141980- TYPE WORK: RECSTIREHAB

FUND: STP

ATHENS TIP # 11-08

LENGTH (miles I km) 3 14.83

DESCRPT: MARS HILL RD/CR 264-5 WIDENING FROM CR 263 TO SR 53IHOG MTN

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 142060-

OTHShore:
PE: 1996 ROW: 2000 CST: 2002 FED Share: GA Share:

$15,000
UNDERWAY $1,610,000 $4,681,000 $3,744,800 $936,200

PROJECT: 142060- TYPE WORK: RECSTIREHAB

i FUND: STP

ATHENS TIP # 11-05

LENGTH (miles I km) 1.8512.98

DESCRPT: SR 53 FM HOG MTN RD (CR 274) TO SR 15IUS 441 IN WATKINSVILLE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 141980-

PE:'1998 ROW: 2001 CST: 2002 FED Share: GA Share:

UNDERWAY $1,100,000 $3,500,000 $2,800,000
$700,000

PROJECT: 170543- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.2/0.32

DESCRPT: CR 121/HALE ROAD @ GREENBRIAR CREEK 4.5 MI SE OF FARMINGTON

PE:2000 ROW: LOCL CST: 2002 FED Share: GA Share:

. $20,000
$393,000 $314,400 $78,600

PROJECT: 171450- TYPE WORK: ENHANCEMENT

FUND: STP

ATHENSTIP#V-03

LENGTH (mileslkm) 0/0.00

DESCRPT: SR 316IEPPS BRIDGE ROAD AT ATHENS PERIMETER

PROJECT: 171460- TYPE WORK: ENHANCEMENT

FUND: STP

ATHENS TIP # V-02

LENGTH (miles I km) 2.5 14.03

DESCRPT: SIMONTON BRIDGE ROAD FM WATKINSVILLE TO'CLARKE COUNTY

ASSOCIATED PROJECTS: 141970-

PROJECT: 171574- TYPE WORK: ENHANCEMENT

FUND: STP

ATIffiNSTIP#V-D5

LENGTH (mileslkm) 4.917.89

DESCRPT: STREETSCAPES FOR BUTLER'S CROSSING IN WATKINSVILLE

PROJECT: 245130- TYPE WORK: REPLACE BRIDGE

FUND: STP

LENGTH (miles I km) 0.43 10.69

DESCRPT: SR 15 OVER ROSE CREEK 7.5 MILES SE OF FARMINGTON

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:
z
PE:LOCL ROW: LOCL CST: 2001 FED Share:
OTHShare: PE:LOCL
ROW: LOCL CST: 2000 FED Share:
OTHShare: PE: 1997
ROW: 2001 . CST:

$52,000 $41,600
$10,400
$394,000 $315,200
$78,800
$250,000 $200,000
$50,000 UNDERWAY
$50,000 AFTER 2002

END OF OCONEE COUNTY

STATE TRANSPORTATION IMPROVEMENTPROGRAM

OGLETHORPE COUNTY

PROJECT: 222460- TYPE WORK: RECST/REHAB

FUND: STP

LENGTH (miles / km) 9.23/14.86

DESCRPT: SR 10 FM 10.2-12.2113.7-16.2117.2-18.7IWILKES/.l-1.715.5-7.0

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1997 ROW: 2001 CST:

9/16/99 Page 208 of275
UNDERWAY $100,000
AFTER 2002

PROJECT: 232315- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.LENGTH (miles / km) 0.21 /0.34

DESCRPT: SR 77 @ GOOSEPOND CREEK 14.5 MI NE OF LEXINGTON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 242315- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE .

.LENGTH (miles / km) 0.37/0.60

DESCRPT: SR 22 @ BROOKS CREEK 25 MI S OF LEXINGTON .

PE: 1996 ROW: 2000 CST: 2000 FED Share: GAShare:

PROJECT: 245370- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23/0.37

DESCRPT: SR 22 @ LONG CREEK 3.5 MI S OF LEXINGTON

PE:2000 ROW: CST:

UNDERWAY $10,000
$660,000 $528,000 $132,000
$20,000 AFTER 2002 AFTER 2002

PROJECT: 245371- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23/0.37

DESCRPT: SR 22 @ BIG CLOUDS CREEK 3.8 MI E OF SMITHSONIA

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002



PROJECT: 245372-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR 22 @ SOUTH FORK BROAD RIVER 4 MI NEOF SMITHSONIA

PE:2000 ROW: CST:

$22,000 AFTER 2002 AFTER 2002

END OF OGLETHORPE COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199

r

PAULDING COUNty

Page 209 oj275

PROJECT: 632660- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE: 1997 ,UNDERWAY

r

LENGTH (miles I km) 0.4/0,64 DESCRPT: SR 120 OVER LANE CREEK 2.3 MI SW OF DALLAS

ROW: 2000 CST: 2000

$39,000 $413,000

FED Share:

$330,400

GAShare:

$82,600

l

i

PROJECT: 632776- TYPE WORK: IMPROVE INTERSECTION FUND: STP

PE: 1999

UNDERWAY

LENGTH (miles I km) 0.54/0.87

ROW: 2000

$170,000

DESCRPT: SR 92 AT CR 283IBROWNSVILLE ROAD

.1:,

LUMP SUM PROJECT

',.

CST: 2001 FED Share:
GA Share:

$403,000 $362,700
$40,300

:~lIHt',.

PROJECT: 64Y830- TYPE WORK: SAFETY

FUND: NHS

LENGTH (miles I km) 0.29/0.47

DESCRPT: SR61 FM CR341 TO SR 6IDALLAS BYP& RRBR{FOR31A$}/641830

PE: 1993 ROW: 2000 , CST:

UNDERWAY $100,000
AFTER 2002

PROJECT: 670366- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23/0.37

DESCRPT: CR 842/0LD HARRIS ROAD @ SOUTHERN RR (719808G) SE OF DALLAS

PE:iooo ROW: LOCL CST:

$27,000 AFTER 2002

PROJECT: 671203- TYPE WORK: SAFETY

FUND: STP

LENGTH (miles Ikm) 0.2/0.32

DESCRPT: SR 6 OVER THE SILVER COMET TRAIL NEW CULVERT

LUMPSUM PROJECT

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share: GAShare:

$92,900
$484,000 $435,600 ,
$48,400

PROJECT: DNR250- TYPE WORK: NEW CONSTRUCTION FUND: REC TRAILS

PE: NONE

.

LENGTH (miles I km) 0/0.00

ROW: NONE

.DESCRPT: DNR RECREATIONAL TRAILS PROG-SILVER COMET TRAIL PUMPKVINE CK

CST: 2000

$125,000

I"', .
.~

FED Share: OTHShare:

S100,000 $25,000

END OF PAULDING COUNTY

I

;'.:;'\
~: ",
t~.

------,_.._---------------STATE TRANSPORTATION IMPROVEMENTPROGRAM

91/6/99 Page 110 of175

PEACH COUNTY

l'ROJECT: 0000128 TYPE WORK: ENHANCEMENT

FUND:' STP

.

' LENGTH (miles I km) 0/0.00

DESCRPT: BYRON RAILROAD DEPOT MUSEUMIRAILROAD CABOOSE & CITY PARK

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$120,000 $96,000

PROJECT: 0000129 TYPE WORK: ENHANCEMENT

FUND: STP

. LENGTH (miles I km) 0/0.00

. DESCRPT: FORT VALLEY RAILROAD MUSEUM

PROJECT: 311540- TYPE WORK: RECSTIREHAB

FUND: 1M

WARNERROBINSTIP#WRI-1993(1)

LENGTH (mileslkm)

1/1.61

DESCRPT: 1-75 @ SR 96

EXIST. LANES: 02 PROPOSED LANES: 04

OTII Share: PE:LOCL,
ROW: LOCL CST: 2001 FED Share:
onl Share:
PE: 1993 ROW: 1999 CST: 2001 FED Share: GAShare:

$24,000
$211,000 $168,800
$42,200 UNDERWAY UNDERWAY $4,444,000 $3,999,600
$444,400

PROJECT: 311700- TYPE WORK: NEW CONSTRUCTION FUND: NHS

WARNER ROBINS TIP # WRI-1996(3)

LENGTH (mileslkm) 0.2/0.32

DESCRPT: 1-75 @PROPOSEDRICHARDRUSSELLPARKWAY

EXIST. LANES: 00 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 363760-

PE: 1995 ROW: 1999 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $3,900,000 $3,120,000
$780,000

PROJECT: 343250- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) 0.3 10.48

DESCRPT: CR 182/WHITE ROAD.-REALIGN TO PROVIDE INTERSECTION WISR 42

PE:2000 ROW: LOCL CST: 2002 FED Share: GA Share:

$31,000
$626,000 $500,800 $125,200

"

PROJECT: 363760- TYPE WORK: NEW CONSTRUCTION FUND: STATE

PE: 1995

UNDERWAY

WARNER ROBINS TIP # WRI-1996(2)

LENGTH (mileslkm) 5/8.05

ROW: LOCL

DESCRPT: RICHARD RUSSELL PKWY FM E OF 1-75 TO' CORDERRDIHOUSTON

CST: 2000

$11,843,000

EXIST. LANES: 00 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 36376X- 311700-

GA Share:

$11,843,000

PROjECT: 363765- TYPE WORK: NEW CONSTRUCTION FUND: STATE

WARNER ROBINS TIP # 2000-2

LENGTH (miles I km) 0.8 1 1.29

DESCRPT: RICHARD RUSSELL PKWY FM LAKE VIEWICR 91 TO HOUSERS MILLlCR83

EXIST. LANES: 00 PROPOSED LANES: 02

-
PE:1995 ROW: LOCL CST: 2000
GAShare:

UNDERWAY $1,700,000 $1,700,000

PROJECT: 363790- TYPE WORK: NEW CONSTRUCTION FUND: STATE LENGTH (miles I km) 0.55/0.89
DESCRPT: SR894IUNIVERSITY BLVD FM SR 49 TO STATE COLLEGE DR-FT VALLEY EXIST. LANES: 00 PROPOSED LANES: 02

PE:NONE ROW: 1997 CST: 2001
GA Share:

UNDERWAY $791,000
$791,000

PROJECT: 363820- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 4.8717.84

DESCRPT: SR 49C/FT VALLEY BYP FM BEVERLY RD NE TO SR 49 - ADD 2 LANES

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: 2001 CST:

UNDERWAY $10,000
AFTER 2002

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99

Page 211 of275

I

PEACH COUNTY

PROJECT: 363910- TYPE WORK: RECSTIREHAB

FUND: NHS

PE:2001

$45,000

~.)1

LENGTH (miles / km) 1.2/1.93 DESCRPT: I-75 @ SR 49 RELOCATE FRONTAGE RDS CHAPMAN RD & INnUST BLVD

ROW: CST:

AFTER2002 AFTER 2002

I

END OF PEACH COUNTY

I

I

I

I

n~f:

I.

I

I

..

I

I

I

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99 Page 212 of275

PICKENS COUNTY

PROJECT: 0000142 TYPE WORK: ENHANCEMENT

' FUND: STP

LENGTH (miles / km) 0/0.00 DESCRPT: BURNT MOUNTAIN SCENIC PRESERVATION PROPERTY ACQUISITION

PE:LOCL ROW: 2000 CST: NONE

$938,000

PROJECT: 621590- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 2.36/3.80

DESCRPT: SR 53 - WB PASSING LNS EAST OF TATE MP 20.4-21.3 & 22.6-24,1

EXIST. LANES: 02 PROPOSED LANES: 03

PROJECT: 621595- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles/ km) 2.94/4.73

DESCRPT: SR 53 - EB PASSING LNS EAST OF TATE MP 24.3-25.4 & 26.5-28.4

EXIST. LANES: 02 PROPOSED LANES: 03

PE:2000 ' ROW: 2000 CST: 2000 FED Share: GAShare:
PE:2000 ROW: CST:

$44,000 $143,000 $1,633,000 $1,306,400 $326,600
$44,000 AFTER 2002 AFTER 2002

PROJECT: 621640- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles/km) 2.7/4.35

DESCRPT: SR 53 EB MP 7.25-8.41 WB MP 8.4-10.05

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1992 ROW: 1998 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $1,240,000
$992,000 $248,000

PROJECT: 622140- TYPE WORK: TURN LANES.

FUND: NHS

LENGTH (miles / km) 14.4/23.10

DESCRPT: SR515 TURN LANES FM 1-575 THRU GILMER TO TOTEHEROW RDIFANNIN

ASSOCIATED PROJECTS: 62214X-

PE:2000 ROW: NONE CST: 2000 FED Share: GAShare:

$325,000
$5,050,000 $4,040,000 $1,010,000

PROJECT: 642140- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 136 BRIDGE REPLACEMENT OVER TALKING ROCK CREEK N OF SR 53

PE: 1995 ROW: 2001 CST:

UNDERWAY $14,000
AFTER 2002

PROJECT: 671214- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles/km) 0/0.00

DESCRPT: STREETSCAPES & SIDEWALKS IN THE CITY OF JASPER

END OF PICKENS COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$750,000 $600,000
$150,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

PIERCE COUNTY

PROJECT: 522340- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 6.9/11.11

DESCRPT: SR 38IUS 84 FM CR 107/0FFERMAN TO S CITY LMTS SCREVENIWAYNE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 52234X-

PE: 1993 ROW: 2001 CST:

9/16199 Page 213 0/275
UNDERWAY $1,667,000 AFTER 2002

PROJECT: 533170- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26 /0.42

DESCRPT: SR 15 @ BIG SATILLA CREEK AT APPLING COUNTY LINE

ASSOCIATED PROJECTS: 53317X-

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

END OF PIERCE COUNTY

'I"
I

I, I I I I I

STATE TRANSPORTATION IMPROVEMENTPROGRAM

PIKE COUNTY

PROJECT: 333110- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I kin) 0.2 /0.32

DESCRPT: SR 18/SR 109 AND SR 74lNTERSECTION IMPROVEMENT

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

9/16/99 Page 214 0/275
$20,000 $547,000 $605,000 $484,000 $121,000

PROJECT: 333145- ,TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / kin) 0.24/0.39

DESCRPT: SR 18 @ ELKINS CREEK .1 MI W OF ZEBULON

PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare: .

$24,000 $10,000 $1,022,000 $817,600 $204,400

PROJECT: 343385- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE,

LENGTH (miles / km) 0.24 /0.39

DESCRPT: SR 109 @ ELKINS CREEK :5 MI E OF MOLENA

PE:2oo0 ROW: 2001 CST: 2002 FED Share: GAShare:

$20,000 $10,000 $553,000 $442,400 $1l0,600

END OFPIKE COUNTY

"
c. "

i'.I,

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199

Page 215 0[275

jJ1f

POLK COUNTY

PROJECT: 0000115 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles I km) 0/0.00 ,

ROW: LOCL

I

DESCRPT: DEPOTIHISTORIC DISTRICT OF CEDARTOWN

CST: 2000 FED Share:

$655,000 $524,000

I

PROJECT: 0000116 TYPE WORK: ENHANCEMENT

FUND: STP

OTR Share: PE:LOCL

$131,000

LENGTH (miles I km) 0 10.00

ROW: LOCL

I'

DESCRPT: ROCKMART STREETS CAPE PROJECT

CST: 2001 FED Share:

$310,000 $248,000

i

PROJECT: 620647- TYPE WORK: RECSTIREHAB

FUND: HPP

OTR Share: PE: 1992

$62,000 UNDERWAY

LENGTH (mileslkm) 4.6/7.41

ROW: 1997

UNDERWAY

DESCRPT: SR 6 FM CR 154 EASTERLY TO OLD CEDARTOWN RD/CR 193

f~.:

EXIST. LANES: 02 PROPOSED LANES: 04

CST: 2000 FED Share:
GAShare:

$6,342,000 $5,073,600 $1,268,400

I

PROJECT: 62132X-

TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 0 10.00

DESCRPT: SR 1 FM BUCHANAN BP TO S/SR 1OO...SEE HARALSON CO- 621320

PE:NONE ROW: NONE CST: NONE

ASSOCIATED PROJECTS: 621320-

I

PROJECT: 62143X-

TYPE WORK: RECSTIREHAB

. FUND: STP

. LENGTH(mileslkm) 0/0.00

DESCRPT: SR 113 FM TAYLORSVILLE CL TO CR 311STILESBORO..SEE BARTOW

PE:NONE ROW: NONE CST: NONE

I

ASSOCIATED PROJECTS: 621430-

PROJECT: 621475- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

PE: 1993

UNDERWAY

I

LENGTH (miles I km) 0.02/0.03 DESCRPT: SR llUS 27 BRIDGE OVER CEDAR CREEK TRIBUTARY SE CEDARTOWN

ROW: NONE CST: 2000

$133,000

1.'.-'
'i:

EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 621320-

FED Share: GA Share:

$106,400 $26,600

PROJECT: 621860- TYPE WORK: RECSTIREHAB

FUND: STATE

PE: 1995

UNDERWAY

Ii.

LENGTH (mileslkm) 5.7519.26 DESCRPT: CEDARTOWN BYPASS WIDENING FM SR 100 N TO JUST S. OF CR 334

EXIST. LANES: 02 PROPOSED LANES: 04

ROW: 2001 CST:

$845,000 AFTER 2002

ASSOCIATED PROJECTS: 62Y860"~.F(:.'
it PROJECT: 62Y86o- TYPE WORK: RECSTIREHAB

FUND: NHS

PE:2000

$1,000

LENGTH (mileslkm) 0/0.00

ROW: NONE

DESCRPT: CEDARTOWN BYPASS FM SR 100 N TO CR 334 - FOR FED PE; 621860 EXIST. LANES: 02 PROPOSEDLANES: 04

CST: NONE

ASSOCIATED PROJECTS: . 621860-

PROJECT: 631148- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles i km) 6.53 I 10.51

DESCRPT: CR 440/470/441 FM CR 168 THRU PAULDING TO CR 226/0LD ATL HWY

ASSOCIATED PROJECTS: 631 14Z-

PE: 1992 ROW: 2001 CST: 2002 FED Share: . GA Share:

UNDERWAY $129,000
$3,099,000 $2,479,200
$619,800

",,: .~
i..,j

" \ STAT""'FRWNSPORPAlPI(;)NIMPRO;J!EMENTPROGRAM

9/16/99 Page 216 of275

POLK COUNTY

PROJECT: 641880- TYPE WORK: TURNU\NES

FUND: NHS,"

LENGTH ("ules? km) 1.08/ I. 74 ,.DESCRPT: SR I.BUS FM THORNTON AVE TO CEDARTOWN ByPASS

PE:'1994i.

_ ....i ' .

ROW: 1999 . CST::2000 .,

FED Share:

~ 'I"
UNDERWAY UNDERWAY $1,271,000 $1,271,000

PROJECT: 670678- TYPE WORK: REPLACE BRIDGE

. FUNDi BRIDGE

LENGTH\(miles / km) 0.2/0.32

,'.' DESCRPT: CR 182/BETHLEHEM ROAD @FISH CREEK 5.7 MI W OF ROCKMARt

PE: 2000

$20,000

ROW: LOCL

. CST:

' '" AFTER 2002

PROJECT:DNR251- TYPE WORK: NEW CONSTRUCTION FUND: REC TRMLS

PE:NONE ."

"',;

;r

LENGTH'(miles/kin) 0/0.00

ROW: NONE

DESCRPT:DNR REC TRAILS PROG-SILVER OMET TRAIL VAN WERT TRAIL HEAD .

. 'CST:2oo0

FED Share:

$100,000 $80,000

END OF P.O' LK COUNTY

OTll Share:

$20,000

.( . .

;, 'v" I,

,. J!

..

'I".'.
Ii
..

STATE TRANSPORTATION IMPROVEMENT PROGRAM

PULASKI COUNTY

PROJECT: 333080- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 257 @ TEN MILE CREEK 3.5 Ml NW OF FINLEYSON

PE:2000 ROW: 2001 CST:

9/16/99 Page 217 of275
$20,000 $10,000 AFTER 2002

PROJECT: 343000- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26/0.42

DESCRPT: SR 230 @ BIG CREEK 5.6 MILES WEST OF HAWKINSVILLE

PE: 1995 ROW: 2001 CST:

UNDERWAY $50,000
AFTER 2002

END OF PULASKI COUNTY

;.

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 218 0/275

PUTNAM COUNTY

PROJECT: 22Y470- TYPE WORK: . RECST/REHAB

FUND: NHS

LENGTH (miles 1 km) 0/0.00

DESCRPT: SR 24/US 441 FM CR 245 TO EATONTON BYP - FOR FED PE; 222470

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222470-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 231610- TYPE WORK: RECST/REHAB

FUND: STP

. LENGTH (miles 1 km) 5.14 18.28

DESCRPT: SR 24IEATONTON BYPASS REMAINING TWO LANES NORTHBOUND

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1995 ROW: 2000 CST: .

UNDERWAY $50,000
AFTER 2002

PROJECT: 231620- TYPE WORK: RECST/REHAB

FUND: STP

LENGTH (mileslkm) 5.07/8.16

DESCRPT: SR 44 FOUR PASSING LANES NB & SB BETWEEN EATONTON & GRAY

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1998 ROW: 2001 CST:

UNDERWAY $30,000
AFTER 2002

PROJECT: 232295 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.22/0.35

DESCRPT: SR 16 @ ROOTY CREEK IN EAST EATONTON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 245350- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22 10.35

DESCRPT: SR 16 @ CROOKED CREEK 6 MI E OF EATONTON

PE:2000 ROW: 2002 CST:

. $20,000 $10,000
AFTER 2002

PROJECT: 271130- TYPE WORK: REPLACE BRIDGE

FUND: PFH

LENGTH (miles! km) 0.4 10.64

DESCRPT: MARTIN MILL RD/CR 29/FH 27 @ LITTLE RIVER

END OF PUTNAM COUNTY

PE: 1996 ROW: LOCL CST: 2001 FED Share:

UNDERWAY
$1,404,000 $1,404,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

QUITMAN COUNTY
PROJECT: 431520- TYPE WORK: IMPROVE INTERSECTION FUND: STP LENGTH (miles / km) 0.38/0.61
DESCRPT: SR 50lUS 82 REALIGNMENT IN THE CITY OF GEORGETOWN

PE: 1996 ROW: 1998 CST: 2000 FED Share: GAShare:

9/16199 Page 219 of275
UNDERWAY UNDERWAY $1,616,000 $1,454,400
$161,600

.PROJECT: 442725- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 39 @ SOAPSTONE CREEK 5 MI N OF GEORGETOWN

PE: 1996 ROW: 2000 CST: 2000 FED Share: GAShare:

UNDERWAY $2,000
$691,000 $552,800 $138,200

END OF QUITMAN COUNTY

; ..
..
.....

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 220 of275

RABUN COUNTY

.PROJECT: 121950- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 2.32/3.74 DESCRPT: SR 2 FM LAKE BURTON BRIDGE TO CHARLIE MTN RD/CR 94 & REALIGN

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1993 . ROW: 1996 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $1,529,000 $1,223,200
$305,800

PROJECT:' i22320- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 9.76/15.71

DESCRPT: SR 15IUS 441 FM N OF TALLULAH FALLS TO S CL OF CLAYTON

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: I2Y320-

PE: 1993 ROW: 2001 CST: .

UNDERWAY $20,013,000 AFTER 2002

PROJECT: 12Y09D- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0 10.00

DESCRPT: 'SR 15IUS441 FM NO. CUCLAYTON TO NC LINE-FOR FED PEl122090

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 122090-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 12Y320- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (mileslkm) 0/0.00

DESCRPT: SR 15IUS 441 FM TALLULAH F TO SCUCLAYTON- FOR FED PE/122320

EXIST-,LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 122320-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 133050- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles 1 km) 10.5 116.97

DESCRPT: SRI5 FM N OF CR 74IROCK MIN RD TO N OF CR 25/STEKOA FALLS RD

LUMPSUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$853,000 $682,400 $170,600

PROJECT: 171580- TYPE WORK: REPLACE BRIDGE

FUN/): BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: CR 80 AT TALLULAH RIVER 6.6 MI SW OF TIGER

PE:2000 ROW: LOCL CST:

$11,000 AFTER 2002

END OFRABUN COUNTY

STATE TRANSPORTATION IMPROVEMENT PROGRAM

RANDOLPH COUNTY

PROJECT: 422240-

TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 8.5/13.69

DESCRPT: SR llUS 27 FR CUTHBERT BYP TO CR 116ILUSCIOUS QUEEN ROAD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: CST:

9116/99 Page 2210/275
UNDERWAY AFTER 2002 AFTER 2002

PROJECT: 422245- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles"!km) 7.78/12.53

DESCRPT: SR llUS 27 FR CR 116 TO LUMPKIN BYPASS/& STEWART

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 42224X-

PROJECT: 42Y235- TYPE WORK: RECSTIREHAB, FUND: NHS LENGTH (miles Ikm) 010.00
DESCRPT: SR I FM CR 153 TO CUTHBERT BYPASS - FOR FED PE; 422235 EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 422235-

PROJECT: 431530- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.21/0.34

DESCRPT: ~R llUS 27 @ GEORGINALABAMA RR 2.2 MI S. OF CUTHBERT

PROJECT: 432095- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles1 km) 0.21 10.34

DESCRPT: SR 50lUS 82 @ PACIDTLA CREEK 4 MI E OF CUTHBERT

PE: 1996 ROW: CST:

UNDERWAY AFTER 2002 AFTER '2002

PE:2000 ROW: NONE CST: NONE

$1,000

PE: 1996 ROW: NONE CST: 2002 FED Share: GAShare:

UNDERWAY
$631,000 $504,800 $126,200

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 442955- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles1 km) 0.22 10.35

DESCRPT: SR 216 @CARTERCREEK4.6 MI S OF CUTHBERT

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 442956- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.23/0.37

DESCRPT: SR 266 @ SOUTHERN RAILROAD 2 MI W OF CUTHBERT

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

END OF RANDOLPH COUNTY

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199 Page 222 of275

RICHMOND COUNTY

PROJECT: 0000154 TYPE WORK: ENHANCEMENT

FUND: STP

AUGUSTA TMA TIP # TEA-6

LENGTH (miles / km) 0/0.00

DESCRPT: CONSTRUCT TWO PETERSBURG BOATS (ELEC) & DOCKING FACILITIES

. PROJECT: 0000155 TYPE WORK: ENHANCEMENT

FUND: STP

AUGUSTA TMA TIP # TEA-3 .

LENGTH (miles / km) 0 /0.00

DESCRPT: LAKE OLMSTEAD MULTI-USE FACILITY & LANDSCAPING

PE:LOCL .
ROW: LOCL CST: 2000 FED Share: GAShare:
.omsso
PE:LOtL ROW: LOCL CST: 2000 FED Share:

$719,000 $575,200 ($75,200) $219,000
$94,000 $75,200

PROJECT: 0000156 TYPE WORK: ENHANCEMENT

FUND: STP

AUGUSTATMA TIP#TEA-5

LENGTH (miles/km) 0/0.00

DESCRPT: CORRIDOR STUDY & GATEWAY LANDSCAPE PLANS

OTH Share: PE:2000
ROW: NONE CST: NONE

$18,800 $120,000

PROJECT: 0000157 TYPE WORK: ENHANCEMENT

FUND: STP

AUGUSTA TMA TIP # TEA-8

LENGTH(miles/km) 0/0.00

PE:LOCL ROW:LOCL .

DESCRPT: AUGUSTA STATE UNIVERSITY HISTORY WALK/SIDEWALKSILANDSCAPING

CST: 2000

FED Share:

GA Share: OTHShare:

PROJECT: 210450- TYPE WORK: RECST/REHAB

FUND: NH~

PE: 1993

AUGUSTA TMA TIP # NHS-2

LENGTH (miles / km) 0.76/1.22

ROW: 2000

DESCRPT: 1-20/1-520 INTERCHANGE RECONSTRUCTION

CST: 2002

FED Share:

GAShare:

$1,000,000 $800,000 ($100,000) $300,000
UNDERWAY $5,000,000
$25,000,000 $20,000,000
$5,000,000

PROJECT: 220680- TYPE WORK: RECST/REHAB

FUND: STP

AUGUSTA TMA TIP # STP-4

LENGTH (miles / kmJ 0.85/1.37

DESCRPT: SR 4/15TH STIAUGUSTA FM M.L.KING BLVD TO GOVERNMENT ST

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 1997 CST:ioOl FED Share: GAShare:

UNDERWAY UNDERWAY $3,263,000
$2,610,400 $652,600

PROJECT: 221180r .

TYPE WORK: RECST/REHAB

FUND: STP

LENGTH(miles/km) 6.16/9.92

DESCRPT: SR 56 FM SR 56 SPURIBURKE TO N OF BENNOCK MILLIPART NEWLOC

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECTS: 22118Z- 221185- .

PE: 1992 ROW: 1992 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY $11,510,000 $9,208,000 $2,302,000

PROJECT: 221185- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.04/0.06

DESCRPT: SR 56 @ MCBEAN CREEK/ALSO BURKE CO

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22118X- 221180-

PE: 1993 ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$1,966,000 $1,572,800
$393,200

PROJECT: 221550- TYPE WORK: RECST/REHAB

FUND: NHS

AUGUSTA TMA TIP # NHS-l

LENGTH (miles / km) 6.29/10.13

DESCRPT: SR 4IDEANS BR RD FM S FT GORDON GATE 5 TO MP 20.75

PE: 1993 ROW: 1999 CST: 2000 FED Share: GAShare:

UNDERWAY
UNDERWAY $1,589,000 .. $1,271,200 . $317,800

STATE TRANSPORTATION IMPROVEMENT PROGRAM

RICHMOND COUNTY

PROJECT: 222350- TYPE WORK: NEW CONSTRUCTION FUND: 1M

AUGUSTA TMA TIP # IM-l

LENGTH (miles 1 km) 1.6912.72

DESCRPT: I-520/SR 415 @ SR 56 ADD WB LOOP & ADD LANES ON SR 56

PE: 1993 ROW: 1998 CST: 2000 FED Share: GA Share:

91J6I99 Page 223 of275
UNDERWAY UNDERWAY $6,600,000
$5,940,000 $660,000

PROJECT: 222370- TYPE WORK: RECSTIREHAB

FUND: NHS

AUGUSTA TMA TIP # NHS-5

LENGTH (miles 1 km) 1.3612.19

DESCRPT: TOBACCO RD @ SR 4IUS 1 IN AUGUSTA

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 1998 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$6,850,000 $5,480,000 $1,370,000

PROJECT: 222720- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

AUGUSTA TMA TIP # BRM-2

LENGTH (mileslkm) 0.21/0.34

DESCRPT: SR 4IUS 1 NBL & SBL @ BUTLER CREEK 7 MI N OF HEPHZIBAH

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1997 ROW: 2001 CST: 2002 FED Share: GAShare:

UNDERWAY $2,000
$730,000 $584,000 $146,000

PROJECT: 227800- TYPE WORK: SAFETY

FUND: NHS

AUGUSTA TMA TIP # NHS-9

LENGTH (miles 1 km) 0/0.00

DESCRPT: ATMSI AUGUSTA SLO SCAN/CMSIRADAR

PE:NONE ROW: NONE CST: 2002 FED Share: GAShare:

$1,650,000 $1,320,000
$330,000

PROJECT: 227810- TYPE WORK: SAFETY

FUND: NHS

AUGUSTA TMA TIP # NHS-9

LENGTH (miles 1 km) 0 10.00

DESCRPT: ATMSI AUGUSTAlRICHMOND COUNTY/GDOT REGIONAL TCC

<,
ASSOCIATED PROJECTS: 22781X-

PE:NONE ROW: NONE CST: 2001 FED Share: GA Share:

$1,000,000 . $800,000
$200,000

PROJECT: 245320- TYPE WORK: RECSTIREHAB

FUND: STP

AUGUSTA TMA TIP # STP-17

LENGTH (mileslkm) 2.2/3.54

DESCRPT: WINDSOR SPRNGS RD/CR 65 FM SR 88IHEPHZIBAH TO WILLIS FOREMAN

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 245325-

PE:2000 ROW: LOCL CST:
GA Share:

$5,000 AFTER 2002
$0

PROJECT: 245325- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

AUGUSTA TMA TIP # BRM-l

LENGTH (miles 1 km) 0.21 10.34

DESCRPT: CR 65IWINDSOR SPRINGS RD @NOR-SOU RR (734145P)IHEPHZIBAH

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 245320- .

PE:2000 ROW: NONE CST:
GA Share:

$5,000 AFTER 2002
$0

PROJECT: 250325- TYPE WORK: NEW CONSTRUCTION FUND: STP

AUGUSTA TMA TIP # NHS-8

LENGTH (miles 1 km) 1 1 1.61

DESCRPT: NOISE BARRIERS JIMMIE DYESS PKY FM OLD BELAIR TO POWELL RD

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$1,000,000 $800,000 $200,000

j
~,

....

PROJECT: 250510- TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1997

UNDERWAY

AUGUSTA TMA TIP # STP-6

LENGTH (miles 1 km) 2.63 14.23

ROW: LOCL

DESCRPT: WRIGHTSBORO RD/eR 1501 FM BELAIR RD TO BARTON CHAPEL RD

CST: 2002

$5,565,000

EXIST. LANES: 02 PROPOSED LANES: 04

.FED Share:

$4,452,000

GA Share:

$1,113,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199 Page 2240/275 -

ili'CHMOFliTCOUNTY

PROJECT: 250570- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE -

AUGUSTA TMA TIP # BRM-3

LENGTH (miles / km) 0.2/0.32

DESCRPT: NORTH LEG ROAD OVER CSX RAILROAD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1996 ROW: LOCL CST: 2002 .
FED Share: GAShare:

UNDERWAY
$1,200,000 $960,000 $240,000

PROJECT: 250610- TYPE WORK: RECSTIREHAB

FUND: STP-

AUGUSTA TMA TIP # STP- I6

LENGTH (miles / km) 2.7 /4.35

DESCRPT: WINDSOR SPRINGS RD/CR65 FM WILLIS FORMAN RD TO TOBACCO RD

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 250615-

PE:2000 ROW: LOCL CST:
GAShare:

, $5,000 AFTER 2002
$0

PROJECT: -262750- TYPE WORK: NEW CONSTRUCTION FUND: DEMO

AUGUSTA TMA TIP # DEMO-3

LENGTH (miles / km) 2/3.22

DESCRPT: ST. SEBASTIAN/GREENE STREET EXT NEAR CSX RR AND i5TH ST &YIU

ASSOCIATED PROJECTS: 26Y75o-

PE: 1999 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$6,731,000 . $5,048,250
$1,682,750

PROJECT: 26U750- TYPE WORK: NEW CONSTRUCTION FUND: DEMO

AUGUSTA TMA TIP # DEMO-3

LENGTH (miles / km) 0/0.00

DESCRPT: ST. SEBASTIAN/GREENE STREET EXT FOR 568 $1 SEE 262750

PE:NONE
ROW: NONE
CST: 2001 FED Share:
GAShare:

- $2,044,000 $1,635,200 $408,800

PROJECT: 26Y75o- TYPE WORK: NEW CONSTRUCTION FUND: DEMO

AUGUSTA TMA TIP # DEMO-3

LENGTH (miles / km) 0/0.00

DESCRPT: ST. SEBASTIAN/GREENE STREET EXT FOR 368 $1 SEE 262750 -

ASSOCIATED PROJECTS: 262750-

PE:NONE ROW: NONE CST: 2001 FED Share: GAShare:

$6,996,000 $5,596,800 $1,399,200

PROJECT: 271296- TYPE WORK: ENHANCEMENT

FUND: STP

AUGUSTA TMA TIP # TEA-2

LENGTH (miles / km) 0/0.00

DESCRPT: CITY OF AUGUSTA CANAL REHAB & BIKEIPED

PROJECT: 290050- TYPE WORK: VEHICLE PURCHASE

FUND: STP

AUGUSTA TMA TIP # FLEX-3

LENGTH (miles / km) 0/0.00

DESCRPT: PURCHASE TWO BUSES

END OFRICHMOND COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare: PE:NONE
ROW: NONE CST: 2000 - FEDShare:
OTHShare:

$1,121,000 $896,800 $224,200
$400,000 $320,000
$80,000

.-

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

9/16/99 Page 225 of275

ROCKiJALE COUNTY

.._ -

PROJECT: 721582- TYPE WORK: NEW CONSTRUCTION FUND: NHS

PE: 1993

UNDERWAY

ATLANTA TMA TIP # RO 035B

LENGTH (miles / km) 0.83 /1.34

ROW: 1994

UNDERWAY,.

DESCRPT: SR 20/138 - RELOCATION OF OLD SALEM ROAD AWAY FROM 1-20

CST: 2000

$2,143,000

FED Share:

$1,714,400

GAShare:

$428,600

i

PROJECT: 752215- TYPE WORK: NEW CONSTRUCTION FUND: STP

PE:-2001

$5,000

ATLANTA TMA TIP # RO 020A

LENGTH (miles / km) 0.25 /0040

ROW: LOCL

I

DESCRPT: SIGMAN RD GRADE SEPARATION AT CSX RAILROAD NORTH OF 1-20

CST:

AFTER J002

I

PROJECT: 752340- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # RO 023

LENGTH (miles / km) 0.95 /1.53

PE: 1999 ROW: LOCL

UNDERWAY

DESCRPT: SMYRNA RD/CR 438 FM KLONDIKE RD TO IRIS DRIVE

I

EXIST. LANES: 02 PROPOSED LANES: 03

CST: 2001 FED Share:
GAShare:

$844,000 $675,200 $168,800

I

PROJECT: 752390- TYPE WORK: RECSTIREHAB

FUND: STP

ATLANTA TMA TIP # RO 017A

LENGTH (miles / km) 0.92 /1048

PE: 1996 ROW: LOCL

UNDERWAY

DESCRPT: KLONDIKE RD/CR 437 FM SMYRNA RD/CR 438 TO JOHNSON SPUR

CST: 2000

$2,398,000

I

FED Share: GAShare:

$1,918,400 $479,600

r

PROJECT: 752400- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

ATLANTA TMA TIP # RO 049,

LENGTH (miles / km) 0.4 /0.64

DESCRPT: HURST ROAD AT HONEY CREEK

PE: 1995 ROW: LOCL CST: 2002

UNDERWAY $703,000

FEDShare: ,

$562,400

I

GAShare: OTHShare:

($240,400) $381,000

PROJECT: 753060- TYPE WORK: IMPROVE INTERSECTION FUND: STP

I~

ATLANTA TMA TIP # RO 202F

LENGTH (miles / km) 0.2 /0.32

DESCRPT: SR 162 AT MCCALLAIFAIRVIEW RD

PE:2000 ROW: LOCL CST: 2001

,$5,000 $525,000

FED Share:

$420,000

OTHShare:

$105,000

PROJECT: 753065- TYPE WORK: TURN LANES

FUND: STP

PE:2000

$5,000

Ifft,'

ATLANTA TMA TIP # R0202E

LENGTH (miles/km) 0.2/0.32

DESCRPT: SR 212 AT OGLESBY BRIDGE ROAD/CR 1

ROW: LOCL CST: 2001

$400,000

FED Share:

$320,000

PROJECT: 753070- TYPE WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # RO 228

' LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 20 @ COWAN RD/CR 30

OTHShare:
PE:2000 ROW: LOCL CST: 2000 FED Share:

$80,000 $5,000
$450,000 $360,000

OTH Share:

$90,000

i-i

PROJECT: 753075- TYPE WORK: TURN LANES

FUND: STP

ATLANTA TMA TIP # RO 2020

LENGTH (miles / km) 0.2 /0.32

,,,,;
PE:2000
ROW: LOCL

$5,000 ,-

r '.'

DESCRPT: SR 20 @ OGLESBY BRIDGE RD/CR i

:'

CST:2001 FED Share:

$450,000 $360,000

OTHShare:

$90,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 226 of275

ROCKDALE CO"uNTY

PROJECT: 753150- TYPE WORK: IMPROVE INTERSECTION FUND: STP

ATLANTA TMA TIP # RO 202G DESCRPT: SR 162 AT ELLINGTON ROAD

LENGTH (miles 1 km) 0.2/0.32

PE:2000 - ROW:LOCL
CST: 2001 FED Share:

$5,000
. $450,000 $360,000

PROJECT: 770935- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # I~O AR 177D

LENGTH (miles 1 km) 2/3.22

DESCRPT: STANTON RD FM HONEY CREEK RD TO SR 138

OTH Share:
PE: 1995 ROW: NONE CST: 2001 FED Share:

$90,000 UNDERWAY
$119,000 $95,200

PROJECT: 770994- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # RO 056

LENGTH (miles 1 km) 6.5/10.47

DESCRPT: BIG HAYNES CREE~ AREA MULTI-USE TRAIL

OTH Share:
- PE:LOCL ROW: LOCL CST: 2000 FED Share:

$23,800
$888,000 $710,400

PROJECT: 771125- TYPE WORK: ENHANCEMENT

FUND: CMAQ

ATLANTA TMA TIP # RO AR 177E

LENGTH (mileslkm) 0/0.00

DESCRPT: EXPANDED SIDEWALKS ON OGLESBY BRIDGE ROAD

OTH Share:
PE:LOCL ROW: LOCL CSr:2001 FED Share:

$177,600
$330,000 $264,000

PROJECT: 771242- TYPE WORK: ENHANCEMENT

FUND: STP

ATLANTA TMA TIP # ROARBP008

LENGTH (mileslkm) 0/0.00

DESCRPT: GREENWAY TRAIL IN SOUTH ROCKDALE-PHASE 1

OTHShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$66,000
-$250,000 $200,000

END OFROCKDALE COUNTY

OTH Share:

$50,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

SCHLEY COUNTY

PROJECT: 322720- TYPE WORK: RECSTJREHAB

FUND: STATE

LENGTH (miles / km) 7.34/11.82

DESCRPT: SR 3IUS 19 FM SR 240 TO CR 248 NEAR SR so/rAYLOR -32272X

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 32272X- 32Y720-

PE: 1993 ROW: 2001 CST:

9/16199 Page 227 of275
UNDERWAY $1,603,000 . AFTER2002

PROJECT: 322730- TYPE WORK: RECSTJREHAB

FUND: STATE

LENGTH (miles / km) 10.3 / 16.62

DESCRPT: SR 3IUS 19 FROM SR 271 TO SR 240

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 32Y730-

PE: 1993 ROW: 2001 CST:

UNDERWAY $2,774,000 AFTER 2002

PROJECT: 32Y720- TYPE WORK: RECSTJREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

I..t.

DESCRPT: SR 3IUS 19 FM SR 240 TO CR 248rrAnOR - FOR FED PE; 322720
EXIST. LANES: 02 PROPOSED LANES: 04

H

ASSOCIATED PROJECTS: 322720-

I

PROJECT: 32Y73Q-

TYPE WORK: RECSTJREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

. DESCRPT: SR 3IUS 19 FROM SR 271.TO SR 240 - FOR FED PE; 322730

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 322730-

PE:2000 ROW: NONE CST: NONE

$1,000

PE:2000 ROW: NONE CST: NONE

. $1,000

PROJECT: 343345- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 153 @ LITTLE MUCKALEE CREEK 3.9 MI E OF JCT SR 45

PE:2000 ROW: 2002 . CST:.

$20,000 $10,000 AFTER 2002

I

END OFSCHLEY COUNTY
I~.

;;;.'r.o
l:. '

STATE TRANSPORTATION iMPROVEMENTPROGRAM

9116199 Page 228 of275

PE:LOCL ROW: LOCL , CST:2001 ~', . FED Share:

PROJECT: 221328- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE'

LENGTH (niiles I km) 0.03/0.05

DESCRPT: SR 21 W/SYL VANIA @ OGEECHEE CREEK

EXIST. LANES: 02 PROPOSED LANES: 04

.1 .

OTH Share:
PE: 1991 ROW: 1999 CST: 2000 FED Share: GA Share: ..

$500,000 $400,000
$100,000 UNDERWAY UNDERWAY $1,675,000 $1,340,000
$335,000

PROJECT: 221329- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles! km) 0.03 10.05

DESCRPT: SR 21 W/SYL VANIA @ HORSE CREEK'

EXIST. LANES: 02 PROPOSED LANES: 04

PE:NONE ROW: 1999 CST::ZOOO FED Share: GA Share:

UNDERWAY $1,196,000
$956,800 $239,200

PROJECT: 227830- TYPE' WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.24/0.39
DESCRPT: SR 73IUS 301 @ SOUTH FORK OGEECHEE CRK 6.8 MI S OF SYINANIA "

PE:2000 ROW: CST:

$20,000 AFfER2002 AFfER2002

PROJECT: 227831- TYPE WORK: REPLACE BRIDGE

FUND: BRioGE

LENGTH (miles I km) 0.24/0.39

DESCRPT: SR 73IUS 301 @ OGEECHEE CREEK 2.8 MI S OF SYLVANIA

PE:2000
ROW: CST: .....

$20,000 AFfER2002 AFfER2002

PROJECT: 262165- TYPE WORK: RECSTIREHAB

FUND: HPP

LENGTH (miles I km) 6.96/11.21

DESCRPT: SR 21/SAV RVR PKWY FM CR 174 TO MILLEN BYPASSIJENKINS COUNTY

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 26216X-

PE: 1992 ROW: 2000 CST: 2000 FED Share: GA Share:

PROJECT: 262167- TYPE WORK: RECSTIREHAB

. FUND: STATE

LENGTH(miles/km) 8.14/B.ll

DESCRPT: SR 2 liSAV RVR PKWY FM SR 73 LOOP TO CR 174

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1994 ROW: 2000 CST:

"UNDERWAY $903,000
$10,600,000 $8,480,000 $2,120,000
UNDERWAY $965,000
AFfER2002

PROJECT: 271300- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (mileslkm) 0/0.00

DESCRPT: LANDSCAPING ALONG SR 21 IN DOWNTOWN SYLVANIA

END OF SCREVEN COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$625,000 $500,000
$125,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page 229 of275

.~. J1

SEMINOLE COUNTY
PROJECT: 442935- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$20,000

LENGTH (miles / km) 0.22/0.35

ROW: 2002

$10,000

t..

DESCRPT: SR 285 @ FISH POND DRAIN APP .5 MI N OF JCT SR 39

) i '. l ..

CST:

AFTER 2002

fr'

ili

END OF SEMINOLE COUNTY

u......
::~. ~:~

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99 Page 230 of275

SpALDING COUNTY

PROJECT: 0000100 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: DOWNTOWN GRIFFIN STREETSCAPE

PE:LOCL ROW: LOCL eST: 2001 FED Share:

$625,000 $500,000

OTHShare:

PROJECT: 0000101 . TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: GRIFFIN URBAN STORMWATER MANAGEMENT & POLLUTION MITIGATION

CST: 2000

FED Share:

$125,000
$875,000 $700,000

PROJECT: 323060- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR ISS/JACKSON ROAD @ CABIN CREEK 2 MI E OF GRIFFIN

OTHShare:
PE:2000 ROW: 2001 CST: 2002 FED Share: GAShare:

$175,000
$20,000 $10,000 $423,000 $338,400 $84,600

PROJECT: 331520- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 4.5917.39

. DESCRPT: SR 155 NB MP 5.8-71 SB 8.5-9.71 NB 9.8-10.91 NB 11.8-12.9

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 331970-

PE: 1992 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $538,000
$3,393,000 $2,714,400
$678,600

PROJECT: 331970- TYPE WORK: RECSTIREHAB

" FUND: STP

LENGTH (miles / km) 0.34/0.55

DESCRPT: SR 155 @TEAMON ROAD/CR 514

ASSOCIATED PROJECTS: 331520-

PE: 1996 ROW: LOCL CST: 2001 FED Share: GAShare:

UNDERWAY
$306,000 $275,400
$30,600

.

PROJECT: 332050- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.5 /0.81

PE: 1994 ROW: 2000

UNDERWAY $68,000

DESCRPT: SR 92 OVER MANLEY CREEK@ MP 5.1 NEAR EDWARDS RD

CST: 2001

$767,000

FED Share:

$613,600

GAShare:

$153,400

PROJECT: 332520- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 8.27/13.31

DESCRPT: SR 16/ARTHUR BOLTON PKWY FM REHOBOTH RD TO 1-75 & 33252X

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 33252X-

PE: 1997 ROW: 2000 CST: 2002 FED Share: GAShare:

UNDERWAY $550,000
$16,870,000 $13,496,000
$3,374,000

PROJECT: 332890- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0.5/0.81

DESCRPT: SR 3IUS 19 TURN LANES AT SR 16 IN GRIFFIN

PE: 1998 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $13;000
$1,246,000 $996,800 $249,200

o

PROJECT: 333060- TYPE WORK: REHAB. BRIDGE

FUND: STP

LENGTH (miles"/ km}' 0.2/0.32

PE:2000 ROW: NONE

" $20,000

DESCRPT: SR 92IUS 19 BUS DRAINAGE IMPROVEMENTS JUST SOUTH OF SR 3

eST: 2001

$110,000

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

$88,000

GA Share:

$22,000

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 2310/275

SPALDING COUNTY

PROJECT: 333245- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles I km) 4.95/7.97

DESCRPT: SR 3IUS 19 FM SOUTH OF SR 7 TO NORTH OF SR 92 BRIDGE

LUMPSUM PROJECT .

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$851,000 $680,800 $170,200

PROJECT: 342621- TYPE WORK: SAFETY

FUND: NHS

LENGTH (miies I km) 1.52/2.45

DESCRPT: SR 3IUS 19/H.TALMADGE HWY FM N OF CS 804 NORTH TO N OF CR 18

EXIST. LANES: 04 PROPOSED LANES: 06

PE: 1993 ROW~2000 CST: 2000
FED Share:

UNDERWAY $200,000
$4,971,000 $4,971,000

PROJECT: 343240- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23/0.37

DESCRPT: SR 155 @ TOWALIGA RIVER 6.5 MI NE OF GRIFFIN

PE: 1999 ROW: 2001 CST: 2002 FED Share: GAShare:

UNDERWAY $50,000
. $644,000 $515,200 $128,800

n:

PROJECT: 343380-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.21/0.34

PE:2000 ROW:

$20,000 AFTER 2002

DESCRPT: SR 155 @ TROUBLESOME CREEK 6 MI NE OF GRIFFIN

CST:

AFTER 2002

PROJECT: 343381- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH(mileslkm) 0.23/0.37

DESCRPT: SR 155 @ TOWALIGA RIVER 6.5 MI NE OF GRIFFIN

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

I

PROJECT: 343460- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

$120,000

..,_~,.'

LENGTH (miles I kin) 0.33/0.53

ROW: LOCL

;i : n .

!>ESCRPT: CS 797/SIXTH STREET @SR 155-CS 792-NOR-SOU RR IN GRIFFIN

CST:

AFTER 2002

~~~.;'

OTHShare:

$415,700

PROJECT: 350710- TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1992

UNDERWAY

LENGTH (tidIesI km) 0.35/0.56

ROW: LOCL

DESCRPT: CS 877/W MCINTOSH RD/GRIFFIN FM OLD ATLANTA RD TO US 41/SR 3

CST: 2001

$304,000

EXIST. LANES: 02 PROPOSED LANES: 04

FED Share:

$243,200

GAShare:

$60,800

PROJECT: 351210- TYPE WORK: RECSTIREHAB

FUND: NHS

PE: 1998

UNDERWAY

LENGTH (miles I km) 0.5 10.81

ROW: NONE

DESCRPT: SR 3IUS 19 TURN LANES AT SR 362 IN GRIFFIN

CST: 2000

$338,000

FED Share:

$270,400

p.

GAShare:

$67,600

~.

i.f

PROJECT: 351220- TYPE WORK: IMPROVE INTERSECTION FUND: STP

PE: 1998

UNDERWAY

LENGTH(mileslkm) 0.37/0.60

ROW: LOCL

n
~ ;" Lj

DESCRPT: MACON RD/CR 511 AT EAST COLLEGE ST/CR 253 & FUTRAL RD/CR 56

CST: 2000 FED Share:

$119,000 $107,100

GAShare:

$11,900

STATE TRANSPORTATION IMPROVEMENTPROGRAM
SpALDING COUNTY END OF SpALDING COUNTY

9/16/99 Page 232 of275

,

-_.'_._------' _______ w__

,

STATE TRANSPORTATION IMPROVEMENTPROGRAM

,
9/16/99 Page 233 of275

:,:,.1. "".,,'':'

STEPHENS COUNTY

PROJECT: 0000143 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

'ff
'I

LENGTH (miles / km) 0/0,00 DESCRPT: DOWNTOWN TOCCOA STREETSCAPE PROJECT PHASE III

ROW: LOCL CST: 2001 FED Share:

$313,000 $250,400

I

PROJECT: 122110-

TY~E WORK: RECSTIREHAB

FUND: STATE

orH Share: PE: 1993

$62,600 UNDERWAY

LENGTH (miles / km) 4.417,08

ROW: 2000

$2,588,000

I

DESCRPT: SR 17 FM S, CITY LIMITS MARTIN TO NW OF CR 13IRUMSEY ROAD EXIST. LANES: 02 PROPOSED LANES: 04

CST: 2002

$9,000,000

GAShare:

$9,000,000

w'
[

PROJECT: 122260- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 4.9617.99

I~

DESCRPT: SR 17 FROM NW OF CR l3IRUMSEY ROAD TO MEMORIAL DRIVE EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 121360- 12Y260-

PE: 1993 ROW: 2001 CST:

UNDERWAY $8,437,000 AFTER 2002

~

PROJECT: 12Y260-

TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0 /0.00

DESCRPT: SR 17 FROM NW OF CR 13 TO MEMORIAL DR - FOR FED PEl 122260

~'

EXIST. LANES: 02 PROPOSED LANES: 04

it

ASSOCIATED PROJECTS: 122260-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 132440- TYPE WORK: NEW CONSTRUCTION, FUND: STP LENGTH (miles/km) 5.7/9.18
DESCRPT: SR 365ffOCCOA BYP EXT @ SR 17 NE ON NEW LOC TO SR 365@CR 311 EXIST. LANES: 00 PROPOSED LANES: 04

PE: 1996 ROW: 2001 CST:

UNDERWAY $3,259,000 AFTER 2002

PROJECT: 150330- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (miles / km) 0.65 /1.05
DESCRPT: TUGALO RD/OLD SR 106 RELOCATION AT THE TOCCOA AIRPORT

PROJECT: 171556- TYPE WORK: ENHANCEMENT

FUND:STP

LENGTH (miles / km) 0 /0.00

DESCRPT: CITY OF TOCCOA STREETSCAPE PHASE II & DEPOT RENOVATION

END OFSTEPHENS COUNTY

PE: 1997 ROW: LOCL CST: 2000 FED Share: GAShare:
PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

UNDERWAY $1,000,000
$800,000 $200,000
$313,000 $250,400
$62,600

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 234 of275

STEWART COUNTY

PROJECT: 0000084 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: RICHLAND BROAD STREET STREETSCAPE

PE:LOCL ROW: LOCL CST: 2000 FED Share:

. $413,000 $330,400.

PROJECT: 322160- TYPE WORK: RECSTfREHAB

FUND: STATE

LENGTH (miles / km) 8.75 /14.09

DESCRPT: SR 1 FM CR 43 NILUMPKIN TO US 280/CUSSETAICHATTAHOOCHEE CO

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 32216X- 321580-

OTR Share: PE: 1993
ROW: 1995 CST: 2002
GAShare:

$82,600 uNDERWAY UNDERWAY $20,500,000
$20,500,000

PROJECT: 333160- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 27 @ BLADEN CREEK 11 MI SW OF LUMPKIN

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 343415- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE'

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 39 @ TALIPAHOGA CREEK APP z MI S OF OMAHA .

PE:2000 ROW: .
CST:

$20,000 AFTER 2002 AFTER 2002

END OFSTEWART COUNTY



STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199 Page 235 0[275

SUMTER COUNTY

PROJECT: 0000085 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: GA SW STATE UNIV WALKWAYS & BIKE TRAILS

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$855,000 $684,000

PROJECT: 322190- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 5.6/9.02

DESCRPT: SR 3IUS 19 FM CR 42 TO 0.3 MI NIUS 280 (INCL NEW RR BR)

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 322193- 32YI90

OTHShare:
PE: 1993 ROW: 2002 CST:

$171,000
UNDERWAY . $2,006,000
AFTER 2002

PROJECT: 322195- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles/km) 5.5 /8.86

DESCRPT: SR 3IUS 19 FM LEE CO LINE TO CR 421~UMTER (INCL BRIDGES)

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 32Y 195-

PE: 1993 ROW: 2002 CST:

UNDERWAY $1,133,000 AFTER 2002

PROJECT: 322310- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.01 /0.02

DESCRPT: SR 3IUS 19 @BEAR BRANCH S/SR 27

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 2000 CST: 2000 FED Share: GAShare:

UNDERWAY $50,000
$216,000 $172,800
$43,200

PROJECT: 322420- TYPE WORK: RECSTIREHAB

FUND: HPP

LENGTH (miles / km) 6.34 /10.21

DESCRPT: SR 3IUS 19 FM ANGELICACKlSUMTER TO SR 2711SCHLEY/32Y420lX

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 32242X- 32Y420-

PE: 1993 ROW: 2000 CST:

UNDERWAY $4,093,000 AFTER 2002

PROJECT: 322780- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 7.85 /12.64

DESCRPT: SR 27IUS 280 FROM SR 45 IN PLAINS TO SR 49 SW OF AMERICUS

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: 2001 CST:

$231,000 $2,517,000 AFTER 2002

PROJECT: 32Y190- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 3IUS 19 FM CR 42 TO NIUS 280 - FOR FED PE; 322190

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 322190-

. PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 32Y195- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

} ~.

. i -.
~.

DESCRPT: SR 3IUS 19 FM LEE CO TO CR 421SUMTER - FOR FED PE; 322195

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 322195-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 331540- TYPE WORK: NEW CONSTRUCTION FUND: STATE

PE: 1992

UNDERWAY

LENGTH (miles.! km) 3.33/5.36

ROW: LOCL

DESCRPT: AMERICUS NORTH BYPASS FM SR3IUS 19 TO CR297

...... :

EXIST. LANES: 00 PROPOSED LANES: 02

"

ASSOCIATED PROJECfS: 322420-

CST: 2000 GA Share: .

$4,223,000 $4,223,000

I
.! ~j

STATE TRANSPORTATION IMPROVEMENTPROGRAM

SUMTER CdUNTY

PROJECT: 333085- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 49 @ SWEETWATER CREEK 1 MI S OF ANDERSONvII.IE

PE:'2000 ROW: 2002 CST:

9116199 Page 236 of275
$20,000 $10,000 AFTER 2002

PROJECT: 333i95- TYPE WORK: REPLACE BRIDGE

'FUND: BRIDGE

LENGTH (miles 1km) 0.22/0.35

DESCRPT: SR 27 @ LIME CREEK 6.7 MI E OF JCT SR 30

, PE:2000 ROW: CST: '

$20,000 AFTER 2002 AFfER2002

PROJECT: 333196- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.24/0.39

DESCRPT: SR 30 @MUCKALEE CREEK 1.1 MI W OF JCT SR 3

PE:2000 ROW: CST: '

$20,000 AFfER2002 'AFTER2002

PROJECT: 343230- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 1.01/1.63

DESCRPT: SR 308IBONDS TRAIL RD REALIGNMENT FROM CR 32 TO CR 140

PE:1999 ROW: 2002 CST:

'UNDERWAY $110,000
AFfER2002

PROJECT: 343410- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.22/0.35

DESCRPT: SR 195 @ LIME CREEK 5 MI N OF JCT SR 30

PE:2000 ROW: CST:

$20,000 AFfER2002 AFfER2002

PROJECT: 350750 TYPE WORK: REPLACE BRIDGE ,

FUND: BRIDGE

LENGTH (miles 1 km) 0.38/0.61

DESCRPT: SR 377/AMERICUS @ GEORGIA SOUTHWESTERNRR

PROJECT: 371764-" TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH'(mileslkm) ,0/0.00

DESCRPT: SCENIC GATEWA YS AND LANDSCAPING IN AMERICUS

END OFSUMTER COUNTY

PE: 1989 ROW: 2000 CST: 2001 FED Share: GA Share:

UNDERWAY $125,000 $619,000 $495,200 $123,800

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$1,250,000 $1,000,000
$250,000

STATE TRANSPORTATioN IMPROVEMENTPROGRAM

TALBOT COUNTY

PROJECT: 322020- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 5.51 /8.87

DESCRPT: SR 96 FM E CLIJUNCTION CITY TO CR 48 WIBUTLER IN TAYLOR CO

EXIST. LANES: 02 PROPOSED LANES: 04

. ASSOCIATEDPROJECTS: 32202X-

PE: 1992 ROW: 1997 CST: 2000
GA Share:

9/16199 Page 237 of275
UNDERWAY UNDERWAY $10,380,000
$10,380,000

PROJECT: 323055- TYPE WORK: REPLACE BRIDGE

.FUND: BRIDGE

,

LENGTH (miles / km) 0.23/0.37

DESCRPT: SR 90 @ CEN OF GA RAILROAD @ WEST EDGE JUNCTIONCITY

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:

$20,000 $10,000 $818,000 $654,400 $163,600

PROJECT: 332900- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles/km) 8.95/14.41

DESCRPT: PASSINGLANES- 2 SITES IN UPSON & 4 IN TALBOT/33290X .

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 33290X-

PE: 1999 ROW: 2001 CST:

UNDERWAY $243,000
AFTER 2002

PROJECT: 333210- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26/0.42

DESCRPT: SR 36 @ FLINT RIVER 9.6 MI E OF WOODLAND

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 343110- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.3 /0.48

DESCRPT: CR 1721POBIDDY ROAD @ FLINT RIVER N OF JCT SR 22IUPSON

ASSOCIATED PROJECTS: 34311X-

PROJECT: 343405- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

'DESCRPT: SR 240 @ BLACKCREEK 2.6 MI S OF GENEVA

PROJECT: 37128Q.. TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: CR 17/GORMAN ROAD @ CSX RAILROAD~ CITY LMT OF TALBOTTON

PROJECT: 371281- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

. LENGTH (miles / km) 0.2/0.32

.DESCRPT: CR 178IPLEASANT VALLEY RD @ CELEOTHCREEKN OF WOODLAND

END OF TALBOT COUNTY'

PE: 1997 ROW: LOCL CST: 2002 FED Share: GA Share:

UNDERWAY
$140,000 $112,000 $28,000

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:

$20,000 $10,000 $474,000 $379,200 $94,800

PE: 1994. ROW: LOCL CST: 2002 FED Share: GA Share:

UNDERWAY
$372,000 $297,600 $74,400

PE:2000 ROW: LOCL CST: 2002 FED Share: GA Share:

$21,000
. $421,000 $336,800 $84,200

STA TETRANSPORTATION IMPROVEMENT PROGRAM

TALIAFERRO COUNTY

PROJECT: 245375-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.23/0.37

DESCRPT: SR 22 @ SOUTH FORK OGEECHEE RIV: 2.6 MI S OF CRAWFORDVILLE

PE:2000 ROW: CST:

9116/99 Page 238 of275
$20,000 AFTER 2002 AFTER 2002

PROJECT: 245376- TYPE WORK: REPLAcE BRIDGE

FUND: BRIDGE

.

LENGTH (miles 1 km) . 0.23/0.37

DESCRPT: SR 22 @NORTHFORKOGEECHEERIV. 2.4 MI S OF CRAWFORDVILLE

PE:20oo ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 245377- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (mileslkm). ,0.24/0.39

DESCRPT: SR 47 @ HARDEN CREEK 8 MI NE OF CRAWFORDVILLE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 245378- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE'

LENGTH (miles 1 km) 0.21/0.34

DESCRPT: SR 47 @ HARDEN CREEK TRIB 8.2 MI NE OF CRAWFORDVILLE

PE:2000 ROW: . CST:

$20,000 AFTER 2002 AFTER 2002

END OF TALIAFERRO COUNTY .'

"

STATE TRANSPORTATION IMPROVEM4NT PROGRAM

9/16199

'{

TATTNALL COUNTY

Page 239 of275

PROJECT: 532640- TYPE WORK: TURN LANES

FUND: STP

PE: 1997

UNDERWAY

J..' i.
:';

LENGTH (miles / km) 0.68/1.09 DESCRPT: SR 30lUS 280 FM SR 56 TO ENTRANCE OF GORDONlA STATE PARK EXIST. LANES: 02 PROPOSED LANES: 03

ROW: 2000 CST: 2001 FED Share:

S75,000 ~ $897,000 S7 I7,600

GAShare:

$179,400

'i.fi

PROJECT: 533120- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

PE:2000

SIO,OOO

LENGTH (miles / km) 0.2/0.32

ROW: 2002

S50,000

I

DESCRPT: SR 144 AT WATERMELON CREEK 3 MI W OF GLENNVILLE

CST:

AFTER 2002

PROJECT: 533180- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.26/0.42

DESCRPT: SR 144 @ BEARD'S CREEK 2 MI E OF GLENNVILLE

PE:2000 ROW: CST:

$33,000 'AFTER 2002 AFTER 2002

PROJECT: 571180- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.5/0.81

DESCRPT: MIDWAY RD/CR 79 @ CEDAR CREEK 2 MI NORTH OF COLLINS

END OF TATTNALL COUNTY

PE: 1996 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$582,000 $465,600 S116,400

!

.... M a
STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99 Page 240 of275

TAYLOR COUNTY

PROJECT: 0000086 TYPE WORK: ENHANCEMENT

FUND: STP

.LENGTH (miles 1 km) 0 10.00

DESCRPT: REYNOLDS DEPOT REHABILITATION

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$716,000 $572,800

PROJECT: 322710- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 8.79/14.15

DESCRPT: SR 3IUS 19 FM CR 248 NEAR SR 90 TO BUTLER BYPASS

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 32Y710-

OTH Share:
. PE: 1993 ROW: 2002 CST:'

$143,200
UNDERWAY $4,761,000 AFfER2002

PROJECT: 32Y710- . TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH(mileslkm) 0/0.00

DESCRPT: SR 3IUS 19 FM CR 248 TO BUTLER BYPASS -FOR FED PE; 322710

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 322710-

PE:z'OOO ROW: NONE CST: NONE

$1,000

, PROJECT: 333205- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 kin) 0.34/0.55

. DESCRPT: SR 128 @ FLINT RIVER 8 MI N OF REYNOLDS

PE:2000 ROW: . CST:

. $43,000 AFTER 2002 v':.. ' AFfER2002

PROJECT: 343365- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23/0.37

DESCRPT: SR 137 @ CEDAR CREEK 13.3 MI SW OF BUTLER

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER200i

PROJECT: 343366- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 137 @ WHITEWATER CREEK TRIB. 7 MI SW OF BUTLER

PE:2000 ROW: CST:

$20,000 AFfER2002 AFTER 2002

PROJECT: 343367- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 137@WHITEWATERCREEK5MISWOFBUTLER

PE:2000 ROW: CST:

$20,000 . AFTER 2002 AFTER 2002

PROJECT: 363140- TYPE WORK: RECSTIREHAB

. FUND: STATE

LENGTH (miles / km) 6.4 / 10.30

DESCRPT: SR 96/FALL LINE FWY FM BUTLER BYP TO W OF CRAWFORD CO LINE

EXIST. LANES: 02 PROPOSED LANES: 04

END OF TAYLOR COUNTY

PE: 1992 ROW: CST:

UNDERWAY AFTER 20.02 AFTER2002 ',

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199 Page 241 of275

TELFAIR COUNTY

PROJECT: 0000130 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles 1 km) 0 10.00

DESCRPT: JACKSONVILLE PEDESTRIAN FACILITIES

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$104,000 $83,200

PROJECT: 521570 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.15/0.24

DESCRPT: SR 31IUS 441 @ ALLiGATORj BIG HORSE OFLOWI BIG HORSE CKS

EXIST. LANES: 02 PROPOSED LANES: 04

OTH Share:
PE: 1988 ROW: 1993 CST: 2000 FED Share: . GAShare:

$20,800
UNDERWAY UNDERWAY
$2,176,000 $1,740,800
$435,200

PROJECT: 522530- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 7.21/11.61

DESCRPT: SR 31IUS 441 FR CR 240 TO S. MCRAE BYPASS

ExiST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 52Y530-

PE: 1993 ROW: 2001 CST:

UNDERWAY $3,155,000 AFTER 2002

PROJECT: 52Y530- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 0/0.00

DESCRPT: SR 31IUS 441 FR CR 240 TO S. MCRAE BYPASS -FOR FED PE;522530

:IT'

EXIST. LANES: 02 PROPOSED LANES: 04

t

ASSOCIATED PROJECTS: 522530-

PROJECT: 52Y540- TYPE WORK: RECSTIREHAB

FUND: NHS

ttr,',"

LENGTH (mileslkm) o {.O.OO

DESCRPT: SR 31IUS 441 FM SR 107/COFFEE TO CR 240 FOR FED PE; 522540

I

EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 522540

PROJECT: 531105 TYPE WORK: NEW CONSTRUCTION FUND: NHS

[

LENGTH (miles 1 km) 1.412.25

DESCRPT: SR 728/S MCRAE BYP FM SR 30lUS 280 SE TO SR 31IUS 441.

EXIST. LANES: 00 PROPOSED LANES: 04

PE:2oo0 ROW: NONE CST: NONE

$1,000

PE:2000 ROW: NONE CST: NONE

$1,000

PE: 1993 ROW: 2001 eST:

UNDERWAY $180,000
AFTER 2002

PROJECT: 53YIOO- TYPE WORK: NEW CONSTRUCTION FUND: NHS LENGTH (mileslkm) 0/0.00
DESCRPT: S MCRAE BYP FM SR 31 TO SR 27 @N.MCRAE BYP-FOR FED PE;53 I I00 EXIST. LANES: 00 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 531100-

PE:2000 ROW: NONE eST: NONE

$1,000

PROJECT: 542045- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) . 0.22.(0.35

DESCRPT: SR 149 @ SUGARCREEK 5 MI SE OF MCRAE

PE: 1996 ROW: 2000 eST: 2000 FED Share: GAShare:

UNDERWAY $11,000
$803,000 $642,400 $160,600

PROJECT: 542050 TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.23/0.37

DESCRPT: SR 149 @ TURNPIKE CREEK 8 MI SE OF MCRAE

PE: 1996 ROW: 2000 CST: 2000 FED Share: GAShare:

UNDERWAY $11,000
$769,000 $615,200 $153,800

.f

STATE TRANSPORPJtTION11f1PR(}VEMElVT PROGRAM

TELFAIR COUNTY-

PROJECT: 542395- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2510.40

DESCRPT: SR 117 @ BIG HORSE CREEK 9.2 MI E OF JACKSONVILLE

PE:2000 ROW: CST:

9/16199 Page 242 of275
$27,000 AFTER 2002 AFTER 2002

PROJECT: 561470- TYPE WORK: NEWCONSTRUCTION FUND: STATE . LENGTH (miles 1 km) 2.8 14.51
1DESCRPT: N MCRAE BYP FM US 341/S BYP TO US 441/WHEELERlINCL SIGNALSIX . EXIST. LANES: 00 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 56147X- 56Y470-
;PROJECT: 56Y470- TYPE WORK: NEW CONSTRUCTION FUND: NHS LNGTH(mileslkm) 0/0.00
DESCRPT: N MCRAE BYP FM US 341 TO US 441fTELFAIR- FOR FEDPE; 561470 EXIST. LANES: 00 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 561470-
END OF TELFAIR COUNTY

PE: 1993
ROW: 2001 . CST: .

UNDERWAY $1,031,000 AFTER2002

OTHShare:
PE:2000 ROW: NONE CST: NONE

$13,000 $1,000

STATE TRANSPORTATION IMPROVEMENTPROGRAM

TERRELL COUNTY

PROJECT: 431410-

TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 9.24 / 14.88

DESCRPT: SR 49 FM SR 45rrERRELL TO SR 308/SUMTERj SEE SUMTER-43141X

ASSOCIATED PROJECTS: 43141X-

PE:2000 ROW: 2001 CST:

9/16199 Page 243 of275
$50,006 $11,000 AFTER 2002

PROJECT: 471438- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 6.94 /11.17

DESCRPT: SR 520IDA WSON HWY FM BALDWIN ST TO END OF MAIN ST IN DAWSON

PE:LOCL ROW: LOCL CST: 2000 FED Share:

END OF TERRELL COUNTY

OTll Share:

$180,ODO $144,000
$36,000

n.
:~w.-
~.
ti
I

STATE TRANSPORTATION IMPROVEMENT PROGRAM

THOMAS COUNTY

PROJECT: 421970-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileSI km) . I 11.61

DESCRPT: SR 38IUS 84 BUS @ATLANTIC-GULF RAILROAD NWffHOMASVILLE

PE: 1992 ROW: 2000 CST: 2000 FED Share: -: GAShare:

9116199 Page 244 of275
UNDERWAY $50,000
$4,126,000 $3,300,800
$825,200

PROJECT: 431150- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.510.81

DESCRPT: CR 299 @ BIG CREEK APPROX 3 MI E OF JCT SR III /MITCHELL CO

ASSOCIATED PROJECTS: 43115X-

PE:1997 ROW: LOCL CST: 2000 FED Share: GAShare:

, UNDERWAY
$491,000 $392,800
$98,200

PROJECT: 431152- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE,

LENGTH (miles I km) 0.2/0.32

DESCRPT: CR 299 @ LITTLE CREEK APPROX 3 MI E OF JCT SR III & MITCHELL

ASSOCIATED PROJECTS: 43115Z-

PE: 1997 ROW: LOCL CST: 2000 FEDShare: GAShare:

UNDERWAY
$347,000 $277,600
$69,400

PROJECT: 431670- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 3.77/6.07

DESCRPT: SR 35IWEST THOMASVILLE BYP FM SR 35BU N TO SR 38IUS 84

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 43Y670-

PE: 1995 ROW: 2001 CST:

UNDERWAY $100,000
AFTER 2002

PROJECT: 43Y670- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: SR 351W.THOMASVILLE BYP FM SR 35BU N TO SR 38 - FOR FED PE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 431670-

PE:2000 ROW: NONE CST: NONE

$1,000

. ~.

PROJECT: 442720- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.2 10.32

PE: 1996 ROW: 2000

UNDERWAY $2,000

DESCRPT: SR 188 @ HORSE CREEK APP 2 Ml W OF OCHLOCKNEE

CST: 2000

$596,000

FED Share:

$476,800

GAShare:

$119,200

PROJECT: 442800- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) 0.2/0.32

DESCRPT: SR 188 @ SR 3 & A&G CROSSING REALIGNMENT

PE:2000 ROW: 2001 CST:

$5,000 $2,000 AFTER 2002

. PROJECT: 442965- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.21/0.34

DESCRPT: SR 33 @ REEDY CREEK APP .8 MI S OF PAVO

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 471436- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0 10.00

DESCRPT: MULTI-USE FACILITIES IN DOWl'lTOWN THOMASVILLE

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$1,250,000 $1,000,000
$250,000

STATE TRANSPORTATION IMPIlOVEMENT PROGRAM
THOMAs COUNTY END OF THOMAS COUNTY

9/16199 Page 245 of275

,........~.;...
f '.
; ,:,.

-----

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199

Page 246 of275

TIFT COUNTY

PROJECT: 0000087 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: GEORGIA AGRIRAMA RAILROAD IN TIFTON

PE:LOCL ROW: LOCL
CST: 2001 .FED Share:

$313,000 $250,400

PROJECT: 0000088 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: TIFTON MULTI-PHASED PED SAFETY & DOWNTOWN BEAUTIFICATION

OTHShare:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$62,600
$518,000 $414,400

PROJECT: 0000089 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: TIFTON MULTI-PHASED BEAUTIFICATION @ 1-75 & HWY 41

OTH Share:
PE:LOCL ROW: LOCL CST: 2001 FED Share:

$103,600
$87,000 $69,600

PROJECT: 410240- TYPE WORK: RECSTIREHAB

. FUND: NHS

LENGTH (miles / km) 8.1/13.04

DESCRPT: (-75 FM N CITY LIMITS OF TIFTON TO TURNER COUNTY LINE

EXIST. LANES: 04 PROPOSED LANES: 08

OTHShare:
PE: 1986 ROW: 2000 CST: 2002 . FED Share: GA Share:

$17,400
UNDERWAY $10,000,000 $29,000,000 $23,200,000 $5,800,000

PROJECT: 422320- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0.76 /1.22
DESCRPT: SR 520lUS 82 FM MAGNOLIA DR EAST TO CENTRAL AVEffIFTON



PE: 1996 ROW: 2000 CST:

UNDERWAY $750,000
AFTER 2002

PROJECT: 431500- TYPE WORK: REHAB. BRIDGE

FUND: STP

LENGTH(miles/km) 0.15/0.24

DESCRPT: SR 7IUS 41/ SOUTH MAIN STREET OVERUTTLE RIVER TRIBUTARY

PE: 1997 ROW: 2001 CST:

UNDERWAY $1,000
AFTER 2002

PROJECT: 431700- . TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR 35IUS 319 OVER ALAPAHA RIVER @ TIFT-IRWIN COUNTY LINE

PROJECT: 432220- TYPE WORK: .MAINTENANCE

FUND: STP

LENGTH (miles/km) 17.4/28.01

DESCRPT: SR 35IUS 319 FM SR 520mFT TO SR 32/IRWIN

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 43222X-

PROJECT: 450560- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 1 /1.61

DESCRPT: VIRGINIA AVE/CS 746 IN TIFTON FM SR 520lUS 82 N TO 8TH ST

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1997 ROW: 2000 CST: 2001 FED Share: GA Share:

UNDERWAY . $5,000
$1,304,000 $1,043,200
$260,800

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

$1,074,000 $859,200 $214,800

PE:2oo2 ROW:LOCL CST:

$134,000 AFTER 2002

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16199'

~.

,1

TIFT COUNTY

PROJECT: 471380- TYPE'WORK: RECSTIREHAB

FUND: STP'

LENGTH (miles/km) 3.44/5.54

\I

DESCRPT: CR 407/0LD OCILLARD & 12TH STREET FM SR 125 NORTH TO CR 18

11

EXIST. LANES: 02 PROPOSED LANES: 04

Page 247 of275

PE:2000 ROW: LOCL CST:

$211,000 AFTER 2002 ~.-'.

~

II

END OF TIFT COUNTY

I

L:.
-~.
'~
~.
i;
h-.
...
i ..

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 248 of275

TOOMBS COUNTY

PROJECT: 0000077 TYPE WORK: ENHANCEMENT

FUND: 'STP

LENGTH (miles I km) 0/0.00

DESCRPT: VIDALIA DOWNTOWN STREETSCAPE PHASE 2 .

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$500,000 $400,000

PROJECT: 522320- TYPE WORK: NEW CONSTRUCTION FUND: STP LENGTH (mileslkm) 2.15/3.46
DESCRPT: SR 30 FM W OF SUNSET DR TO BROADFOOT ST & I-WAY PAIRIVIDALIA EXIST. LANES: 02 PROPOSED LANES: 04

OTB Share:
PE: 1992 ROW: 1998 CST: 2001 FED Share: GA Share:

$100,000
UNDERWAY UNDERWAY $3,981,0.00 $3,184,800
$796,200

PROJECT: 52Y130- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: SR 4IUS 1 FM LYONS CL TO SCUOAK PARKIEMANUEL- FOR FED PE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 522130-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 52Y180- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0 10.00

DESCRPT: SR 4IUS 1 FM SR 56 TO SR 29 - FOR FED PE; 522180

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 522180-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 52Y190- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0 10.00

DESCRPT: SR 4 FM SR 29 TO S CLILYONS - FOR FED PE; 522190

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECTS: 522190-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 52Y200 TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0/0.00

DESCRPT: SR 41LYONS FM S CTY LMTS TO N CTY LMTS- FOR FED PE; 522200

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 522200-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 52Y220- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 0 10.00

DESCRPT: SR 4IUS 1 FM PLANT HATCH RD TO SR 56/APPLING - FOR FED PE;

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 522220-

PE:2oo0 ROW: NONE CST: NONE

$1,000

PROJECT: 542415- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.24/0.39

DESCRPT: SR 56 @ ROCKY CREEK 13 MI SE OF LYONS

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 542416- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23/0.37

DESCRPT: SR 147 @ COBB CREEK 17 MI S OF LYONS

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

.STATE TRANSPORTA'i'ION"iMPROVEMENT PROGRAM .

9/16199 Page 249 of275

. TOOMBS COUNTY

PROJECT: 571416- TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

I

DESCRPT: MULTI-USE WALKWA YS IN VIDALIA & LANDSCAPING

CST: 2000 FED Share:

$625,000 $500,000

I

END OF TOOMBS COUNTY

OTHShare:

$125,000

I

-.


STATE TRANSPORTATION IMPROVEMENTPROGRAM

TOWNS COUNTY

PROJECT: 122230- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.5 10.81

DESCRPT: SR 2IUS 76 3 MILES SFlHlAWASSEE @ HlA WASSEE RIVER

PE: 1996 ROW: 2000 CST: 2000 FED Share: GAShare:

9116/99 Page 250 0/275
UNDERWAY $10,000
$596,000 $476,800 $119,200

PROJECT: 122420- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 2.1/3.38

DESCRPT: SR 515IUS 76 FM CR 207IPINECREST RD TO E. OF CR 115IFULLER C

EXIST. LANES: 03 PROPOSED LANES: 04

, PE: 1996 ROW: 1997 CST: 2000 FED Share: GAShare:

UNDERWAY UNDERWAY
$2,035,000 $1,628,000
$407,000

PROJECT: 132710- TYPE WORK: RECSTIREHAB

FUND: APD

LENGTH (miles 1 km) 1.2 1 1.93

DESCRPT: SR 515 FM SR 2 NORTH OF HlAWASSEE TO THE NORTH CAROLINA LINE

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1998 ROW: 2000 CST:

UNDERWAY $1,199,000 AFTER 2002

END OF TOWNS COUNTY

..



.-. '--_._-'----..,............-

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116/99

Page 251 of275

TREUTLENCOUNTY

PROJECT: 0000131

TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles Ikm)

0/0.00

DESCRPT: SOPERTON STREETSCAPE

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$106,000 $84,800

PROJECT: 21095X- TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles I km) 0/0.00

DESCRPT: 1-16@ 1 LOCILAURENSI3 TREUTLENI2 EMANUELI SEE 210950

OTII Share;
PE:NONE Rl1W:-NONE CST: NONE

$21,200

ASSOCIATED PROJECTS: 210950- .

PROJECT: 231700- TYPE WORK: RECSTIREHAB

FUND: STP

PE:2000

$30,000

LENGTH (miles I km) 2.2/3.54

ROW: NONE

DESCRPT: SR 29 NB MP 4.95-6.051 SB MP 7.0-8.1

r

EXIST. LANES: 02 PROPOSED LANES: 03

L

CST: 2002 FED Share:
GA Share:

$1,263,000 $1,010,400
$252,600

PROJECT: 245360- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE -', .

LENGTH (miles I km) 0.27/0.43

DESCRPT: SR 46 @ OCONEE RIVER OVERFLOW 7.6 MI SW OF SOPERTON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

END OF TREUTLEN COUNTY

.
;1
;. ;

-------~--------------------,-,_._._-----------

STATE TRANSPORTATION IMPROVEMENTPROGRAM

911619~1

Page 151 of175

TROUP COUNTY

PROJECT: 0000117 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I Jim) 0/0.00.. "

DESCRPT: LAGRANGE STREETSCAPE

; .' PE:LOCL
ROW: LOCL
CST: 2001
FED Share:

$1,125,000 $900,000

PROJECT: 0000118 TYPE WORK:, ENHANCEMENT.,

FUND: STP .

LENGTH.(miles I km) 0 10.00

DESCRPT: YOUNG'S MILL BRIDGE PEDIBIKE TRAIL & STREETSCAPING

OTH Share:
PE:LOCL ROW: LOCL CST: 2000 FED Share:

$225,000
. $191,000 $152,800

PROJECT: 310730- TYPE WORK: NEWCONSTRUCTION FUND: NHS LENGTH (miles I km). 0.85 /1.37
DESCRPT: 1-185 CONN @1-85 & 1-1851 INTERCHANGE CONSTRUCTION .'I
ASSOCIATED PROJECTS: 362910-

OTH Share:
PE: 1993 ROW:2000 CST: .

$38,200
UNDERWAY. <, $905,000
AFTER 2002

PROJECT: 321715- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles I km) 3.05/4.91

DESCRPT: SR 14IUS 29 FM CR 403IUPPER GLASS BRIDGE TO OLD VERNON RD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 , ROW:2001 .
CST:

UNDERWAY , $1,000,000
AFTER 2002

PROJECT: 321720- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE'

PE: 1991

UNDERWAY

LENGTH (miles I km) 0.3 /0.48

ROW: 2000

$200,000

DESCRPT: SR I @ UNNAMED TRIBUTARY TO WEST POINT LAKE

CST: 2000

$920,000

.,

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 362920-

FED Share: GAShare:

$736,000 $184,000

PROJECT: 322230- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 2.84 /4.57

DESCRPT: SR 14 NB & SB FM MP 3.87-5.371NB & SB MP 7.07-8.41

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2002 CST:

UNDERWAY $400,000
AFTER 2002

PROJECT: 322240- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / km) 0.8 11.29

DESCRPT: SR 109 FM 1-85 TO 1-1851NCL 1-85 RAMP

EXIST. LANES: 02 PROPOSED LANES: 05

PE: 1992 ROW: 2001 CST:

UNDERWAY $120,000
AFTER 2002

PROJECT: 322250- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles I km) 1.4212.29

DESCRPT: SR llUS 27/LAGRANGE FM AUBURN ST TO SR 219/MORGAN ST

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992 ROW: 2001 CST:

UNDERWAY $12,725,000 AFTER 2002

".

PROJECT: 343190- TYPE WORK:, REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.21/0.34

PE: 1997 ROW: LOCL

UNDERWAY

DESCRPT: CS 769/JEFFERSON STREET @ CSX RAILROAD IN WEST LAGRANGE

CST: 2002

$710,000

FED Share:

$568,000

GAShare:

$142,000

''" .... I.:f
I I :1 I
~r~..
it
m.R..
I
~f.r

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199 Page 253 of275

TROUP COUNTY

PROJECT: 343455- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.3 /0.48

DESCRPT: CS 1081/GREENVILLE STREET @ CSX RAILROAD IN EAST LAGRANGE

PE:2000 ROW: LOCL CST:

$77,000 AFTER 2002

PROJECT: 351170- TYPE WORK: TURN LANES

FUND: STP

LENGTH (miles / km) 0.63 /1.0 I

DESCRPT: SR 14IUS 29 LEFT TURN LANE FROM MEADOW WAY DR TO SR 14 SPUR

OTHShare:
PE: 1997 ROW: LOCL CST: 2001 FED Share: GAShare:

.,
$257,900 UNDERWAY
$800,000 $640,000 $160,000

PROJECT: 362920- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 7.9/12.72
sa DESCRPT: SR llUS 27 FM N.t;:AR CR 673 NORTH TO 54 INCL BRIDGE

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 321720-

PE: 1993 ROW: CST:

UNDERWAY AFTER 2002 AFTER 2002

PROJECT: 36Y91O- TYPE WORK: NEW CONSTRUCTION FUND: NHS LENGTH (miles / km) 0/0.00
DESCRPT: 1-185 CONN FM 1-185 @ 1-85 TO SR llUS 27 - FOR FED PE;362910 EXIST. LANES: 00 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 362910-

PE:2000 ROW: NONE CST: NONE

$1,000

PROJECT: 371390- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.51 /0.82

DESCRPT: CR 2821YOUNGS MILL RD FM CAMP DR OVER BEECH CK TO EXIST RDWY

PE: 1996 ROW: LOCL CST: 2000 FED Share: GA Share:

UNDERWAY
$911,000
. $728,800
$182,200

PROJECT: 811066- TYPE WORK: RECSTIREHAB

FUND: 1M

LENGTH (miles / km) 0/0.00

DESCRPT: UPGRADE 1-85 NB AND SB WEIGH STATIONS INCL SCALE REPLACEMENT

PE: 1995 . ROW: NONE CST: 2000 FED Share: GAShare:

UNDERWAY
$5,000,000 $4,500,000
$500,000

END OF TROUP COUNTY

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

911619~\
Page 254 of275

TURNER COUNTY

PROJECT: 410245- TYPE WORK: RECSTIREHAB

. . FUND: NHS

.

c LENGTH (miles 1 km) 11.1/17.87

DESCRPT: 1-75 FM TIFT COUNTY LINE TO SR 159

.PE: 1994 ROW: 2000 CST: 2001

UNDERWAY $3,000,000
$23,000,000

EXIST. LANES: 04 PROPOSED LANES: 08

FED Share:

$18,400,000

GAShare:

$4,600,000

PROJECT: 410250- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles 1 km) 10.7/17:24

DESCRPT: 1;.75 FM SR 159 NR ASHBURN TO SR 300/CRlSP

EXIST. LANES: 04 PROPOSED LANES: 08

ASSOCIATED PROJECTS: 41025X-

PE: 1986 ROW: 2000 .CST: 2001 FED Share: GAShare:

UNDERWA'I $1,500,000 $31,300,000 $25,040,000 $6,260,000

PROJECT: ,431570- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.21/0.34

DESCRPT: SR 112 @ LITTLE RIVER 3 MILES WEST OF SYCAMORE

,PE: 1995 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $2,000
$558,000 $446,400 $111,600

PROJECT: 431580- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: SR 112 @ ASHBURN BRANCH 1.6 MILES SW OF ASHBURN

PE: 1995 ROW: 2000 CST: 2001 'FED Share: GA Share:

UNDERWAY $2,000
$249,000 $199,200
$49,800

PROJECT: 431590- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.19/0.31

DESCRPT:' SR 112 @ DANIELS CREEK SOUTHWEST OF ASHBURN

PE: 1995 ROW: 2000 CST: 2001 FED Share: GAShare:

UNDERWAY $1,000
$275,000 $220,000
$55,000

PROJECT: 431600- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.2/0.32

DESCRPT: SR 112 @ BIG BRANCH 6. I MILE SOUTHWEST OF SYCAMORE

PE: 1995 ROW: 2000 CST: 2001 FED Share: GA Share:

UNDERWAY $2,000
$266,000 $212,800 $53,200

PROJECT: 442980- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.27/0.43

DESCRPT: SR 112 @ DEEP CREEK 4.6 MI E OF ASHBURN

PE:2000 ROW: CST:

$24,000 AFTER 2002 AFTER 2002

PROJECT: 442981- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.24/0.39

DESCRPT: SR 112 @ DOUBLE RUN CREEK 1 MI SW OF REBECCA
)

o

END OF TURNER COUNTY

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 255 0/275

TWIGGS COUNTY

PROJECT: 24502X- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE.

LENGTH (miles / km) 0/0.00

DESCRPT: SR 18 @ BIG SANDY CK FM MP 0.2 IN TWIGGS TO MP 11.60 WILKNSN

PE:NONE ROW: NONE CST: NONE

ASSOCIATED PROJECTS: 245020-

PROJECT: 322470- TYPE WORK: RECST/REHAB

FUND: STP

LENGTH (miles / km) 7.5 /12.08

DESCRPT: SR 96 FM SR 87 TO 1-16

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2002 ROW: CST:

$194,000 AFTER 2002 AFTER 4002

PROJECT: 342980- TYPE WORK:RECST/REHAB

FUND: STP

LENGTH (miles / km) 2.79 /4.49

DESCRPT: SR 18 WB MP 2.31 - 3.6 & EB MP 3.6 - 5.1 IN WILKINSON

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 34298X-

END OF TWIGGS COUNTY

PE:2000 ROW: 2001 CST: 2002 FED Share: GA Share:

$125,000 $64,000
$1,419,000 $1,135,200
$283,800

~~..Jr

k

"

J-


-------------------- --------v__-.._.-,... -----_.--

.STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199

Page 256 of275

UNION COUNTY

PROJECT: 122410- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles / /em) 0.95 /1.53

DESCRPT: SR l1IUS 19 FM CR 47 NORTH TO CR 3041 PART ON NEW LOCATION

EXIST. LANES: 02 PROPOSED LANES: 05

ASSOCIATED PROJECTS: 122200-

. PE:2000 ROW: CST:

$400,000 AFTER 2002 AFTER 2002

PROJECT: 132180- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (miles / km) 0.23 /0.37

DESCRPT: CR 341 @ NOITLEY RIVER SW OF BLAIRSVILLE

PE:2000 ROW: LOCL CST:

$40,000
AFTER~002

END OF UNION COUNTY

OTHShare:

$130,000

o


STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16199 Page 257 of275

UPSON COUNTY

PROJECT: 0000132 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: FLINT RIVER ACCESSIBOAT RAMP AND RESTROOMS

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$125,000 $100,000

PROJECT: 322920- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0.2/0.32

DESCRPT: SR 3IUS 19 AT CR 73/EAST AND WEST COUNTY ROAD IN THOMASTON

OTHShare:
PE:2001 ROW: 2002 CST:

$25,000
$10,000. $102,000 AFTER 2002

PROJECT: 371780- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0 /0.00

DESCRPT: MULTI-USE SIDEWALKS IN THOMASTON

END OF UPSON COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$275,000 $220,000
$55,000

~
;ll;
I.. .
.,
I I
~
I
.~

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 258 of275

.WALKER COUNTY

PROJECT: 0000144 TYPE WORK: ENHANCEMENT

FUND: STP

CHATTANOOGA TMA TIP #

LENGTH (miles 1km) 0/0.00

DESCRPT: ROSSVILLE-CHICKAMAUGA AVE STREETSCAPE

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$750,000 $600,000

OTH Share:

PROJECT: 621195- TYPE WORK: NEW CONSTRUCTION . FUND: OTHER

PE: NONE

CHATTANOOGA TMA TIP # NPS-97-4

LENGTH (mileslkm) 3.7716.07

ROW: NONE

DESCRPT: CHICKAMAUGA BYP NEW CST50 CONN;MCFARLANDCONN;RMP C&D; SR2

CST: 2000

EXIST. LANES: 00 PROPOSED LANES: 04

FED Share:

ASSOCIATED PROJECTS: 62119Z-

GA Share:

$150,000
$14,600,000 $11,680,000 . $2,920,000

PROJECT: 621650- TYPE WORK: RECSTIREHAB

FUND: STP

-, LENGTH (mileslkm) 3.7/5.96

DESCRPT: SR 136 EB MP 21.4-22.8- 25.7-26.6IWB 4.12-5.22- 26.6-28.0

EXIST. LANES: 02 PROPOSED LANES: 03

. PE: 1992 ROW: 2002 . CST:

UNDERWAY $450,000
AFTER 2002

PROJECT: 632930- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles 1 km) 10.1/16.23

DESCRPT: SR 136 FM SR 1 TO SR 136 CONNECTOR I GORDON CTY

LUMPSUM PROJECT

ASSOCIATED PROJECTS: 63293X-

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

PROJECT: 642250- TYPE WORK: RECSTIREHAB

FUND: NHS

CHATTANOOGA TMA TIP # NH-STP-98

LENGTH (mileslkm) 5.04/8.11

DESCRPT: SR 193 FM OLD SR 193 NORTH TO TENN STATE LINE & 64Y250 (STP)

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 64Y250-

PE:2001 ROW: NONE CST:

PROJECT: 642430- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles 1 km) 2.05 /3.30

DESCRPT: SR 337 FM OLD SR 337 TO SR 1

LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share: GA Share:

PROJECT: 671216- TYPE WORK: ENHANCEMENT

FUND: STP

PE: LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: CHATTANOOGA CREEK GREENWAY MULTI-USE TRAILS & BRIDGE REHAB

CST: 2000

FED Share:

END OF WALKER COUNTY

OTHShare:

. $288,000 $230,400 $57,600 $75,000
AFTER 2002
$26,000 $20,800
$5,200
$100,000 $80,000 $20,000



-.
STATE TRANSPORTATION IMPROVEMENT PROGRAM

9/16/99 Page 259 of275

WALTON COUNTY

PROJECT: 0000171 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

LENGTH (miles / km) 0/0.00

ROW: LOCL

DESCRPT: MONROE-BROAD ST/GA HWY 11 CORRIDOR STREETSCAPE IMPROVEMENTS

CST: 2000

FED Share:

$606,000 $484,800

PROJECT: 132620- TYPE WORK: TURN LANES

FUND: STP

LENGTH (miles / km) 0.2 /0.32

DESCRPT: SR 20 AT SR 81 IN LOGANVILLE

OTII Share:
PE: 1995 ROW: 1998 CST: 2000 FED Share: GAShare:

sin.zoo
UNDERWAY UNDERWAY
$105,000 $94,500 $10,500

PROJECT: 132960- TYPE WORK: TURN LANES

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: SR. 10 TURN LANES FM LOGANVILLE TO CR 268/0CONEE

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 13296X-

PE:2000 ROW: NONE CST: 2000 FED Share: GAShare:

$130,000
$2,990,000 $2,691,000
$299,000

PROJECT: 132980- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23 /0.3 7

DESCRPT: SR 11 @ CSX RAILROAD IN SOUTH SOCIAL CIRCLE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 132981- TYPE WORK: REPLACE BRIDGE

. FUND: BRIDGE

LENGTH (miles / km) 0.24 /0.39

DESCRPT: SR 11 @ APALACHEE RIVER 7.5 MI NORTH OFMONROE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 132982- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 028/0.45

DESCRPT: SR 10lUS 78 WBL @APALACHEE RIVER 4 MI E OF GRATIS

PE:2000 ROW: CST:

$36,000 AFTER 2002 AFTER 2002

PROJECT: 132983- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

.

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR 10 BUS WBL @SR 10 EBL (US 78) 2 MI WEST OF MONROE

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PR,OJEC. T: 133055- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles / km) 5.8 /9.34

DESCRPT: SR 11 FM LOUISE DRIVE TO BRIDGE OVER APALACHEE RIVER

LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$475,000 $380,000
$95,000

,
,i

-.

PROJECT: 142000- TYPE WORK: RECSTIREHAB

FUND: STP

PE: 1999

UNDERWAY ~

LENGTH (miles / km) 2.5 /4.03

,\

DESCRPT: SR 20- 4-INTERS & 2-PASSING LN FM ROCKDALE CL TO LOGANVILLE

ROW: 2001 CST: 2002

$165,000 $880,000

EXIST. LANES: 02 PROPOSED LANES: 03

FED Share:

$704,000

GAShare:

$176,000

!
.i
'1 .'. !

'j; STA~TE TRANSPORTATION IMPRO'VEMENTPROGRAM

WALTON COUNTY

PROJECT: 142295-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE "

LENGTH' (miles / km) 0.23/0.37

DESCRPT: SR,81@ ALCOVY RIVER 2 MI SWOF BOLD SPRINGS

PE:2001 ROW: CST: .

9/16199 Page 260 0/275
$20,000 AFTER 2002. ', AFTER 2002

,',~PROJECT: I7H 70-

TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH(miles / km) 0.2/0.32

. DESCRPT: CR',289IBEARDEN ROAD @ JACKS CREEK 1.2 MI NW OF GOOD' HOPE

END OF WALTON COUNTY

PE: 1995 . ROW: LOCL CST: 2000 , FED Share: GA Share:

UNDERWAY
$470,000 $376,000 $94,000



'it-m,:Ii)
I I I
I
I;
I
~~.'
E
' R1"to ~
m
~
m'
~.,
"~" ~

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99 Page 261 of275

WARE COUNTY

PROJECT: 521530- TYPE WORK: RECSTIREHAB

FUND: NBS

LENGTH (miles / km) 1.3/2.09

DESCRPT: SR 4BUIUS I/WAYCROSS FM NIBLACKSHEAR AV TO CR 144/AIRPORT RD

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1992. ROW: 2002 CST:

UNDERWAY $2,000,000 AFTER 2002

PROJECT: 522060- TYPE WORK: NEW CONSTRUCTION FUND: NBS LENGTH (miles / km) 0.1 /0.16
DESCRPT: US82/84 CO~. FM CORRIDOR Z TO US 84IFRANCIS ST. EXIST. LANES: 04 PROPOSED LANES: 05

PROJECT: 522770- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 9.25/14.89

DESCRPT: SR 38IUS ~4 FROM CR 4721MANORTO CR 79

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 522775-

PROJECT: 522780- TYPE WORK: RECSTIREHAB

FUND: HPP

LENGTH (miles / km) 6.2/9.98

DESCRPT: SR 38IUS 84 FM CR 79 TO EXISTING 5-LN/WAYCROSS @ SR 4 N.& Y

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 52Y78D-

PROJECT: 523255- TYPE WORK: TURN LANES

FUND: NBS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 4 TURN LANES FM LUCY MOORE RD TO HAVANNA AVE

. PE: 1995 . ROW: LOCL
CST: 2002 FED Share:
GA Share:

UNDERWAY
$140,000 $112,000 $28,000

P: 1994 ROW: 2002 CST:

UNDERWAY $1,000,000 AFTER 2002

PE: 1994 ROW: 2000 CST:

UNDERWAY $1,400,000 AFTER 2002

PE:2000 ROW: NONE CST:

$120,000 AFTER 2002

PROJECT: 571420- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0/0.00

DESCRPT: REHABILlTATI0N OF WAYCROSS DEPOT - PHASE II

END OF WARE COUNTY

PE:LOCL ROW: LOCL CST: 2000 FED Share:
OTHShare:

$986,000 $788,800
$197,200

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9/16/99 _ Page 261 of175

WARREN COUNTY

PROJECT: 210930-

TYPE WORK: SAFETY

FUND: 1M

LENGTH (miles / km) 1.2/1.93

DESCRPT: 1-20 SAFETY UPGRADES@3 LOCIWARRENII-MCDUFFIEI2-COLUMBIA

ASSOCIATED PROJECTS: 21093X-

PE: 1998 ROW: NONE CST: 2000 FED Share: GA Share:

UNDERWAY
$9,529,000 $8,576,100
$952,900

- PROJECT: 221620- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

_

LENGTH (miles / km) 0.56/0.90

DESCRPT: SR 17 @REEDY CK {FM SR 296/MP 0.18 TO MP 0.74}RDWY $=22Y620

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22Y620-

PE: 1991 ROW: 2000 CST: 2000 FED Share: GAShare:

UNDERWAY $50,000
$350,QOO $280,000
$70,000

PROJECT: 22Y620- TYPE WORK: REPLACE BRIDGE

FUND: NHS

LENGTH (miles / km) 0 /0.00

DESCRPT: SR 17 @REEDYCK {FM SR 296/MP 0.18 TO MPO.74}BRDG $=221620

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 221620-

PE: 1991 ROW: NONE CST:2000 FED Share: -GAShare:

UNDERWAY
$765,000 $612,000 $153,000

PROJECT: 232220- TYPE WORK: RECSTIREHAB

nJND:STP

LENGTH (miles / km) 0.3 /0.48

DESCRPT: SR 12/E WARRENTON @ SOUTHERN RR BRlDIREMOVE & REPLW/@-GRADE

EXIST. LANES: 02 PROPOSED LANES: 04

PE:2000 ROW: 2001 CST:

$783,000 $26,000
AFTER 2002

-END OF WARREN COUNTY

-----------_._--,--------------------------

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116199

Page 263 of275

WASHINGTON COUNTY

PROJECT: 220545-

TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles 1 km) 9.8/1.29

DESCRPT: SR 15 FM 800 IT S OF MATTHEWS RDffENNILLE TO WACO RD

EXIST. LANES: 04 PROPOSED LANES: 05

PE:NONE ROW: 2000 CST:

$382,000 AFTER 2002

PROJECT: 222i9X- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1km) 0/0.00

DESCRPT: SR 15 @ 3 LOC BTWN WRIGHTSVILLE & TENNILLEI SEE JOHNSON CO

ASSOCIATED PROJECfS: 222190-

PROJECT: 222285- TYPE WORK: RECSTIREHAB

FUND: HPP

LENGTH (miles 1 km) 8/12.88

DESCRPT: SR 24/SR 540 FM CR to TO JUST WEST OF SR 68 & 22Y285

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 22Y285-

PROJECT: 222290- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 12.2/19.64

DESCRPT: SR 88/SR 540 FR W OF CR 106 TO SR 171 IN JEFFERSON COUNTY

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 22229X-

PROJECT: 222300- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 3 14.83

DESCRPT: SR 15/ NB MP 28.1-29.6/WASHINGTONIISB MP 1.0-2.5/HANCOCK

EXIST. LANES: 02 PROPOSED LANES: 03

ASSOCIATED PROJECTS: 22230X-

PROJECT: 22Y285- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH(mileslkm) 8/12.88

DESCRPT: SR 24/SR 540 FM CR 10 TO W OF SR 68 - FOR EDS $1 SEE 222285

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECfS: 222285-

PROJECT: 231240- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 2.6 /4.19

DESCRPT: SR 24 BET SANDERS'LE & DAVISBORO EB MP 14.3-13.4IWB 5.3-7.0

EXIST. LANES: 02 PROPOSED LANES: 03

PE:NONE ROW: NONE CST: NONE

PE: 1996 ROW: 2000 CST: 2002 FED Share: GAShare:
PE: 1993 ROW: 1999 CST: 2002
GAShare:
PE: 1994 ROW: 2000 CST:

UNDERWAY $1,606,000
$967,000 $773,600 $193,400
UNDERWAY UNDERWAY $24,200,000
$24,200,000
UNDERWAY $40,000
AFTER 2002

PE: 1996 ROW: NONE CST:

UNDERWAY. AFTER 2002

PE: 1997 ROW: 2001 CST:

UNDERWAY $5,000
.AFTER 2002

PROJECT: 245140- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles 1 km) 0.25 10.40

DESCRPT: SR 24 OVER WILLIAMSON SWAMP CREEK 1.3 MILES NW OF DAVISBORO

PE: 1997 ROW: 2001 CST:

UNDERWAY $5,000
AFTER 2002

PROJECT: 250590-TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (miles 1 km) 0.510.81

DESCRPT: JORDAN MILL RD ON NEW LOC FM TANLEY TO HOSPITAL RD & SR 24

PE: 199.6 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$719,000 $575,200 $143,800

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

WASHINGTON COUNTY END OF WASHINGTON COUNTY

. '.' ,

9/16/99 Page 264 of275

,'

#. ~. '"

U" 11 1~.1'
I I
f
L' F
tr
-It
D~J
p.
L

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

9116/99 Page 265 of275

WAYNE COUNTY

PROJECT: 0000078

TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0/0.00 '

DESCRPT: JESUP CORRIDOR ENHANCEMENTS AND RR & BUS DEPOT REHAB.

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$500,000 $400,000

PROJECT: 522380- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (milesI km) 6.71 110.80

DESCRPT: SR 38IUS 84 FM SOUTH CITY LIMITS OF SCREVEN TO SR 203

EXIST. LANES: 02 PROPOSED LANES: 04

OTH Share:
PE: 1994 ROW: 2001 , CST:

$100,000
UNDERWAY $2,214,000 AFTER 2002

PROJECT: 522390- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 5.13/8.26

DESCRPT: SR38IUS 84 FM SR 203 TO CR 392 ATJESUP

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1994 ROW: 2002 CST:

UNDERWAY $3,825,000 AFTER 2002

PROJECT: 522410- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 1.88/3.03

DESCRPT: SR 27IUS 341 FM E CL OF ODUM E TO CR 115

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 522430- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles I km) 4.917.89

DESCRPT: SR 27IUS 341 FM US 25 TO I-MILE W OF CR 394

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 522440- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (mileslkm) 3;8/6.12

DESCRPT: SR 27IUS 341 FM I-MILE W OF CR 394 TO CR 260

EXIST. LANES: 02 PROPOSED LANES: 04

PROJECT: 523265- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (milesI km) 0.27/0.43

DESCRPT: SR 27IUS 341 @LITTLE SATILLA CREEK CITY LIMITS OF ODUM

PE: 1993 ROW: 1997 CST: 2000
GAShare:

UNDERWAY UNDERWAY
$2,853,000
$2,853,000

PE: 1993 ROW: 1997 CST: 2000
GAShare:

UNDERWAY UNDERWAY $10,778,000
$10,778,000

PE: 1993 ROW: 1997 CST:2000 .
GAShare:

UNDERWAY UNDERWAY
$6,663,000
$6,663,000

PE:2000 ROW: CST:

$31,000 AFTER 2002 AFTER 2002

PROJECT: 542425- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

!.

LENGTH (miles I km) 0.22/0.35 DESCRPT: SR 203 @ REEDY CREEK 1.1 MI E OF APPLING CO LINE

~.i

END OF WAYNE COUNTY

PE:2001 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

I
:,.:)I

-
STATE TRANSPOR.TATION IMPROVEMENTPROGRAM

WEBSTER COUNTY

PROJECT: 333165- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.24/0.39
DESCRPT: SR i7IUS 280 @ LANAHASSEE CREEK 2.2 MI E OF PRESTON

PE:2000 ROW: CST:

9116/99 Page 166 of275
$20,000 AFTER 2002 AFTER 2002

PROJECT: 343360- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.21 10.34

DESCRPT: SR 41 @ BEAR CREEK 1.8 MIN OF WESTON

PE:2000 ROW: CST:'

$20,000 AFfER2002 AFfER:Z002

P~OJECT: 343361- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH(mileSI km) :0.26/0.42

DESCRPT: SR 41 @ KINCHAFOONEE CREEK IN SW PRESTON

PE:2000 ROW: CST:

$21,000 AFfER2002 . AFTER2002

PROJECT: 343362- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH(mileslkm) 0.23/0.37

DESCRPT: SR 153 @LANAHASSEECREEK 3.5 MI NE OF PRESTON

PE:2000 ROW: CST:'

$20,000 AFfER2002 AFfER2002

PROJECT: 343363- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE .

LENGTH (miles I km) 0.23/0.37

DESCRPT: SR 45 @ KINCHAFOONEE CREEK OIF .2 MI S OF SUMTER CO LINE

PE:2000 ROW: CST:

$20,000 AFfER2002 AFTER 2002

PROJECT: 343364- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.27/0.43

DESCRPT: SR 45 @ KINCHAFOONEE CREEK .1 MI W OF SUMTER CO LINE

PE:2000 ROW: CST:

$20,000 AFfER2002 AFTER 2002

END OF WEBSTER COUNTY

i

STATE TRANSPORTATIONIMPROVEMENT PROGRAM

9/16199

Page 2670[275

i'.'

WHEELER COUNTY
PROJECT: 0000133 TYPE WORK: ENHANCEMENT

FUND: STP

PE:LOCL

I.'

LENGTH (miles / km) DESCRPT: GLENWOOD DOWNTOWN PARK

0/0.00

ROW: LOCL CST: 2001 FED Share:

.'
$25,000 $20,000

I

PROJECT: 262061- TYPE WORK: RECSTIREHAB

FUND: STATE

orn sss-
PE: 1992

$5,000 UNDERWAY

LENGTH (miles / km) 11.5 /18.52

ROW: 2000

$3,512,000

I

DESCRPT: SR 31IUS 441 FM N/CR 132 THRU DODGE TO SR 46ILAURENS EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 26206X- 26Y061-

. CST:

AFTER 2002

,r
i

PROJECT: 26Y061-

TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0 /0.00

PE:2000 ROW: NONE

$1,000

DESCRPT: SR 31 FM CR 132 THRU DODGE TO SR 46/LAURENS- FOR FED PE

I

EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECTS: 262061-

CST: NONE

PROJECT: 531250- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.2 /0.32

DESCRPT: SR 46 AT OCONEE RIVER

PE: 1991 ROW: 2000 CST: 2001 FED Share: GA Share:

UNDERWAY $25,000
$9,300,000 $7,440,000 $1,860,000

PROJECT: 533150- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23/0.37

DESCRPT: SR 30lUS 280 @ OCHWALKEE CREEK 1 MI E OF GLENWOOD

PE:2000 ROW: CST:

$22,000 AFTER 2002 AFTER 2002

PROJECT: 542100- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24 /0.39

DESCRPT: SR 19 @ OCHWALKEE CREEK I MI N OF GLENWOOD

END OF WHEELER COUNTY

PE: 1997 ROW;' 2001 CST: 2002 FED Share: GA Share:

UNDERWAY $10,000
$829,000 $663,200 $165,800

- - - - - - - - - - - - - - --- - - - - - - - - - - - _ . _ - -~ - - - - - _ . " - - - -

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99

Page 268 of275

WHITE COUNTY

PROJECT: 0000145 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0/0.00

DESCRPT: RUSSELL BRASSTOWN SCENIC BYWAY CORRIDOR MANAGEMENT .

PE:2001 ROW: NONE , . CST:NONE

$90,000

PROJECT:. 0000146 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles I km) 0 10.00

DESCRPT: HELEN - MAIN STREET BRIDGE WALKWAYIUNDERPASS

PROJECT: 121740- TYPE WORK: RECST/REHAB

FUND: STP

LENGTH (miles I km) 0.35/0.56

DESCRPT: SR 17 FM S OF SR 356 TO N OF SR 75 ALT

PROJECT: 122130- TYPE WORK: RECST/REHAB

. FUND: STP

LENGTH(mileslkm) 2.21/3.56

DESCRPT: SR 75 FM SR 75 ALT/CLEVELAND NE TO CR 88

EXIST. LANES: 02 PROPOSED LANES: 03

PE:LOCL ROW: LOCL CST:2001 FED Share:

$20,QOO $16,000

OTH Share:
PE: 1995 . ROW: 1989 . CST: 2000 FED Share: GAShare:

$4,000
UNDERWAY UNDERWAY
$392,000 $313,600 $78,400

PE:2000 ROW: 2002 CST:

$33,000 $42,000 AFTER 2002

PROJECT: 132560- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.23 10.37

DESCRPT: SR 115 @ CHATTAHOOCHEE RIV 7.5 MI E. OF CLEVELANDIHABERSHAM

ASSOCIATED PROJECfS: 13256X-

PE: 1996 ROW: 2000 CST: 2000 FED Share: GAShare:

PROJECT: 141830- TYPE WORK: RECST/REHAB

FUND: STP

LENGTH (miles I km) 7.32 111.79

DESCRPT: SR 384IDUNCAN BRIDGE RD FM W OF SR 115 TO SR 75 (8 LOCATIONS

EXIST. LANES: '02 PROPOSED LANES: 03

PE:2002 ROW: . CST:

UNDERWAY $20,000
$818,000 $654,400 $163,600
$140,000 AFfER2002 AFTER 2002

PROJECT: 170881- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (mileslkm) 0.1/0.16

DESCRPT: CS 613ILORELY RD OVER CHATTAHOOCHEE RIVER IN HELEN

EXIST. LANES: 01 PROPOSED LANES: 02

END OF WHITE COUNTY

PE: 1993. ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$306,000' $244,800
$61,200

STATE TRANSPORTATION IMPROVEMENTPROGRAM

9116199 Page 269 of275

WHITFIELD COUNTY

PROJECT: 0000147 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (mileslkm) 0/0.00

DESCRPT: TUNNEL HILL W&A RAILROAD TUNNEL PHASE 2

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$313,000 $250,400

PROJECT: 610760- TYPE WORK: RECST/REHAB

FUND: 1M

LENGTH (miles 1 km) 0.53 10.85

DESCRPT: 1-75 @SR3IUS41IROCKYFACEEXIT

EXIST. LANES: 04 PROPOSED LANES: 06

OTH Share:
PE: 1994 ROW: 2000 CST:

$62,600
UNDERWAY $2,000,000 AFTER 2002

~.

}f

PROJECT: 610890- TYPE WORK: RECST/REHAB

FUND: 1M

~.

LENGTH (miles 1 km) 1.18/1.90

DESCRPT: 1-75 INTERCHANGE AT CARBONDALE ROADICR 665/SEE 61Y890

ASSOCIATED PROJECfS: 61Y890-

PE: 1995 ROW: 2000 CST:

UNDERWAY $1,634,000 AFTER 2002

PROJECT: 610900- TYPE WORK: RECST/REHAB

FUND: 1M

LENGTH (miles 1 km)0.81 11.30

DESCRPT: 1-75 AT SR 201 - RELOCATE CR 243 AWAY FROM FREEWAY

PE: 1995 ROW: 1998 CST: 2000 FED Share: GA Share:

UNDERWAY UNDERWAY
$616,000 $554,400
$61,600

PROJECT: 610905- TYPE WORK: RECST/REHAB

FUND: 1M

LENGTH (miles 1 km) 0.5 10.81

DESCRPT: 1-75 AT SR 201 - WIDEN AND LENGTHEN RAMP TAPERS

PE: 1995 ROW: NONE CST: 2000 FED Share: GAShare: '

UNDERWAY
$508,000 $457,200
$50,800

PROJECT: 611280- TYPE WORK: MAINTENANCE

FUND: 1M

LENGTH (miles 1 km) 0/0.00

DESCRPT: BRIDGE PAINTING IN WHITFIELD COUNTY/61Y280

LUMP SUM PROJECT

ASSOCIATED PROJECTS: 61Y280-

PE:NONE ROW: NONE CST: 2000 FED Share: GAShare:

$401,000 $360,900
$40,100

PROJECT: 61Y280- TYPE WORK: MAINTENANCE

FUND: STP

LENGTH (miles 1 km) 0/0.00

DESCRPT: BRIDGE PAINTING IN WHITFIELD COUNTY/611280

LUMP SUM PROJECT

PE:NONE ROW: NONE CST: 2000 FED Share:

$326,000 $260,800

ASSOCIATED PROJECTS: 611280!:r.

GAShare:

. $65,200

".:....~.

PROJECT: 61Y890- TYPE WORK: RECST/REHAB

FUND: STP

LENGTH (miles 1 km) 0/0.00

DESCRPT: 1-75 INTERCHANGE AT CARBONDALE ROADICR 665/SEE 610890

PE: 1995 ROW: 2000 CST:

UNDERWAY $4,905,000 AFTER 2002
t'

ASSOCIATED PROJECTS: 610890-'
"':

.i

PROJECT: 620960- TYPE WORK: RECST/REHAB

FUND: STP

PE: 1992

UNDERWAY

, LENGTH (miles 1 km) 2.5 14.03

ROW: 1992

UNDERWAY

DESCRPT: SR 3IUS 41 FM S OF STONECREST DR N TO CR 306ITUNNEL HILL

CST: 2000

$7,482,000

EXIST. LANES: 02 PROPOSED LANES: 05

FED Share:

$5,985,600

GAShare:

$1,496,400

,I
:J

\ 'STJt~IJ'ETJotNSP(jRtATI0N1MPR(jVEMEJVT PROGRAM

WHITFIELD COUNTY

PROJECT: '631250- TYPE WORK: RECSTiREHAB

FUND: STP

,LENGTH (miles/km) 2.8/4.51
DESCRPT: SR201 EB MP 13.6-14.91 WB MP 14.6-15.51 WB 17-181RTL @ SR 2

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1992 ROW: 1998 , CST: 2000'
FED Share: GAShare:

9/16/99 ' Page 270 of275
UNDERWAY UNDERWAY , "'$4,275,000 $3,420,000
$855,000

PROJECT:' 671220- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (niilesIkm) 0/0.00

DESCRPT: TUNNEL HILL W&A RAILROAD REHAB & LANDSCAPING

END OF WHITFIELD COUNTY
:"r'. ..

PE:LOCL ROW: LOCL
CST: 2000 FED Share:' ,
OTHS!lare:

$875,000 $700;000
$175,000

'f

,i
.,
i. :.
II.'i.
I
E
I I

. STATETRANSPORTATIONIMPROVEMENTPROGRAM

9/16199 Page 1710/175

WILCOX COUNTY

PROJECT: 0000134 TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (mues / km) 0/0.00

DESCRPT: PINEVIEW CABOOSE PARK

PE:LOCL ROW: LOCL CST: 2001 FED Share:

$49,000 $39,200

PROJECT: 431690- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: SR 30lUS 280 @ ALAPAHA RIVER TRIB. 0.7 MI W OF PITTS

OTHShare:
PE: 1997 ROW: 2001 CST:

$9,800
UNDERWAY $3,000
AFTER 2002

ASSOCIATED PROJECTS: 431695-

PROJECT: 431695- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE'

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 30lUS 280 @ALAPAHA RIVER 1.2 MI W OF PITTS

ASSOCIATED PROJECTS: 431690-

PE: 1997 ROW: 2001 CST:

UNDERWAY $2,000
AFTER 2002

PROJECT: 432070- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 30lUS 280 @ ALAPAHA.RIVER TRIB.0.8 MI E OF SEVILLE

PE:2000 ROW: 2002 CST:

$15,000 $10,000 AFTER 2002

PROJECT: 432075- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.23 /0.37

DESCRPT: SR 30lUS 280 @ ALAPAHA RIVER TRIB. 1.3 MI E OF SEVILLE

PE:2000 ROW: 2002 CST:

$15,000 $10,000 AFTER 2002

END OF WILCOX COUNTY

STATE TRANSPORTATION IMPROVEMENTPROGRAM

WILKES COUNTY

PROJECT: 221740- TYPE WORK: RECSTIREHAB

FUND: STATE

LENGTH (miles / km) 4.6317.45

DESCRPT: SRI7 FM MP 14.68-16.71IMP 23.88-26.28IINCL CLVTS @3 LOC

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 22Y740-

PE: 1993 ROW: 2002 CST: .

9/16/99 Page 272 of275
UNDERWAY $200,000
AFTER 2002

PROJECT: 2278f5- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: SR 17 @ ROCK CREEK 2.3 MI N OF WASHINGTON

PE:2000 ROW: CST:

$20,000 AFTER 2002
AFTER~002

PROJECT: 22Y260- TYPE WORK: RECSTIREHAB

. FUND: NHS

LENGTH (miles / km) 0 /0.00

DESCRPT: SRI7 FM N WASHINGTON BYP TO CR 193 - FOR FED PE; 222260

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222260-

PROJECT: 22Y264- TYPE WORK: RECSTIREHAB

FUND: NHS

LENGTH (miles / km) 0/0.00

DESCRPT: SR 17 FROM CR 113 TO NO.OF CR 50lELBERT - FOR FED PE; 222264

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 222264-

PROJECT: 22Y740- TYPE WORK: RECSTIREHAB

FUND: NHS .

LENGTH (miles / km) 0/0.00

DESCRPT: SR 17 FM MP 14.68-16.71IMP 23.88~26.28 - FOR FED PE; 221740

EXIST. LANES: 02 PROPOSED LANES: 04

ASSOCIATED PROJECTS: 221740-



PROJECT: 232300- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24 /0.39

DESCRPT: SR 44 @KETTLE CREEK 6.5 MI SW OF WASHINGTON

PE:2000 ROW: NONE CST: NONE

$1,000

PE:2000 ROW:J:IlONE CST: NONE

$1,000

PE:2000 ROW: NONE CST: NONE

$1,000

PE:2000 ROW: CST:

$22,000 AFTER 2002 AFTER 2002

PROJECT: 245385- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.22/0.35

DESCRPT: SR 44 @ FISHING CREEK 5 MI NE OF WASHINGTON

PE:2000 ROW: CST:

$20,000 AFTER 2002 AFTER 2002

PROJECT: 271285- TYPE WORK: ENHANCEMENT

FUND: STP

LENGTH (miles / km) 0.2 /0.32

DESCRPT: DOWNTOWN WASHINGTON STREETSCAPE PHASE II

PE:LOCL ROW: LOCL CST:2000 .
FED Share:

$300,000 $240,000

.

OTHShare:

$60,000

END OF WILKES COUNTY .

STATE TRANSPORTATION IMPROVEMENT PROGRAM

9116/99 Page 2730/275

WILKINSON COUNTY

PROJECT: 221762- TYPE WORK: REPLACE BRIDGE

FUND: NHS

PE: 1992

UNDERWAY

LENGTH (miles I km) 1 /1.61

ROW: 2000

$250,000

~I,;.,

DESCRPT: SR 29IUS 441 @ BIG SANDY CREEK S OF IRWINTON EXIST. LANES: 02'PROPOSED LANES: 04

CST: 2000 FED Share:

$3,750,000 $3,000,000

GAShare:

$750,000

'I', t
~ "t
;"

PROJEct: 221870- TYPE WORK: NEW CONSTRUCTION FUND: HPP

PE: 1992

UNDERWAY

LENGTH (milesI km) 7 I I 1.27

ROW: 2000

$1,715,000

I: I

DESCRPT: FALL LINE FWY/NORTH GORDON BYPASS FM SR 57 TO SR 243 @ LAKE EXIST. LANES: 00 PROPOSED LANES: 04

CST: 2000 FED Share:

$19,758,000 $15,806,400

GAShare:

$3,951,600

I

PROJECT: 221875- TYPE WORK: RECSTIREHAB

FUND: STP

LENGTH (mileslkm) 4.717.57

PE:2000 ROW:

$200,000 AFTER 2002

DESCRPT: SR 57 FM FALL LINE FREEWAY TO EAST OF SR 18 AND ALONG SR 18

CST:

AFTER 2002

PROJECT: 222220- TYPE WORK: REHAB. BRIDGE

FUND: BRIDGE

LENGTH (milesI km) 0.35/0.56

DESCRPT: SR 57 OVER THE OCONEE RIVER AT WASHINGTON COUNTY LINE

EXIST. LANES: 02 PROPOSED LANES: 03

PE: 1998 ROW: 2001 CST:

. UNDERWAY $100,000
AFTER 2002

PROJECT: 231420- TYPE WORK: RECSTIREHAB

FUND: STATE '

LENGTH (milesI km) 5.9/9.50

DESCRPT: SR 29IUS 441 FROM SR 112 TO SR 96 INCLUDE BRIDGES

EXIST. LANES: 02 PROPOSED LANES: 04

PE: 1993 ROW: 2000 CST:

UNDERWAY $773,000
AFTER 2002

PROJECT: 23143X- TYPE WORK: RECSTIREHAB

FUND: STATE

. LENGTH (miles I km) 0/0.00

DESCRPT: SR29IUS 441 FROMCR471 TO SR 1121 LAURENS- 231430

ASSOCIATED PROJECfS: 231430-

PROJECT: 245020- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles I km) 0.24/0.39

DESCRPT: SR 18 @ BIG SANDY CK FM MP 0.2 IN TWIGGS TO MP 11.60 WILKNSN

ASSOCIATED PROJECfS: 24502X

PROJECT: 262470- TYPE WORK: NEW CONSTRUCTION FUND: STATE LENGTH(mileslkm) 16.7/26.92
DESCRPT: FALL LINE FWY ON NEW LOC FM SR 243 TO SR 24 IN BALDWiN CO EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECfS: 26247X- 26Y470-

PROJECT: 26Y470,- TYPE WORK: NEW CONSTRUCTION FUND: NHS LENGTH (miles I km) 0/0.00
DESCRPT: FALL LINE FWY FM SR 243 TO SR 24IBALDWIN - FOR FED PE;262470 EXIST. LANES: 02 PROPOSED LANES: 04 ASSOCIATED PROJECfS: 262470-

PE:NONE ROW: NONE CST: NONE

PE: 1995 ROW: 1998 CST: 2000 FED Share: GAShare:
PE: 1993 ROW: 2001 CST:

UNDERWAY UNDERWAY $1,020,000
$816,000 $204,000
UNDERWAY $3,556,000 AFTER 2002

PE:2000 ROW: NONE CST: NONE

$1,000

STATE TRANSPORfFATIlJN'IMIJ'ROVe"MENT PROGRAM---

9/16/99

Page 274 of275

WILKINSON COUNTY

PROJECT: 271298- TYPE WORK: 'ENHANCEMENT

FUND: STP

LENG!['H(miles / km)

0/0.00

DESCRPT:'CITY OF,GORDON RAILROAD DEPOT REHAB

PE:LOCL ROW: LOCL CST: 2000 FED Share:

$135,000 $108,000

PROJECT: 34308Z- TYPE WORK:RECST/REHAB

FUND: STP

L'ENGTH (miles / km) 0/0.00

DESCRPT: SR 18 EB FM MP 2439IJONES TO MP 0.7IrwILKINSON343085

OTHShare:
" PE:NONE ROW: NONE CST: 2000

$27,000 .$0

ASSOCIATED PROJECTS: 343085-

END OF WILKINSON COUNTY

STATE TRANSPORTATIONIMPROVEMENTPROGRAM

WORTH COUNTY

PROJECT: 432145- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.24/0.39

DESCRPT: SR 300 SBL @ JONES CREEK 1.4 MI S OF OAKFIELD

PE:2000 ROW: CST:

9/16199 Page 275 of275
$20,000 AFTER 2002 AFTER 2002

PROJECT: 470895- TYPE WORK: REPLACE BRIDGE

FUND: BRIDGE

LENGTH (miles / km) 0.21 /0.34

DESCRPT: CR 297 @ SWIFT CREEK APPROX. 2 MILES NE OF WARWICK

EXIST. LANES: 01 PROPOSED LANES: 02

END OF WORTH COUNTY

PE: 1995 ROW: LOCL CST: 2000 FED Share: GAShare:

UNDERWAY
$505,000 $404,000 $101,000

TRANSIT PROJECTS

I



i

,
:.:<'
1
(
.J

TABLE OF CONTENTS FOR TRANSIT

I. Introduction II. AlbanyMPO III. Athens MPO
IV. AtlantaMPO
V. Augusta-Richmond CO. MPO
VI. Brunswick VII. Columbus MPO VIII. Macon-Bibb Co. MPO
IX. Rome-Floyd Co. MPO
X. Savannah MPO
XI. Warner Robins XII. Statewide

Page 1 3 8 13 21
25
29
34 39 44 50 53

., ,
)

,

INTRODUCTION

jt

Part 2 of the STIP is a compendium of transit projects listed for FY 2000 through FY 2002 in the

:,.

:;

J
~

adopted Transportation Improvement Programs (TIP) for urbanized areas in Georgia. It includes projects to be funded under Title 49 U.S.C. Sections 5307,5308 (Clean Fuels Program),5309,' 5310, and 5311. Transit projects were listed according to the following transit agencies:

Albany Athens Atlanta

LOCATION

Augusta Cobb County Columbus Macon

Rome Savannah

TRANSIT AGENCY NA1vffi
Albany Transit System (ATS) Athens Transit System (ATS) '\ Metropolitan Atlanta Rapid Transit Authority (MARTA) Augusta Public Transit (APT) Cobb Community Transit (CCT) Columbus Transit System (METRA) Macon-Bibb County Transit Authority (MBTA)
Rome Transit Department (RTD) Chatham Area Transit Authority (CAT)

Brunswick and Warner Robins do not.have an urban public transportation system. However, the projected Section 5307 and 5310 projects are listed in the TIP as mandated by federal regulations.

The local transportation planning process prepares annually a TIP for capital and operating

projects. The l\1PO along with the public participation process annually selects and adopts the

,.

projects listed in the TIP. Only projects listed in the TIP may be considered for Federal and State

~-

funding. In accordance with the Transportation Efficiency Act for the 21st Century (TEA-i 1),

the projects for FY 2000 - FY 2002 are included in the STIP.

L.

.,-.

1

The Georgia Department of Transport:ation'(GADOT) is the designated recipient of FTA

funds under 49 U.S.C. Section 5307 on behalf of areas under 200,000 population. These

include transit properties in Albany, Athens, Macon, Rome and Savannah which request

. FTA transit financial assistance from the Governor's' Apportionment and matching State

assistancevIn addition, GADOT's0ffice of'Intermodal Programs coordinates with the

Georgia Department ofHumail Resourees(GDHR) for projects to be funded under

Section 5310.. TheOffice of'Intermodal Programs also programs fundihg'forthe rural

transit assistance program under Section 5311. The GADOT programs and contracts

funds for public transportation as outlined in the TIP, STIP and in the State General Fund

Budget.

.

Transit agencies in Atlanta, Augusta and Columbus, with populations of over 200,000

people, are not a part ofthe Governor's Apportionment process. However, the State does

provide general fund assistance for one half of the local share of capital projects listed in

the TIPs for Augusta and Columbus. In Atlanta, the state does provide capital assistance

on various projects for the regional transit agencies.

.

2
".'1"

Albany
,.
~: .... t
e .'
I:
..~ ) 3

-~

CAPITAL SCHEDULE FOR ALBANY TRANSIT SYSTEM

Section 5307

I

p':g~gmemH:n~t::M'ttmtttllmtmlfMlt'f:@t;mit%flN;;lttml;miUmmtttw :::~~:Uim:~:~fX:~Mt::tU:'::;: nUmmfflYilQ:1ttHfl; lfMmeYQg:wumr: NU'f":J;OTAJit:mtt:

$.iteJMNtlnrK:;tt;::::tft:::t:::f:Utf:K::ttMttt~tt:t:tn:::::tt::::'::tttttttm;nttMt ;tt~:t:'-.QJ9~:;;t'tt ;~'t:t~}IP.i1(l.~t:::tt:t: .t::::~'tt'-QJ9$.4ntt:::

Transit Coach/Lease (4) 30 foot

$121 ,528

$121 ,528

$121 ,528

$364,584

Transit Coach Lease (4) 30 foot

$129,500

$129,500

$129,500

$388,500

Transit Coach Lease (2) 25 foot

$0

$0

$26,534

$26,534

Paratranslt Bus Lease (3) 25 foot

$37,686

$37,686

$37,686

$113,058

Paratranslt Bus Lease (3) 25 foot

$0

$38,606

$38,606

$77,212

Support Vehicles

$35,000

$0

$17,000

$52,000

Forklift

$0

$35,000

$0

$35,000

Facility Modification Ren. Storage/Battery Charging Area

$0

$3,500

$0

$3,500

Facility Modification - Security Lighting

$0

$15,000

$0

$15,000

Facility Modification- Ceiling Tiles and Paint

- Facility Modification Office and Garage Roofs

- Facility Modification Pave Bus Parking Apron
Facility Modification . Pave Bus Wash Exit

- Oil Water Separator EPA Regulations

Parts Storage Bins

-

$15,000 $45,000
$0 $0 $38,000 $0

$0 $0 $110,000 $45,000 $0 $15,000

$0

$15,000

$0

$45,000

$0

$110,000

$0

$45',000

$0

$38,000

$0

$15,000

Fareboxes for Replacement Vehicles
- Capital Maint. Item Engine Cradle & Dolly - Capital Maint. Item Engine and Trans. Rebuild - Capital Maint. Item Spare Engines & Trans. - Capital Maint.. Purchase Tires

$0 $0 $0 $0 $10,000

$25,000 $20,000
$0 $15,000 $10,000

$10,000 $0
$11,000
$10,000

$35,000 $20,000 $11,000 $15,000 $30,000

Maintenance Tools and Equipment

$5,500

$5,500

$5,500

$16,500

2-Way Radios

$12,500

$5,000

$5,000

$22,500

Fuel Tank Testing
- Bus Shelters Non-Advertising (2 3)

$1 ,000 $0

$1,000 $9,000

$1,000 $13,500

$3,000 $22,500

Office and Facility Automation

$2,000

$3,000

$3,000

$8,000

Bus Benches (10 -10 -10)

$3,000

$3,000

$3,000

$9,000

PB.Q~lfi'-lMt.Q$.J.KtHtmmtl;gnn;nmtllltmnttllllll;;ltttl;n;'tl:::mtt:mnr ':':rmn't$.4~.~~l~~~U 'trr;;rt$.M7JU9.:': ;t;r%tl$.4$.I~Q:'4t :mtt::$.n~()JI.":;

FEDERAL COST

$364,571

$517,856

$346,283

$1,228,710

STATE COST

$45,571

$64,732

$43,285

$153,589

LOCAL COST

$45,571

$64,732

$43,285

$153,589

DOT DISTRICT # 4

CONGo DIST.

2 RDC

SWG

OPERATING ASSISTANCE SCHEDULE FORALBANY TRANSIT SYSTEM Section 5307

)i.Jrtiil@@m!@iMilMMm;llmmm;mlW;mtt:rmMMMllmW@1 tt;n14Q4I2&lmmm JiMJlito.4.ISJ.1ii@Mr J@WI04&ISMmm 111~ltfffjm\lmt~llitf ,tOSe.SAmGilee.8.IQDtttt@:tttfllttt')rr:)mmmumm= u:)r::::Ulr:p;lo.P.ME1@t: ;r=tIll=)m)E)flU1Jll1lm:~ Hl~::)=:~:l~:m:fiM::Qz.lll;mmn mnnt:mQllt.HtIl'f

- 07/01/99 06/30/00

$1,620,71 0

$1,620,71 0

- 07/01/00 06/30/01
07/01/01 - 06/30/02

$1 ,398,392

,
$1 ,396,392

$1 ,398,392 $1 ,396,392

HH.SaUSI1i11If,QS1Nlrttttti:)::rll:):tI):Imr=:::=t:=m:tttilnirWtt: ::::~tlli:::$.1:;'~QrZ1)(M ;~tlr::~:1$1,a$.l~a$.%.;:: llrr;;;$1J$lliVs.at ::;;;;;;;;~::$4~41;i~J.9.It

FEDERAL COST

$435,093

$362,591

$362,500

$1,160, 184

LOCAL COST

$1,185,61 7

$1 ,035,801

$1 ,035,892

$3,257,31 0

DOT DISTRICT # 4

CONGo DIS.

2 ROC

SWG

7;" ... ~.:.:;~.~....

......,.

;;

"'j

...................,'"

,:.

I

CAPITAL SCHEDULE FOR ALBANY TRANSIT SYSTEM

~ jj IT

Section 5309

: : : = - - 0!":t :.::{

T::;4P4Qg~:::::'rl: ::::r::':::r)J,m4:Q,~U'f:::::%:I'

'.'::'" 00. :":' '. :.:rLF:VOQ:::::.!:::r::: ::::::::::::::'!:::::S;YiU1::::!:!:t:.t:r::

Admmlstratlon/Transter Facility

$700,000

$0

$0

$700,000

Building Modification

$50,000

$50,000

$50,000

$150,000

Vehicle Replacements

$158,000

$345,000

$997,000 $1,500,000

::!:!e8~;;r.iI1l::fJ,~$1!:;t:':':':::::::::1:':rmg:::::m::r:::rr::':'::::IIIIIf:r'::II :::rr::;i:'I:::$.~t1~~ttp.tJ.r .::::::':rrriM~~$i(f,qnI: ::::I::}}!::$j::~Q4.7:i~QA} ::i:}t:;l$a~~$P.~nuor

FEDERAL COST

$726,400

$31 6,000

$837,600 $1,880,000

LOCAL COST

$90,800

$39,500

$104,700

$235,000

STATE COST

$90,800

$39,500

$104,700

$235,000

DOT DISTRICT # 4

CONGo OIST.

2 ROC

SWG

0\

. .,

-.

CAPITAL SCHE0 ULE IN ALBANY FOR EL0 ERLY AN 0 DISABLE0
Section S310
==~:~~ !:$.l1lPfft.it:fN1::mm1If:t:\:m::;::L:)\:::t:@ff::)f)::)))ii)iiiil)!)!:I':::;:::!!::!!?: ,!::??::':::4V:tUt~'!:tl)f :rl:::{'f:4,*Q'1$f::!::m::::,::,
ft1es.QiIP;mQNf)I'!III'!I:;;:'1I:IIi:IIliiii'fIiimIII:III:::::;;))1 ::)::!W::::::::SM:IOU@t:::::j':I:: 1:If:rlIFMiltUI!n:mUi::

Purchase of Service

$24,476

$24,476 00

Purchase 0 f Service

$25,700

$25,700 00

Purchase of Service

$26,985 $26,985 00

m;~ilUa.U~!eQS.'tI:::11':If:I1ltI'1mln:;1nm'nmmf'1:::I:I': ::1:::::;;I)1':fI$.~4~4ZQI :!:::1:;:11:::%:::$.16.17001:::: :':Ii:IIIrI1H$~S~1lJ.5f :m:Il:':::':I:::::::$irm:t~111

FEDERAL COST

$19,581

$20,560

$21,588

$61,729

STATE COST

$4,895

$5,140

$5,397

$15,432

DOT DISTRIGT # 4

CONG DIS

2 RDC

SWG

"

Athens
~. r-
L.:
L.,.:
.. ..'
8

': :~-.;;:

.~

~:"--

.. / '

~

~

'....- ..

l"'~' ..~....... \0... . ' ~

...t .. ..~.""!

l".~.

.~~.

',~ ~'_.'

..

1,---.'

....

CAPITAL SCHEDULE FOR ATHENS TRANSIT SYSTEM Section 5307

ima.$.Q.Slettlfti:;:t:t:tl1mnt'l,{tmmtMt::::'t::t:'1{ii::t1::::::'i:mti} :StJ.NlhW;:m':rttitkI\i;if\iMltM1il1'lttmttr;:'ttt:::::j':::::tt;:lt::t

::;ii;!i:tti::~B~nQOliiii::ti!!
i:::::r:::Htul1:nSQ\':::'::tt:t

:tt;tii!!':;Ejtat:!!!i!ii!:'!!!:' t:;::::t::::a:llt:O.7111111

11:::.:I:II!li:I!:ti.;l:~:':':!li:lt:tl;:I_

Transit Vehicle (1)

$260,000

$0

$0

$260,000

Transit Vehicles 2)

$0

$530,400

$0

$530,400

Transit Vehicles 2)

$0

$0

$535,000

$535,000

Demand Response Vehicle-Van (1)

$60,000

$0

$0

$60,000

Demand Response Vehicle-Van (1)

$0

$61 ,500

$0

$61 ,500

Demand Response Vehicle-Van (1)

$0

$0

$63,000

$63,000

Capital Maintenance

$100,783

$0

$0

$100,783

Capital Maintenance

$0

$85,000

$0

$85,000

Capital Maintenance

$0

$0

$72,000

$72,000

Replace Maintenance Equipment

$0

$5,400

$0

$5,400

Office Equipment

$0

$0

$5,700

$5,700

Supervisor Vehicle (1)

$0

$0

$15,000

$15,000

J?:'R~4iQ;11QQ$~ttm;MIMl'l:Jlm;m;:llJ:::::m::::r::::mt;:;::l::J lJ:HF':::::::J$4.~p.~1.J.~U tJtrm;::USll.m~uor: lmr'::'r'::::::$.I~nnIQUJ r:JJ::::I$.~i~7t.a~r.~f

FEDERAL COST

$336,626

$545,840

$552;560

$1,435,026

STATE COST

$42,078

$68,230

$69,070

$179,378

LOCAL COST

$42,078

$68,230

$69,070

$179,378

DOT DISTRICT # 1

CONGo DIST.

11 ROC

NEG

. ",

OPERATING ASSISTANCE SCHEDULE FOR ATHENS TRANSIT SYSTEM
Section 5307

===-- :):(&:1IJ.BWMmWiWfii:=:)::)=))I:::;::::!:ffffm)'ffi:1@fffrWiim;lMWfi:I1tiWfil if;);i:If':Q.~:Q!tP;imffr :::r~=:)1W)mt!1!o.Z$fn:nn
WaeSBAl1ING=::B:i.B.IQQ:)(:):)r:W):=:!=W!:::I)(:!:IH:!r:!n/m~!:):!:W)(iIIII li:l:l((Fnl~lII;;ff!( ::!:fff::!:):!:!e,m:JUl=!=!(:!:IW!=!

07/01/99 - 06/30/00

$2,3 16,243

$2 ,316,243

- 07/0 1/00 06/30/0 1

$2,235,200

$2,235,200

07/01/0 1 -06/30/02

$2,334,033 $2,334,033

teB(ldEQllMQ$I1=!Hti@lfMI=i;!===~ill::!;::;:tHH:rIm:liH:::fl!mt@ff IiW%il$2~ajl~g4~=m :H:!jj=l:=$:~~ga$~gop:r 1;;li:ri$2~3.3.4~U.$S.f 1!::=11:$$.~$.ja$.~4ti$.j

FEDERAL COST

$454,743

$446 ,200

$454,743 $1,355,686

LOCAL COST

$1,861,500 $1,789,000 $1,879,290 $5,529,790

....

o

DOT DISTRICT # 1

CONGo 0 IS.

11 RDC

NEG

.:: ~

.',~,

!":"'.,. ..-., ..

tt.~",'

r'

CAPITAL SCHEDULE FOR ATHENS TRANSIT SYSTEM Section 5309

::~;;;;;lll:;~:::'::;:'ll::;l_ fm;.s.CSle1't.8)N:Wl@fMM1Hi\ttt:n:t:@:rmmtttt@@tlHl :t:mm@i:fW\J8)ii:t'ttfl illl:}@e~:t(l1ml:@@W
tSTmM#.li!;il~ttj:!~::~:ijin!j::M!i::::iM:;tniiijiiIIIIIIIIIitnit'lmIII'::'i;I:li i;Jtf:IJIJ>U,6Ittiiiij:i!:::: ::;tiijij:i:iji::Wpn.:QI~1itirji'!fi

Transit Bus Vehicle (1) Transit Bus Vehicles (1) Transit Bus Vehicle (1) Multi-Modal Transportation Center
- Contingency Funds Section "5309"

260,000 26,000

265 ,200 26, 520

267,500 1,199,000
26,750

260, 000 265 ,200 267,500 1,199,000
79,270

fS8aUEtllHlJ.!$nIIIIII%t:tti'Ii:IIIj:I:tjI:;jijttr:'iI't:ifj!I:Ii: III!irr'!~iji::!:i:'2~nnIQQf :i:IIirr~:'!Wl!2~U72Jn tr:!:it'lrn.J4U3.~I$Qji; ::::ti:IIIJ!:2~n7UJS7Qt

FEDERAL COST

228,800

233 ,376

1,194,600

1,656,776

LOCAL COST

28 ,600

29, 172

149,325

207,097

STATE COST

28,600

29, 172

149,325

207, 097

.........

DOT DISTRICT # 1

CONG DIS.

11 RDC

NEG

0'

.

CAPITA,.. SCHEDULE IN ATHENS FOR ELDERLY AND DISABLED Section 5310

ImJ.R:)I.~ffm't@mfft\I}::\~:N:f:\::\l:ri\tl{%::::}1;ttlmf':'\lmWtt\:~}::t:~t\m:f::::::~\W:::1:Mzn~9It::::}}: tt':t:i::':1\YLQIZt;f:@lCfmmfWlM7na9:t::~:\I~
t\r::::ttUUt:'\Q1.l,::\:::ttt'::::::r:\:::::':\::::'::::li\\HUt\tlt;ttnttI::IJfM::()at:t:::::::\'::UtlttrrnQ1r.Atr:r:I:I:

$18,828

$18,828

Purchase of Service

$19,769

$19,769

Purchase of Service

$97,559

$97,559

:fIRQUsetiIQSlt::iw;m;I!IU;!\:f\\:!iii!ii::WfIfI!f\f:::::t\:\:\:':\:::;;!:::::\:: ::I::IlffMWr$.'-:S"lJ.2.Sn :::;!lMl\fmI;::$~l:llm$.$.I: :jmH:nl::;:::::::$":Z"'~$St :t'::Ijm:\::::':f$1:$.~":':$.I.:::'

FEDERAL COST

$15,062

$15,815

$78,047

$108,925

STATE COST

$3,766

$3,954

$19,512

$27,231

DOT DISTRICT # 1

CONGo DIS.

11 ROC

NEG

.Atlanta
~,
12

.'r'
~.

..

CAPITAL SCHEDULE FOR METROPOLITAN ATLANTA RAPID TRANSIT AUTHORITY
Section 5307

nasS'-,81tlPN::;\lff\I:WI:\:\\:\\;:':::::;::f??f?f\;rt:\:::::::::'m::::f'@\fm:f::g:I
:S.mJfMifilti@@fl;:111111::::1:@Vi::VV:::I:'@:::\::f::I:::::::'IWV:III::::11:111fi

:::t\"::';::\I:\:fi1t::;OtM:lf:11::
:?@:f:l:z,pz~a41:::::VVf

II}}}lia:i~U1???:{ff; VfVf:17Pl:o.a~I::11n:

1!)!)!)!):)i!I:)i::iii~iil::!:!:!)!:l:!::!_

Vehicle Overhaul (Bus/Rail)

$4,833,287 $4,833,287 $4,833,287 $14,499,861

Associated Capital Maintenance

$8,047,563 $8,047,563 $8,047,563 $24, 142,689

Tools and Equipment

$1,000,000 $1,000,000 $1 ,000,000 $3,000,000

Security Equipment

$1,000,000 $1,000,000 $1,000,000 $3,000,000

Line Structure Rehabilitation/Renovation

$500,000

$500,000

$500,000 $1,500,000

Facilities Rehabilitation/Renovation

$522,684

$525,000

$525,000 .$1 ,572,684

Environmental Rehabilitation/Renovation

$500,000

$412,684

$400,000 $1,312,684

Maintenance and Support Vehicles

$425,000

$425,000

$425,000 $1,275,000

Computer and Computer Related

$100,000

$100,000

$100,000

$300,000

Training

$130,000

$130,000

$130,000

$390,000

Preventive Maintenance

$18,544,855 $21 ,665,489 $25,454,858 $65,665,202

Bus Replacement Program

$1,000,000 $1,000,000 $1 ,000,000 $3,000,000

Transit Enhancements

$41 0,000

$500,000

$50,000

$960,000

:t.ljp'U$.lhet.6i~t.l:rr'itiJlttt%\'fIlttift:::I:':,,::::::,,:m:::"::"::::t:::::t:::t:ttV:;$3.tl~ln:a~aa~n ::::::":%:$.4m1a9.U).~a::,,: ::t:::l:$4a~I$.$.'~tlu.$Y :!:::I$.j:20~~1:B.Wj:2~r:::

TRANSIT PLANNING PROGRAM

Regional Transit Planning

$807,825

$807,825

$807,825

Short Range Transit Planning

$1 ,51 0,821 $1 ,633,505 $1 ,633,505

Special Projects Planning

$1,000,000 $1,000,000 $1,000,000

Long Range Transportation Planning

$881 ,354

$968,670

$968,670

::r.Gjh.~tj:ef.mmdg:temma;tf.Qt~B:::::::j::\:::Itrr:::fi::I: :::m::::::;r:$.4;gQQjPQU:::: ::1:1:;:::1$.W.JttJ.\f.~~Q~:::: ::lmt::::m:$'4.~4.tt:n~Qu.;O\:::

$2,423,475 $4,777,831 $3,000,000 $2,81 8,694 :}:I;(l.gQ~"P~f

:mmQUmmmni.ti.$.1Jntimti:tmm:t:li:tltfn:tm::t:ttl::::t:lftt@ t::fF$.4.J.:~~t:a~~$.$.f :::;mtI41;~Q~q2Q:'::: :H::::::::::$.471Q.ZillQlt

FEDERAL COST

$32,970,71 1 $35,639,21 8 $38,300,566

STATE COST

LOCAL COST

$8,242,678 $8,909,805 $9,575, 142

..:1:.'/:$. ..::'.3l"...'..a::3...I: f. K'1.':':~{...f:J'::
$1 06,91 0,496
$26,727,624

...
DOT DISTRICT # 7

CONGo OIST.

4,5,6 ROC

ARC

.,

..

CAPITAL SCHEDULE FORMETROPOLITAN ATLANTA RAPID TRANSITAUTHORITY 5309

J):g~QB.'.Rr.U1N1Hlfftm:n;m;mHttlfimfft}ftnHlmffmmttmrffHtEMiP:~itii~{\f;ttmtfrty.HllffllJ tMHMEMiQ.gftltt t::f::m;mmA~ft@tt

FliJ.~B~ijn.ri~vBH:rmi:mM:rtHnmmm:r:tt:::r:HmM:$Tle!@rrI :litm1:Q73.Q1Mmti :::tit~::::7Q1:~lliHnt m::H:i1:P.tl~1~imiim ~i~lmHtt~rJI)mjtrttt

Line Structure Rehabilitation

$2,327,000 $2,443,000 $2,565,000 $7,335,000

Station Rehabilitation/Renovation

$1,164,000 $1 ,222,000 $1,283,000 $3,669,000

RailCar Rehabilitation/Retrofit Propulsion System

$9,308,000 $9,773,000 $10,262,000 $29,343,000

52 New Rail Cars

$8,000,000 $54,000,000 $29,500,000 $91 ,500,000

Ashby Station TOO

$1 ,400,000

$1 ,400,000

.~nhtB.~!~f.~fJiBtp'P.tmn!ijetmI:l::::::::JiII:J:}:r.;ng-lttmtJ''t}tt}m::H?lQZ@'Q~ :~:rtrtt:J::t:lg7~/.it: @lmt@lr7Qil@'1.:~ itftttf@llt@tmmr~@

Procurement of Clean Fuel Buses

$16,880,000 $1 1,500,000 $15,000,000 $43,380,000

amHN'W::m:ijrt~:ttr::t:t:ttttt::::l::m:::t:t:m:t(:::::::::tt::{$JiUMhlHt,:,'tt::::t:t:Nt1:QZ3.Ql: :m::t::m:t:::t::7Q1:~P.~ tmttmm:17QZ:U:1!

North Line Extension-Dunwoody to North Springs

$56,400,000 $14,500,000 $1 1,500,000 $82,400,000

and 28 rail Cars

1

Corridor Study: South Dekalb-Lindbergh Study

$803,000

$950,000

$0 $1 ,753,000

.1

Access to Jobs Planning Study

AUTH

ml~p.Q.g~lm.:q~mm:m::::t:tt:'~t:'&f:m::m:;:::::::::r:frr:::f::::::mm{J::Jtm:::fmmt~: ::f::::fi$.~~,-~~~gg :':J::::r:$,~li~~~'tmP. it::/;;$z:q~l~lP'~qQl).: :t::f$~~Q}Z~'::QD~

FEDERAL COST

$77,025,600 $75,510,400 $56,088,000 $208,624,000

1

{

STATE COST

$0

$0

$0

$0

LOCAL COST

$19,256,400 $18,877,600 $14,022,000 $52,1 56,000

1

DOT DiSTRICT# 7

CONGo DIST.

4,5,6 ROC

ARC

;>, <

::;":::.;0'....
t.~.,..<~

'1\ ..... <.... . "

I..

~j",

't.:,.' ~'%

~.

~.

.~..............""'".





-,j.

CAPITAL SCHEDULE FOR COBB COMMUNITY TRANSIT Section 5307

: t.1:.~$.PBIPT.!QN .'. $TtRW?:::::i\" .:~ ;~. ~. .. ...
Transit Center

.,"-

:

:

:: :

... ...

.......... :.'iY:Q.Q@::).:!@. @'.:::@.!'!'!'!gl9Pilf!'fffff @.:...f!:.mJfM4~g.!tff .ff :fffiWEQTWlllf!@@tt

:":":"":':':;;:":'

....
t{

:I7Q7~Q.l@.I.tt!:

tttt.:7IZIp.3.iltm:. :':tt?MPZg$.!ttl?'

$200,000

$300,000

$100,000

$600,000

CNG Fueled Support Vehicles

$25,000

$25,000

$25,000

$75,000

Bus Stop Improvements

$100,000

$100,000

$100,000

$300,000

Capital Cost of Leasing

$150,000

$40,000

$40,000

$230,000

Computer and Computer Related

$20,000

$20,000

$20,000

$60,000

Preventative Maintenance

$2,300,000

$2,660,000

$2,620,000

$7,580,000

Capital Projects: Bus Replacement

$1,600,000

$0

$640,000

$2,240,000

Capital Projects: Paratransit Vehicle Replacement

$0

$490,000

$560,000

$1,050,000

Fare Collection System

$100,000

$0

$0

$100,000

Capital Projects: ATMS and Related Equipment

$100,000

$100,000

$100,000

$300,000

Capital Projects: Paratransit Operations

$665,000

$783,000

$672,000

$2,120,000

Capital Projects Total

$5,260,000

$4,518,000

$4,877,000 $14,655,000

Transit Planning Program Education/Training Transit Planning Program Total

$300,000 $5,000
$305,000

$300,000 $5,000
$305,000

$300,000 $5,000
$305,000

$900,000 $15,000
$915,000

RRQYBATmPQ$%JtJJ':.:.m.'mmFm::m.:mm!JJ'.t::r:'!lttE:t::t.:I:tt!'.:m::t tftff$.$.~~P.Q9f .t'tff::$.4.~~~~lQ.Q.~t :t.ltf$.$.f1Ig~gP.P.f .:.tf!$.t;~7A~mm ..

FEDERAL COST

$4,452,000

$3,858,400

$4,145,600 $12,456,000

STATE COST

$556,500

$482,300

$51 8,200

$1 ,557,000

LOCAL COST

$556,500

$482,300

$518,200

$1 ,557,000

DOT DISTRICT n. 7

CONGo OIST.

6,7 ROC

ARC

,

;

'.

"

CAPITAL SCHEDULE FOR DOUGLAS COUNTY Section 5307

!i~i~~l:l~l:l;iir;l:l:ll:!:;:::!~!_ :IP:;stU1UemIINfI\:Wtm:f:trmm:\:::mt::::::::::l::Im:I::\:m::~m;:::m\m::::::It\t I)::::::t;::ttF:Pt=;:;QDIM;m:W :;mmmmBYiIJ:1.j\j;::;imjI:m
:ISOOJ..fMll::I':::tI?:g/:l11t::n::::::r:':::::t:t:Hj?}?:t::::::::::tt::::::::::::tI::::::'{::::t:::::?I,{::::: ::::::::::::::?1!:Q~$.'-Qi::::::tt:::::, :::;:}:::t:::*P7.~$~::J:}:J::t

Park and Ride Multimodal Terminal

$336 ,000

$275 ,000

$375,000

$986,000

City of Douglasville Mini-Bus Study

$0

$0

$0

$0

Van Purchase

$89 ,000

$85 ,000

$ 119 ,000

$293 ,000

Terminal Equipment

$0

$50, 000

$0

$50,000

Computerized Data Collection System

$0

$50,000

$0

$50, 000

:::::::::::r:::::::::::::I:$.4:g!nU:P'P: :,::g:a~us.p;rr~~$.lmI:::::'::':::I'::'::':"::"I':":::r:':::;

":::::::::; ..:..:.;:..:';,:;:.;;:..;...;...;................ :;;:::f
::':':':':':':':',':':' ::::::;:::::::::::::;:;:::::

::::':::::":':'::':r$4gq~~UP'

::'::::'::::::::::::=:::I::::::$4:$.4~tl.(l.:Q :::::::::r:::$.}Ia:t$~QQJ:::

FEDERAL COST

$340,000

$368,000

$395,200 $1,103,200

STA TE COST

$42,500

$46,000

$49,400

$137,900

LOCAL COST

$42 ,500

$46,000

$49,400

$137,900

DOT DISTRICT # 7

CON G 01 ST.
<

7 RDC

ARC

If'" v~..,.""
l;~' .......)'~'

~ .~

CAPITAL SCHEDULE FOR GWINNETT COUNTY Section 5307

!:::II:':'lll!lli;l~;lll:I~I:I:I:I:_ ;;:Q.gSQmlell1~IH\Wm::1Im:\mmi:i:\t\:;I\:m;n::!III;m:~lmmmW:I;mm:m mmm!!l;:1l3t::~U.fiIII~:f: ::mm\mtff:M:!Ult;;:I:!!l:mm
l$.llnM~#:::;j:l=:J:t:::'!!:ff:Jl:;U:=:::::I::M:::::tJmUJ:;tmU\MUrr:::lrr::::r:::::flfl ::::;::i;;::::::i1J:\l7~J~~lt=::=rr: :=::::::::::rilI1Q1lj:$.$!;:lftr::

CNG Local Buses and Related Buses

$7,731 ,500

$0

$0

$7,731,500

Diesel or CNG ADA Buses

$700,000

$0

$0

$700,000

Transit Enhancements, Slqnaqe

$77,700

$25,400

$27,200

$1 30,300

Capital Cost of Leaslnq

$195,363

$0

$0

$1 95,363

Preventive Maintenance

$2,31 8,831

$2,506,61 8

$2,693,440

$7,5 18,889

CNG Fueling Facility

$1 ,468,442

$1,468,442

::J~Jlg~$.gli::gg$m:J:t:J::;:t::::t:::::}}:tilt::;:::tr:}}It=ttt::::::r:::::: =t:jr$.m~~~~1M~~p:=:= =::}}::JI$.;.~;i:aa~tm):~m:: :;:::::::::rw$.a~fla:Q1p4u.:::: :rJ:J:$n::t~f.44!~4g~J:

FEDERAL COST

$9,993,469

$2,025,61 4

$2, 176,512 $14, 195,595

STATE COST

$1,249, 184

$253,202

$272,064

$1 ,774,449

LOCAL COST

-00

DOT DISTRICT # 7

$1,249, 184 CONGo DIST.

$253,202

$272,064

4,6, 11 ROC

$1 ,774,449 ARC

. . '.

,.

CAPITAL SCHEDULE FOR ELDERLY AND PERSONS WITH DISABILITIES ATLANTA AREA Section 5310

Cherokee

6V7023

$19,000

6V7025

$20,000

6V7026

$21,000

$60,000

Clavton

7V7035

$30,000

7V7041

$32,000

7V7047

$33,000

$95,000

Cobb

7V7036

$79,000

7V7042

$83,000

7V7048

$87,000

$249,000

Dekalb

7V7037

$120,000

7V7043

$127,000

7V7049

$133,000

$380,000

Douglas

7V7038

$13,000

7V7044

$14,000

7V7050

$15,000

$42,000

Fayette

3V7034

$13,000

3V7039

$14,000

3V7043

$15,000

$42,000

Fulton

7V7039

$164,000

7V7045

$172,000

7V7051

$181,000

$517,000

Gwinriett

1V7025

$53,000

1V7028

$55,000

1V7030

,$58,000

$166000

Henrv

3V7035

$15000

3V7040

$16000

3V7044

$17,000

$48,000

Rockdale

7V7040

$9,000

7V7046

$10,000

7V7052

$10,000

$29,000

Il.QTiAtlG.QS1ltt ImlMWllnllWmW@W :~mm::~mm$!it.$.,mQ.n mmllWll$$lS!\fmfi %:@lmM~f.J!),Ofi @mmll$.hfi:2IlJ.OP.

FEDERAL COST (BO%)

$412,000

$434,400

$456,000

$1,302,400

STATE FUNDS (20%)

$103,000

$108,600

$114,000

$325600

I

.,

. .:.-.. . -
oN

:'",...

!' . c;.. ;
I'

;" ~ , -.' '.No',
v-. .v

[~: ...,., ':.

;.

, ./ ...... ~.. ,

....,'.'.... ~~.:.:

I

.,,,,,

OPERATING ASStSTANCE SCHEDULE FOR NONURBANIZED AREA TRANSIT (Atlanta Area) Section 5311
QQWN,T=\tltt ~;nRMttr:::t:r:::::::::::?MMtrt?ttm:t::tth=ttWtttttHit::: =}mtl:tff:Yipgt:t::t:t ,=::?fl:t::J.iyrq,.:;::;::;::;:tt t::t::%?\Jf:X$i..?ittttt ti:tt:;:{[QJtA.Pittlt

Cherokee 689004

$71,400

71 ,400

689005

$75,200

75,200

689006

$79,200

79,200

Henry

389004

$57,953

57,953

389005

$61 ,438

61 ,438

389006

$63,895

63,895

WQ1f.tWUQ$T.${\'}=tt:::lr:::=lt:::::t::::ti:f:t:fdimr::fI::mt=::::::t;:1::::=:mf:=:::::=:=t:1F: :tttf::=:::::=ilg~;:a?i:m f::::==::fn:::=:itl~~~~t:: :t:=::::::t:=:::=:=:=il4Ii~~:~.:PQ~~~':'

FEDERAL COST (50%)

$64,677

$68,319

$71,548

204,543

LOCAL FUNDS (50%)

$64,677

$68,319

$71,548

$204,543

Cherokee

CAPITAL SCHEDULE FOR NONURBANIZED AREA TRANSIT (Atlanta Area)

Section 5311

t:=ttttf;t:::Q?t:=t}t=:~

STIP # .

6C9004

6C9005

9C9006

2 Minibuses, 1 with Lift

$82,000

$82,000

2 Shuttle Buses

$90,000

$90,000

Henry

STIP # Modified Van Modified Van, Minibus with lift Shuttle Bus

3C9004 $29,000

3C9005 $71 ,000

3C9006 $42,000

29,000 71,000 42,000

[[fPIAIPqp.Ttmm:=:=f:t::::tt::t::t=f:ttt::::=f:t:r:=::f=lJt:::::ffrtt:tt::::r::fIr:: .:=r::::::rU:1:1}QQPrfr:~

FEDERAL COST (80%)

88,800

STATE FUNDS (1 0%)

11,100

LOCAL FUNDS (1 0%)

11,100

f.l~lU~qq::::::::=:::::: :f::f::f:~ .~HU!Qt::ttt ftrr:..:?14iQJJ.Qt=::r::

128,800

~ 33,600

251,200

$16,100

$4,200

'$31 ,400

$16,100

$4,200

$31 ,400

\, .

~'1.i' -

I~t

Augusta

~.~ '1
I~

I

I

I

-f--'j_.-
~-

:'
21

..;--.::":--
""' ,"."~

10." . . ."

r'rr-' ,"..... \.. ."

~. " - .... "-

to-

,-

!;./"." "",",:
>

tk'o"O.o.,

..( ~~.,.'J:t ~

CAPITAL SCHEDULE FOR AUGUSTA PUBLIC TRANSIT Section 5307

:!:1~1:!

:!:!1!1!:

:i~lW:~1:1!);!

!:!:!

:!:)

\:\:::I~~~::\::~\:\::~:~tM:;b.;F~:::::}':~:::~I~:
:I1'E::\::::2QiQ2;J:I:::'\:::\::\:1

:i\1:\11~1;!!!!!1:!:!i;i~;:ii1!\!:!!!!!!!!!;_

Transit Vehicles

..

$850,000

$0

$1,200,000

$2,050,000

Capital Maintenance Items

$50,000

$50,000

$50,000

$150,000

Preventive Maintenance

$730,000

$0

$0

$730,000

ADA Expenses

$ 154,000

$1 66,000

$1 78,000

$498,000

Fareboxes

$330,000

$0

$0

$330,000

Transit Systems Analvsis

$50,000

$0

$0

$50,000

Contract Contlnqencles

$1 50,000

$1 0,800

$71 ,400

$232,200

Transit Vehicles to be flexed from 023

IV IV

$400,000 FY 00

e8.QU:._lt.(),sm:::fII:::::t:II,)'IIIt:::::::m~t:lt;:::!:III!r:::::::II,rmtEI ttit::m:$I~a7H:UQnnt Jirt;tr:I::::$.!2;~s.tJ.(n :t\Ilm:"J.ils.g~4nOI ttrIt'$J.:'n4u.~2llu.t

FEDERAL COST

$1,851 ,200

$1 81,440

$1 ,1 99,520

$3,232, 160

STATE COST

$231,400

$22,680

$1 49,940

$404,020

LOCAL COST

$231 ,400

$22,680

$149,940

$404,020

DOT DISTRICT # 2

CONGo DIST.

10 ROC

CSR

..

CAPITAL SCHEDULE IN AUGUSTA FOR ELDERLY AND DISABLED Section 5310
==~ Imf.HWMII:::::;:i;::l::l;;::;::;fIff:::::::::l::::::::;::m:::::::::::':':::I:t:::::;':;;::::'::IIIIIIIIII:I@ :':I:::;:'::t:gYitPg4j:::;::;f:'N ::::::::::::::':~Mto.g9nm;E:;::
:~:meBAm'N:GfRefl'QP:::t:::::::"'r::::::::rrrrrr:r:mtt:;:;;,::;;:;,::;::::r:;II ;rrr:::::::::::;SNt~Q=:::'::::'::III; :=:::rr::':::F:~m)1:::::::;:::;:::::;';=:::':

Purchase of Service

$48,952

$48I 952

Purchase of Service

-

$51,399

$51,399

Purchase of Service

$53,969

$53I 969

eBQUeQ1NPQS:T;::::,;r,:r':r';,:r'Im:;,:r:Im;:};:Irr:ttt:mtttrt::,::mtt r:;:::;:tf'::;'l::::rs.:4.a~~$.~: :'t::::tt'r::ftI$.$.1'~$.$$: :':';:':f:;::I:t:m::::!$$.~i~Q(l~ rt':tt;;tt::$j:$.4:~:3z.Q

FEDERAL COST

$39,162

$41,119

$43,175

$123I 456

STATE COST

$9I 790

$10,280

$10,794

$30,864

IV W

DOT DISTRICT # 2

CONG DIS

10 RDC

CS R

ww
.... t-.J ~.

Shuttle BuslMlnlBus with Lift, Two MobileRadios
Mini-Bus with Lift and Mobile Radio

$38.500

$38,500

FEDERAL COST STATE COST LOCAL COST

DOT DISTRICT# 2

CONG.OIST.

10 ROC

OPERATING ASSISTANCE FOR NONURBANIZED AREA TRANSIT (Richmond County) Section 5311

CSR

FEDERAL COST LOCALCOST
DOTDISTRICT# 2

$109,800

$115,300

$121,065

$109,800 $115,300 $121,065

CONG.OIST.

10 ROC

CSR

Brunswick
r f,I.".
U
25

,;.,

. ' . :~.< .~

.- ..
..)

,.... ,._.-

\,

t.'

, ," . v . ,....

... .... . . 1

CAPITAL SCHEDULE FOR BRUNSWICK MPO
Section 5307

:~::gg$.e.8JeJ:ltlN.::::t~:I::I:::~:::~:::::II:::i:::tl?:?::\:tMtI::I:'I~ ii:tt:\::lfl\y.UOXmXJ :1:ttt~.in.I.Mit:::\i itl@~FNi:~Q~ill1~ @}:MtQTfAUJnw
r$.tn~ti'H:ImrrriiitJimiiiiJJJ:i:iiiii:iiiiiii:iiIiiiJiii':::::iJi'Jiiiii:i:ii:iIII:JJJJJr i:tiln~Qs.ntf.~Hli:iiii imi:I$.Qs.nn:~i::itiI: iiiilf$.QSnlliJIt r!{~rftttttttj~~frrrt;

Facility Leasing Three 30' Transit buses Office Equipment Two Vans
Capital Maintenance
Contingency

$0

$30,000

$30,000

$60,000

$0 $150,000 $150,000 $300,000

$0

$20,000

$0

$20,000

$0

$40,000

$40,000

$80, 000

$0

$ 10,000

$ 10,000

$20,000

$0

$ 15,000

$15,000

$30, 000

?Ra.QQ~Pm:':Q.~Sitti::ii:ii\if:i::ii:iii:"i:i:::i::!ii::i::i)::i:i'::Ji\i:}i,!:::::II} i)i::i:i:)miff'::::::i::::fi)iI:i:$Qir Jiii:J:@$g~$.~Q;Q:q::i:i :ii:i:r':i:i::i$g4$.~lnIP::::' ]fff$$jiQ~t.U~q,t

FE0 ERAL COST

$0 $2 12,000 $196,000 $408,000

LOCAL COST

$0

$26,500

$24,500

$5 1,000

STATE COST

$0

$26 ,500

$24,500

$5 1 ,000

DOT DISTRICT # 5

CONGo 0 IS.

1 ROC

CG

I, 'J ,.

OPERATING ASSISTANCE SCHEDULE FOR BRUNSWICK MPO
Section 5307
1::~e~Jl#.m;~~.;~~BI_lli!j::ilillr~~~i::!I:l;:!Jj :;{;:f:\$.,JfmlQIMlmlm:@$flIQQIt;lll@ tIl\~~tffrIl\]ftl1J 1::::1:I:1IM:::ljI:lmiMl::::::::I::MI&lI::D.f.l::lM::: lWmDTAC:::::::::::r

FY 2000

$0

$0

FY 200 1

$404,998

$404,998

FY 2002

$464,464 $464,464

IRSIU-:e.e.1@It.lSlm::ttIl1ttll:llltIIIIfii\:::I::::\f:1:::::f:{@f\f:mfl1:Itii :;:::;:;lfk$4l~4.~S.l.j: MttI:$4fi4i4~4: ;m@;I:$.1$.fis.~;41~

FEDERAL COST

$0 $339,990 $339,990 $679, 980

LOCAL COST

$0

$65,008 $124,474 $ 189 ,482

DOT DISTRICT # 5

CONG DIS

1 ROC

CG

.. ...- r'~'.' --,-:,
~..:.- ,:..:

' ..

N 00

,.......~,' A" "

r..' .'

CAPITAL CHEDULE IN BRUNSWICK FOR ELDERLY AND DISABLED Section 5310

Purchase of Service Purchase of Service Purchase of Service
DOT DISTRICT # 5

$20,710

$21,746

$22,833

$20,710 $21,746 $22,833

$4,142 CONGo DIS.

$4,349

$4,567$13,058

1 ROC

CG

Columbus
29

1.."..-...;..-.;;-..,......\-..-..~..

_ ,
~

.....

..

r," "-"",.
1". '.....

". ........."':.
~,

Ir''''~'v.,"

i..

.~

..... : .. '-,

r.

.?~

r.-_..'.',._ .... ~.

CAPITAL SCHEDULE FOR COLUMBUS TRANSIT SYSTEM
Section 5307

D.e$'9t~nlfrfiff:tji:@:::tfrfifmffl:ttt~;iffm@i)ilfmifm:m:ff~~)f ~it;it~W:t~~o.~:~):::::~f'~: ~:~:,,::~;:~:t~:fWJ)fm~~i:~: '~;fml~':!Y~~I%Df WiN:mTAtf:)::::;: $mIR~IMmm\\:tr~t'ttm~'lt':~~f~~~~:ttrWm:tKm:~tt'~fmrm~~::~:~::n\:tf't:Wf'tt /l\tllmou:tit'M tt~tr~D~u:~s.Mm: ::Mt':aD2.ot),1,lWn ~~t~~~~~t@tlt~tttttt

Tire Leasing (Tires, Tubes, Materials)

$65,415

$60,000

$61,972

$187,387

EnQine Rebuild Proqram (15)

$50,000

$70,000

$55,125

$175,125

Transmission Rebuild Program (18)

$48,150

$55,000

$53,085

$156,235

Transit Coaches (5)

$235,000

$502,400

$508,200

$1,245,600

Perventive Maintenance

$263,000

$280,000

$289,958

$832,958

AC RecyclinQ Unit

$7,200

$0

$0

$7,200

Brake Durm Removal Cart

$1,400

$0

$0

$1,400

Engine Crane

$1,500

$0

$0

$1,500

Jump Starter

$2,000

$0

$0

$2,000

Rempacement Saden

$16,500

$0

$0

$16,500

Utility Cart

$6,000

$0

$0

$6,000

Bus Stop Signs & Bus Stop Poles (300 signs & 100 poles)

$9,500

$8,000

$0

$17,500

800 MhZ Radio System

$95,000

$0

$0

$95,000

Mini Buses

$100,000

$180,000

$50,000

$330,000

Support Van

$0

$27,000

$0

$27,000

Scheduling Software for Demand Response

$0

$10,000

$0

$10,000

ow

Heater for Lower Shop Update Bus Wash System

$0

$25,000

$0

$75,000

$0

$25,000

$0

$75,000

Wheel Chair Tie Downs

$2,520

$2,800

$0

$5,320

Transport Center Roof Underside

$0

$100,000

$0

$100,000

Office Furnishlnqs

$8,234

$0

$0

$8,234

Safety Equipment (CPR Training Equipment)

$3,500

$0

$0

$3,500

Computer and Accessories

$5,000

$0

$0

$5,000

Tralninq Room Partition

$3,900

$0

$0

$3,900

Miscellanous Capital and Safety

$0

$10,000

$0

$10,000

Lawn Eauipment

$2,120

$0

$0

$2,120

Change Machine

$2,500

$0

$0

$2,500

Contract Continaencles (5%)

$46,422

$70,260

$50,917

$167,599

Administration (2%)

$18,569

$28,104

$20,367

$67,040

Total Planning Costs

-

$114,637

$182,506

$182,506

$479,649

~eaPJ..t1.$r@ttrt;nwtttt@:ttt;K;lt:t:t;tt{Wn;t;Ml%W ;WWnl1~o.~:1~1\ t:tt$.nJi~'tQt tWl#1~a~a~,~t tM;$4~qe.$;2lfr'

FEDERAL COST

$886,454

$1,348,856

$1,017,704

$3,253,014

STATE COST

$110,807

$168,607

$127,213

$406,627

LOCAL COST

$110,807

$168,607

$127,213

$406,627

DOTDISTRICT # 3

CONGo DIST.

2,3 RDC

LC

"

OPERATING ASSISTANCE SCHEDULE COLUMBUS TRANSIT SYSTEM (METRA)
Section 5307

IIBfMJ.lI:m::l!'::JfliiMl!l!liM:iiMH:I::fIMm:: !Mf::~:::iIa:Q~IQj::!:i:~i!iiii :ii:::::i't~:::f:alaln$miWiW tmmmaI2IDlif:ii:IN: t~III~t~~~tmIIr~ItI~~))~~~rft~lj
fllBailNI;:e;e.B.:I~lj::i:~:!::::i~:i:: i::i!m:~::i:~::i:!~:~J.i~)i]l.li:!~!:Il::i:!i:!:! ~:~i:::!:!:I~t::t:!:~'IYi:!ftl!iiiii:t:!d:ii! !t:itt:li~!:::EIiKgl.tI!mt:!*1i ~:m:!'!'!i@;llmlJ.i:!i!:!:::!~:~!:::i:i:::

FY 2000

$2,221 ,373

$2,22 1,373

FY 2001

-

FY 2002

$0.00

$0

$0.00

$0

~::illgIII!lmI11i::!!m@m::::t)~~t~:~ i!:~!:l!!:::~II;I~I:'~aza.!~:! ~::i!mU::i:!:~:::::::~It::UM;!!($g;IQ: :;!M!!li!!!!::::!!::M:!!::!!!$.I~IQ:

FEDERAL COST

$7,629

$0.00

$0.00

LOCAL COST

$2,2 13,744

$0.00

$0.00

.

DOT DISTRICT #

3 CONGo DISTRICl1

2,3

$2,22 1,373 $7,629
$2,2 13,744
ROC: LC

1'..;..'..:-;'".

'\ .:;;
-\'

I: . "~i . ..","

CAPITAL SCHEDULE FOR COLUMBUS TRANSIT SYSTEM

Section 5309

==~ :'::S1.1IP;JtlfJlmt:m::fl':fWrr:lfrmm::j:;:I:@jff:j:t::::::::jn:::I:W::;:::::t':m:j:j:;:j:t;;j:' :F:i\NlI4~~$.:::::m:;::rm m::;::I:::::::~Q4P~gtr:::::;;j::: :tnn::llEr,;::OP:IIII1J :mnnE'J:::iSY::U1:::r:lnnn
DESCRIPTION

Facilities Modification

150,000

150,000

50,000

350,000

Thirty Foot Transit Coaches

240,000

240,000

240,000

720,000

Paratransit Vehicles

69,000

69,000

69,000

207,000

15 Passenger Vans (Welfare to Work)

235,000

235,000

235,000

705,000

Fareboxes

5,000

5,000

5,000

15,000

Bus Shelters

21 ,000

21 ,000

21 ,000

63,000

Bus Benches

5,000

5,000

5,000

15,000

2-way Radios

25,000

25,000

25,000

75,000

::N?8qqiGlli~Q$TrI:f:IImff;ffffEItf:::::f::f'::rr:::r::f::m: :Itf::;I::I:ftZ$.Q~P:PQf ;::;:::f:;::f;::::fllio;~qO:o):::: I::;::I:::::::::;::lJ$.$.n~QQ:QI :I::I:::ff:I2~1:em:QPf

FEDERAL COST

600,000

600,000

520,000

1,720,000

LOCAL COST

w
N

STATE COST

75,000 75,000

75,000 75,000

65,000 65,000

215,000 21 5,000

DOT DISTRICT # 5

CONGo DIS.

2,3 RDC

LC

I

,.



CAPITAL SCHEDULE IN COLUMBUS FOR ELQERLY AN0 DISABLE0
Section 5310

====- 1$'ngtf.:~:t:l:l:m~:::itmmmmm::r::mrr;:mm:m:::lmmmm::::rml{II::::rtI~I ;r::r:::::l:~M1;q~~:I:lmr:m f:::rtt~yzpa~;}:::::r:}:~
I:Qe.$GBJRmlQriH?:fjr:jrr?:IIJ?IM:jl:lJ::r:::JH::::::::rr:::jrj::::ffII:::: :fIIf:rrJPl:3UKIIfII: Ir::::::jr::::::::f:Pl::lQ1::MrIHIHm~

Purchase of Service

$48,952

$48I 952

Purchase of Service

$51,399

$51,399

Purchase of Service

$53,969

$53I 969

:::IRBQUimrdIQ$1WlJH::fIlIlIf:::r:::::rlmM'ttIit:::::j:::j:j:fII:: :::::jI::l::i1f:::::lU4~Q1:3.I:: :::::::::j::rrr:::11:$.4~J276!r f11jr::Irrrl$4$.:~~nnn: ::njH::::H:j):::::::$1.:aa~s,a,,::::

FEDERAL COST

$35,258

$37,021

$38,872

$111,151

STATE COST

$8,815

$9,255

$9,718

$27,788

ww

DOT DISTRICT # 3

C0 NG DIS

2,3 RDC

LC

Macon
::rf
~;'::l1i'
:U.
'-.
.'~ ,
34

.. ,~~ .,.,.,. ........
4 ,.j,""

,.

' ....')

:- ' ..'

:c......:,:'.

.... .... .,.~

_

':.~

CAPITAL SCHEDULE FOR MACON-BIBB COUNTY TRANSIT AUTHORITY Section 5307

: ::::3 :\:;~:'~~':~~~~i~:::'~\;~;li~~~l'_ \:::;::j::::::r::Jff:Y;\Q'j1\::::=:::::tt; :J;l.~fOftlnQNt::::::r:r: t::;:::tf:*::~(f::tj:tt ;':.::.: : .:{.~:.;.:.:.-..::'.>.'..\.f....:.~.;.<..:.:.;:~.:;.?..?.:::

.'-':::':".:".:;:-:.;.;.;.:-:';':':';';.:.'
..-:::::-::.:~::::\:::::::}::::::::

s.mffMtI.":!:{:(=(,!=.:= ..... '.-.

::c: .:,.::;:

03 !)()~:::::::n :::::=:::=::::3.aa1:(~2:::W:mf::::

Purchase nine 30 ft transit buses

$690,000

$690,000

$690,000 .$2,070,000

Purchase video camera and equipment

$1 ,100

$0

$0

$1 ,100

Purchase thirty fare boxes

$174,000

$0

$0

$174,000

Purchase Bus Washer

$0

$150,000

$0

$150,000

Replacement of Paint Shop

$0

$70,000

$70,000

$140,000

Purchase of one Administrative Vehicle

$0

$0

$25,000

$25,000

Purchase of two paratransit vans

$34,000

$0

$35,000

$69,000

Purchase two trolleys

$300,000

$0

$0

$300,000

Purchase three computers and software

$7,500

$0

$0

$7,500

Paint Transit Authority Office

$0

$0

$35,000

$35,000

Resurface Parking lot

$0

$0

$60,000

$60,000

Transit Route Study between Macon & WR

$50,000

$0

$0

$50,000

W VI

:e;IQa.9'lt:::~I$mII::::m:mrn::::::?:tt:I::{:itint!::::W:::t::::=:=:::=:mI::=::IIW ::w:t=n:$~:~g~$~9:~O;:: H:::r!}I=::=::~nf.J~J)QJ: :::l:::!::mt::t$."~:S~QQUt ::::::!:::::::t::$afo.lf,J~ml:i

FEDERAL COST

$0

$0

$0

$0

STATE COST

$628,300

$455,000

$457,500

$1,540,800

LOCAL COST

$628,300

$455,000

$457,500

$1 ,540,800

DOT DISTRICT # 3

CONGo DIST.

8 ROC

MG



OPERATING ASSISTANCE SCHEDULE FOR MACON-BIBB COUNTY TRANSIT AUTHORITY
SECTION 5307
~~ ::\\$.,nR\::#,i:)IJM1\\IJ:\:;\::Jmrm:::::\:m\:\::iriffi:i::JJ:mfI:::mrtrmmm::::::ti:rmJ iJ:rm:~p~$p~J::::I::f: ::::'i:::::::r:IaI31:0Iimi@\
iQRe:B:ATING::JleiUQP:::::m:::'W::::m://://::,m:::::::/:':,m:W//:::/:m::: :::/::m:/':FY::i()P:m:m::::::::m:: ':::m:::::::/JiMJ1:1j'j/;::::,:r::

(07/01/99 -06/30/99)

$1I 701,680

$1I 701,680

(07/0 1/00- 06/30/01)

$ 1,735 ,7 17

$1,735,717

(07/01/01 - 06/30/02)

$1I 770 ,430

$ 1,770 ,430

te.laUEQ11:aQSrn::::::m:j::::I':jtIm:I:::::r:::::::I:;:::::j::r:j::'j:Ij/:::::::I:::m::It ~lIj :m$1!~Zf:1j~~~n:w rt;::::::$(UZ35.iZlZr ::IIjr:j::::$1lil:1!Q~4.3.PI ;Im:::jt'$a~lQl1iJ:21@:

FEDERAL COST

$99 ,190

$376 I 470

$372 ,470

$848, 130

LOCAL COS T

$1,602 ,490

$ 1,359 ,247

$1,397, 960

$4, 359 ,697

DOT DISTRICT # 3

CON G 0 1ST.

8 RDC

MG

C-.-.'-.~

i"''"':

. ~,

'

~

.' :

.. .,. , ~

'";

,~"'" ' ....:.;.

. ,...'....'.':., '

;..: ~

...:.: -.-,.' .--.;:.

CAPITAL SCHEDULE FOR MACON-BIBB COUNTY TRANSIT AUTHORITY SECTION 5309

r::):;):ap.aliQ:$:::f:'r/:ff:r:::eQ;'On1tf;?:I:hIt?:t:3.P~l::o:a::::IIII gg$t'{ImmtP:N:i::::::::i:It:::i:f:i:::::I::I:E:i::::::::::?:i::::::::i:::::'i:::f:::::::::fi:::::::.f;i::U.Uii::I?:i::::):E:iii:ii:i::i::::fff-;::~~:i:::::I:ii::}::::: iiii:III::le~~N~~iiI::::f:i::i:ii:::::fii::?::i:ttf=)m~p.::}}?:i:i:i:

Purchase .eleven 30 ft transit buses

$920,000

$920,000

$805,000

$2,645,000

e:f{()~e.m:':~:~$m::II)If%:II:::::I::::::::):J:):~')IJ))iff:g:::::::):):)::f,:::,:::ff::::::}}:):::::;:::J$$.gU;~qQ):::::)::J:)J}J:J:i~O~~~nlf ::I:gm::::::::t$~:Q:$;~qQQJ :%:::::::::::'::~~9.4~iOg,Q:)::

FEDERAL COST

$736,000

$736,000

$644,000

$2,116,000

STATE COST

$92,000

$92,000

. $80,500

. $264,500

LOCAL COST

$92,000

$92,000

$80,500

$264,500

DOT DISTRICT # 3

CONG.DIST.

8 ROC

MG

.

-.I"

10'

'. "

:$.ffit.J?Utt::t::;:j:I:::H::::;::,:.'
:Pl;SPBIRTIQN}" :

CAPITAL SCH EDULE IN MACON FO R ELDERLY AN 0 DISABLED

:, ',:, ,:,', ,,:,
: .,

Section 5310
==~ : ',:: :,'::::AVZQ~1IrjI: :' :I:IaVit~a,6:mmrmM ' . ;::FJYQQ::f:!:/: ',' :!/::I::!F:)1]1,1:IIII::i:H::

Purch ase of Service

$47,069

$47,069

Purchase of Service

$49,422

$49,422

Purchase of Service

$5 1,893

$5 1,893

ie:RQu.:iomi;G:asmll1IIII::JI:::::r::'IIHmnllfnrlIilI::IIt:;l ::r::::::::::::::::/l:;;::;:$.4l1iQAI t::':::::i:II::::i::::l::::::$.4.$.~fl22 IJ1:::':::':l'III::J.5.1lIQtl ::J:::::I:J::l:II:$.1.:4.:a.~a8.:4

FEDERAL COST

$37, 655

$39,538

$4 1,514

$ 118,707

STATE COST

$9,414

$9,884

$ 10,379

$29,677

w

00

DOT DISTRICT # 3

CONGo D1ST.

8 RDC

MG

:';, ....


Rome
39

,

'~

. CAPITAL SCHEDULE FOR ROME TRANSIT DEPARTMENT Section 5307

\R:D:QRIBlf.l:fiEW:m:I:\\\i:i:mUi:m;\UM@MIMm:U::m;;:I\Ii: I\HI:HFJti\ggI@\\t :ImgeMi:Qji:IMU\ WMi:\\Rgg:!\&\%\ :W:tImQitlllII::: 'SmJB;:\#::::\:j::::\;:;:::;:::m:j:::;:'\\I:;m:;::I\::;:::::::mmm:::::::;::I:::;:::;:::mm:tj::::I'II:;:;IIIIIIm::::I :;::::::::;::::Q;PQg,gi1II:I:::: \::::::::mQg:~3p.;m:::::;I ;I\;1MQg:~g,3311:I:: ~~tt~~~IIIIIIIIII~~~t1jj~t

One 40 ft Transit Coach with Lift

$125,000

$0

$0_ $125,000

Two 40 ft. Transit Coaches with Lifts

$0 $260,000

$0 $260,000

One 26/30 ft. Transit Coach with Lift

$0 $180,000

$0 $180,000

Three 26/30 ft. Transit Coaches with lifts

$0

$0 $555,000 $555,000

One 16 Passenger Administrative Van

$0

$28,000

$0

$28,000

Maintenance Equipment and Tools

$9,500

$6,000

$6,000

$21 ,500

Maintenance Items

$35,000

$30,000

$30,000

$95,000

:fM;~~Y:e.QlmQg$.J.r:\::;::::;:rrr\:::;\I\It::\:\;r\:\m;:\:t\:::\;:i\;\I::\:\;:\\i\:::\;\;\;r\:rI;:::\r':\:$1;~;~OA:::: :;:i\i,::r\;$~04id~O:q@ I;I;r\$~~ll!gA\;:; "'n$1lg'4.j~OAr

FEDERAL COST

$135,600 $403,200 $472,800 $1,01-1,600

STATE COST

$16,950

$50,400

$59,1 00 $126,450

LOCAL COST

$16,950

$50,400

$59,1 00 $126,450

DOT DISTRICT # 6

CONGo DIST.

7 ROC

CV

1#." ......

t' -

.. ~

r' .~- .. , r;--4 -. v_

OPERATING ASSISTANCE SCHEDULE FOR ROME TRANSIT DEPARTMENT
Section 5307
~~~:::: =~- ::::::::::::::~m~ga:1IIm:: :::::::::::EM:Qj:,::::::::::::

(01/0 1/00 - 12/3 1/00)

$ 1,187,000

$ 1,187 ,000

(01/0 1/0 1 - 12/3 1/0 1)

$ 1,247, 000

$ 1,247, 000

(01/0 1/02 - 12/3 1/02)

$ 1,3 10,000 $ 1,3 10,000

tlllY.'ili::IQql1::::::::j:j:jl:j::::::t:::::j:::::::::::::j:t:::j:::jfIj::::1I:t):m:);: II:::,m~:lx~:qDI:::; I:mj::~jJ.gll~IQI:j:: ;::1)1;1~:I~lgl::::: ::::$::I~ZI.Ii.P',gl:::::

FEDERAL COST

$ 346, 60 1 $ 346, 60 1 $ 346,601 $ 1,039, 803

LOCAL COST

$ 840, 399 $ 900,399 $ 963, 399 $ 2,704, 197

DOT DISTRICT # 6

CONG DIS1

7 RDC

CV

"

CAPITAL SCHEDULE FORROME TRANSIT DEPARTMENT Section 5309

:l~$.iJJJr.mllM@@mml@m:II:;IIIIItm&II@mm{E::I::::I::~mm:::f~ :mt:H~ft:gg.:mWi II1Ift:gg~lj!=i:1 !:~~]t:~~jJ$.;g:,q~lm:m ~~~fl~~tl~~l@~l~IrlI~~~
:rp$.:~aJamIQN::ir:::~:,:r::rrt:::::II:::::~I:tr:I:::I::r:::::r:~::::,:::~::::::::m:::: :~:i:::::::::I]fif(:::Qq:::ii::m~r ::::::trr:$M;i~1M::I::r :::~:::::::::::::$M::Qg;:::Itri I:;::::::::mgl.~JMm::::::

Two 40 foot Transit Coaches with Lifts

$250,000

$0

$0 $250,000

Four 26/30 ft Transit Coaches with Lifts

$0 $720,000

$0 $720,000

Four 26/30 ft. Transit Coaches with Lifts

$0

$0 $740,000 $740,000

Two mini Buses with Lifts (Paratransit)

$150,000

$0

$0 $150,000

One 16 Passenger Administrative Van

$0

$28,000

$0 $28,000

Maintenance Tools and Equipment

$9,500

$6,000

$6,000

$21 ,500

Maintenance Items

$35,000

$30,000

$30,000

$95,000

:~::et:'Uilu.4:Y1rRQ\$!m::::::::::Ir:::::::II:::::::I:::::~@rr:::::::I~::~~:::::::::::::r:r:l@Ill::$.14.4J$.Q~I ::::rIr:$.l:Al:fQQ~:l r:m::::::$.l:rt;~fgg~I ::I:$.g~~nl.l:f$.Q~I

FEDERAL COST

$355,600 $627,200 $620,800 $1,603,600

LOCAL COST

$44,450

$78,400

$77,600 $200,450

STATE COST

$44,450

$78,400

$77,600 $200,450

DOT DISTRICT # 6

CONGo DIST.

7 RDC

CV

1'.

-..

I

I

Savannah

I

I

I

I

I

I

I

-I

I

I.:
i

I

I.

,-,

t
M1
44


t-

,_ .

~,

'.~

:.'; .. '

CAPITAL SCHEDULE FOR CHATHAM AREA TRANSIT AUTHORITY
Section 5307

Capital Maintenance Items Replace Fare Collection System Office Equipment and Furniture Facility Modification and Improvement On-Board Security Camera System Service/Support Vehicles Passenger Amenities Maintenance Tools and Equipment

l:!:;l;l'l\lil:l

!l=il~

:il:!l!:lj!:!l!

!

:

!

ttI::~:::~::tje:\~HI1It@it:t
;~:r::~:::JU:)$Q33:?:tttm

:l:l;!!~;!::::;!i~;::':'ll:!:l:!!l!i;ll_

$0

$700,000

$800,000

$1,500,000

$0

$0

$0

$0

$0

$80,000

$0

$80,000

$0

$80,000

$250,000

$330,000

$0

$0

$0

$0

$2O,000

$20,000

$20,000

$60,000

$100,000

$80,000

$0

$180,000

$0

$0

$50,000

$50,000

e8Q4E!JflrC~$:p:::I:tt~I:::t::t:::::~r: : !!~{ifIft!~i!rttrffrrj~~mm~i mI::::::::::I$.1:$.n.~Opu.:j:: ttr:t:II:$~6aHnlD.J: :ttJ:(::$1]1.:~nmu.~n: ::::tm::::::::::$~~~,ttp::attpt

FEDERAL COST

$96,000

$768,000

$896,000

$1 ,760,000

STATE COST

$12,000

$96,000

$1 12,000

$220,000

LOCAL COST

$12,000

$96,000

$1 12,000

$220,000

DOT DISTRICT # 5

CONGo OIST.

1 ROC

CG

.' " .';.

'.

'.

.

CAPITAL SCHEDULE FOR CHATHAM AREA TRANSIT AUTHORITY Section 5307

:l:lil.l1:1~!!:;:=;:'=l!:;:!ill!l':!1_ :ggQBIRliJQ.N.;;gWm::fltnflmgt\fi}t:tt\tm:J~i:;I\JI@ffi:'lmtnmttli@Q.Qi;}:lff? llfWi:HIiYIO,tli:JIII:;
S.mtflUl.ff:mfifiI1Ifitft:ft:iIIIi:::r::i:fi:::MitIftttt:it:it:i:imit::i:~tt::tttt :tIIri\$.rP.$02StttI::i t:t:t:::::$.P$.03a:ttII::::

Capital Maintenance Items

$0

$700,000

$800,POO $1,500,000

Replace Fare Collection System

$0

$0

$0

$0

Office Equipment and Furniture

$0

$80,000

$0

$80,000

Facility Modification and Improvement

$0

$80,000

$250,000

$330,000

On-Board Security Camera System

$0

$0

$0

$0

Service/Support Vehicles

$20,000

$20,000

$20,000

$60,00'0

Passenger Amenities

$100,000

$80,000

$0

$180,000

Maintenance Tools and EQuipment

$0

$0

$50,000

$50,000

:RsaU'IWiIQS1NMillUiifnmmiWmil:M@1m:tM@f:;;Nl iiMmmI$J.:lll,-lQlii .miMl:il;gllt::JtOfU :,:;mn;;$ti,:tQ4UIII lftmmU~IW~mmJ

FEDERAL COST

$96,000

$768,000

$896,000 $1,760,000

STATE COST

$12,000

$96,000

$1 12,000

$220,000

LOCAL COST

$12,000

$96,000

$1 12,000

$220,000

DOT DISTRICT # 5

CONGo DIST.

1 RDC

CG

...... ,.~.~ ..~ ,

,
"...,.",.

y........"-,.!.'
.;;- . . )

f'I".J.--,.~.~~ 'I.,t ,,:

(N .... ,.:......\)
\-;'.. ;: i

1.:.-:,,'.:.., t: .'

OPERATING ASSISTANCE SCHEDULE FOR CHATHAM AREA TRANSIT AUTHORITY Section 5307

:";: ::, ,;)

;Qp;S.BAm'NGeeR'Op::::,:. ......:

:::,: .

(01/01 /00 - 12/31/00)

- (01/01/01 12/31/01)

"u:::r:S()50a~:::ii:i:'::;m:::;s.Qs.nU::fffm: :mm::HiiQSlm$m;:mff mf~mf~t~~tt~r\~~~~til1~\titlJ '::t;::;.:FYUQ;;::/ffJ :',:::::It:::;::f!'Y.M),lttiJlli' :;I;:::::;:;WifiYdI2it:JiJ:;:;:;:; ;::J/ttmfQIII:g;:;i:;i:;:;:;'

$7,882,000

$7,882,000

$8, 197,000

$8, 197,000

(01/01/02 - 12/31/02)

$8,442,91 0 $8,442,91 0

ermUSITIQQS1JMlttttlT;;ml;;;;;;il;;;;:;;;;;m;;;:;:;:::;:;:;'r;l@@;;;m@; {n;;1;;;$.Z11.1.1~no..Q) r;Wllml$8ilaZ;IQll :;;;;;:;:m;;1l.m42.~$J.:1 ;;;t;;1:$O~i2U"jt:o.

FEDERAL COST

$1 ,349,082

$689,903

$689,903 $2,728,888

LOCAL COST

$6,532,91 8 $7,507,097 $7,753,007 $21 ,793,022

DOT DISTRICT # 5

CONGo DIST.

1 RDC

CG

...

,r.
\.

CAPITAL SCHEDULE FOR CHATHAM AREA TRANSIT AUTHORITY Section 5309
<
~smJt~~IJllf~~~~~~~r~~~t~ti~~~~~~~~~f~~~ll~tl~%11~~tMl111l~llt~~lj~~~iI IHIMi$I$OanimWm :iimmI!$.Q$"3$I~ii}m~ :;VtM5.ISl.ltMIHI 1}\M~\1mt~)tttl~1~lt~?~~~~~ :QasCBIR1fJPNmm;n;tmm;t:m;;u;:tttt:::I:mmm:ummllHI1@ ~nIIItftl:::Qn:mmmm mmUit::eIHUtmmnr w;m;;mlflM;na:::uUUJ:=:i: ;:i~Jt~m[Q;r.AI~nnUll

Buses and Facilities

$10,000,000 $4,000,000 $4,000,000 $18,000,000

Water Taxi Program

$620,350

$0

$0

$620,350

:RBaaeC1HCQ$.liIfWmmW)iltm;mmi:Um;mmllm@tti:I mmf$.IJI~I.II.~35.I!i :immt$IUJOOJIOni; limW;$.I1QJQ~QJJb: i:rll$.1:I.~lal.~3$.Q!i

FEDERAL COST

$8,496,280 $3,200,000 $3,200,000 $14,896,280

LOCAL COST

$1 ,062,035

$400,000

$400,000 $1,862,035

STATE COST

$1 ,062,035

$400,000

$400,000 $1,862,035

DOT DISTRICT # 5

CONGo DIST.

1 ROC

CG

r::"'.

7~" ....-,

... ' ..' -"

y'

V,"

,',.

u.

h

CAPITAL SCH E0 ULE INSAVAN NAH FOR EL0 ERLV AN 0 DISABLE0
Section 5310
=:~~ :$mJRUK:(\\I(\\b:::tiW(::\IIII':::::t:::::i\:IIIIIIi\tIIII\it:(:I(\,ItttI :i:"'::'::i:iSY.ilQg1.itr::t'W: \:(I(:I(::SYZU2.$ItnU:
P~Q$.UtlngN:r:'::::r:::@t;;tI't::'1:::1::::::::11:::'rrrr:::1::::111t11:::'}::: :%r::t1::F:~;NQliHm:::@::'m':':: :::::t:@1:,j:f,1lYUU:ttt::::tj;;

Purchase of Service

$108,701

$108,701

Purchase of Service

$114,136

$114,136

Purchase of Service

$119,843

$119,843

jea~4p.llM~Q~i%}t;;tJttI:;;:rjt:r::::;;n::nlWnn:t:t:::Itt: ?::?t:;'::t:tt$I'a8.fl.41:: ?:tt:':;'::t:'I:::$,1::1t1~j:a&:: ::::::::IH?':'::t:::$.'4:~n~f~, :I:lt:m::::;:m:::$~4~;'l?:A~

FEDERAL COST

$86,961

$91,309

$95,874

$274,144

STATE COST

$21I 740

$22,827

$23,969

$68,536

DaT DISTRICT # 5

Ca NG DIST.

1 RDC

CG



..



o
.~
:~. .:

..
Wamer Robins

50

"

.r,

.

'\~~.~

,..........--.,
~.... ,.)/

... r';'!1~

k

....

"

','.'Il

i~ .

."J

.... .. ~"".""""'"

;._'....,....1.'

':

.~

~"" ";:

CAPITAL SCHEDULE IN WARN ER ROBINS FOR ELDERLY AND DISABLED
Section 5310

= = - :$:J!JBHt:~;)m)::::::::ff::::::;::ftmf::::f;::I::mfilI:::mtm:::::~~:{:::~::::::::~t:f::::f:nii~M:1iq~J.lI:gj:f:I:::::~M4qJ!1tnt t:tlI6M::PIIt::::t ::::IIIIffiY=:::P.~:~::Itil

Purchase of Service

$ 18, 828

$ 18,828

Purchase of Service

$ 19, 769

$ 19,769

Purchase of Service

$20, 757

$20,757

glg4.ig11:Q~$immi:@J::i~:::i:::::::IIE:iiiiII::::~:~I:~:i~I:~;H:I;iM:i~'la~g~:mII:I::~::$1:a~i:QaIldmii'Ug~Z$Z:::i::::~::::11I:~$.~i.n~$A:

FEDERAL COST

$ 15,062

$ 15,8 15

$ 16,606

$47,483

STA TE COST

$3,766

$3,954

$4, 151

$ 11I 871

...t..i..l.

DOT DISTRICT # 3

CONG DIS.

2 RDC

MG

.,..





......

<>

,.

CAPITAL SCHEDULE FOR NONURBANIZED TRANSIT (Peach County) Section 5311

$i[UiMlftrttimmli@ttJimimmWrtmr:li'ttthi t:ri:l:e.9.QQ4mr mmlC$.(ffmmm 't:liil.Q?:QQQNr: ~~~tltt~r@tjttttf@ :mga,8.f.BDi;ir11IWmmimririmiirmrII'il :rrr;;liY.ii~nnr:;;ii ;mrrifirt:iQm:i:rm; ;mt:ifiYIpgmWr :::@W;rQIAWM:;i:i::

Mini-Van with Lift

$40,000

$40,000

:RI!9l.@ilU;Q$F.MllmmlllrIIlll\tttl:l mlttta9iPQQ I11im@1:lmltIA @Wm;mWltl'RlllIII::lMilg:t

FEDERAL COST

$32,000

$0

$0

$32,000

STATE COST

$4,000

$0

$0

$4,000

LOCAL COST

$4,000

$0

$0

4,000

DOT DISTRICT # 3

~ONG. 015T

2 ROC

MG

OPERATING ASSISTANCE FOR NONURBANIZED AREA TRANSIT (Peach County) Section 5311

~~1J11Ita~%U~t~~~%~1~~1%~~~~~~~tt~~~~%~~{~~t~~~l~t{~~~~{~~~{~~~~~~;~UU m;:ae.9.QI!4Nl mnaa$.pgWI nWaalQHm:I ~tt{;j~Jtttt~lI~t~t{~i :lSpeSAIJNGtBSlJIUimmW1UW;lmmlm mmHR'\Q~fItn :im:lU1i~NQ1Jtm; lWiUPlV{9.IWlll:;r :;:ltffiQWUn:lU:

(01/01/00 - 12/31/00)

$87,860

$87,860

(01/01/01 - 12/31/01)

$92,725

$92,725

- (01/01/02 12/31/02)

$96,800

$96 j800

!;eSaISGI111.tl.SZlmmWmmU;WMrillilUm rlfU$lil~llfb :i:iM:illiDIIZI:(ti lIWIU$.IIBQ1:: il':r:l$.2ZZ~il$.I

FEDERAL COST

$43,930

$46,363

$48,400 $138,693

LOCAL COST

$43,930 $ 46,363 $ 48,400 $138,693

DOT DISTRICT # 3

CONGo 015T

2 ROC

MG

:~

Statewide



m

w~

".

iIf!',

53

Q .~

"r'"',''' '

"'I"~ .'.,-~:
i..... ,

r
. t'

v,
~

CAPITALSCHEDULE FOR ELDERLY AND DISABLED (Statewide) SECTION 5310
_~!f.tt}::::}; ;~;;};;)t:~;~~WY~;};;t ;:;;::::;:;:;!t:r:;:~~~:+;::;;~ ;~;:;t:n!!:~~w!."H:}}, :::}J:::::!;M:;!;~!iii:;}+:

1

8V8001

(15 Counties) 8V8013

8 8025

2

8 8002

(13 Counlles) 8 8014

8 8026

4

8 8004

(10 Counlles) 8V8016

8V8028

5

8 8005

(11 Coumles) 8 8017

8 8029

6

8 8006

(15 Counlles) 8V8018

8v8030

7

8V8007

(11 Counlles) 8 8019

8 8031

8

8 8008

(16 Counites) 8V8020

8 8032

9

8 8009

(15 Coumtes) 8 8021

8V8033

10

8V8010

(14 Counties) 8V8022

8 8034

11

8 8011

(18 Counties) 8 8023

8 8035

12

8 8012

(9Counlles) 8V8024

8V8036

$135,558 $97,903 $99,786 $69,661 $47,068 $41,420 $67,779 $69,662 $73,427 $24,476
$317,175

$142,336 $102,798 $104,775
$73,145 $49,422 $43,492 $71,168 $73,145 $77,098 $25,700 $330,785

$149,453 $107,938 $110,014
$76,802 $51,893 $45,666 $74,723 $76,802 $80,953 $26,985 $347,478

$427,347 $308,639 $314,575 $219,608 $148,383 $130,578 $213,670 $219,609 $231,478
$77,161 $995,438

~si::::~:;:~;::t:::t: ::;::m;~~B ~ ::;~::m~;~~~i~irt; ::;:;+'2',~29,~'89"

'STATE COST (20%) .LOCAL I-UNUS (0%)

$ 208,783 $ 218,773 $ 229,741 $ 657,297

0

0

0

0

. '. ."



..

...

. Ii

CAPITAL SCHEDULE FOR STATEWIDE NONURBANIZED AREA TRANSIT
Section 5311
:.:-.:....:.:. JP,UJ .~~:my.::(~"8ffl~:n~:mJ~~~jl i.ffilRlfMtt ?~jJntlltiMmJ:jl:~ :i~jlMlifYlg91m:jttt :ltitltF:X~P.J.llfIIj Ijlt@(fQIAPIIIIj

1

Gainsville

1C9004

$432,000

1C9005

$199,000

1C9006

$ 119,000

$750,000

2

Tennille

2C9004

$1,129,500

2C9005

$555,000

2C9006

$ 356,000

$2,040,500

3

Thomaston

3C9004

$192,000

3C9005

$415,000

3C9006

$ 326,000

$933,000

4

Tifton

4C9004

$182,500

4C9005

$277,000

4C9006

$ 115,500

$575,000

5

Jesup

5C9004

$310,000

5C9005

$384,000

5C9006

$

78,000

$772,000

1.1
V.

6

Cartersville

6C9004

$712,000

6C9005

$434,000

6C9006

$ 383,000

$1,529,000

7

Atlanta

7C9004 7C9005

$0 . $0

7C9006

$0

$0

All

Supplemental

8C9004 8C9005

$100,000
.

$100,000

8C9006

$ 100,000

$300,000

All

Intercity Bus

8C9102-

$927,439

8C9103

$1,007,527

8C9104

$ 1,007,527

$2,942,493

~)fl{ttmttllt :rOTAtn:WSmSmttimtMWW1MiMttt tMi:f~i$.;iHJ.aS.A@~ %ttm$,gi$l~lP.~ :;:Mi;;t$.liJ17~g tttft$iia:!1:~OO~

: i : : :':i .: :;: :;.:I:ij!:I I: 1 :1 1: :i: :'I:i: :i1~1: ~:~: :::.;:~::::,:,:= 1tEOE.fJAt::~o.a.$:nts.o.%.:lm:r~::~~i~f)f~~::llI

. :.. :. . :~~mi:~If$.~r:l:a~J~J:

~:::~:::rtr:.$...f..J.l.~1:m:~:Qq~?:t'n?:9tftjt~tiff$$.lrA7lfal~gPg'

:l~l~:~:~:$.l:::~1~j~4
.~S4m~@

~MWpnf:l:JJ::::::PM4If!~Q

~4AOO

.. ~ "~

OPERATING SCHEDULE FOR STATEWIDE NONURBANIZED AREA TRANSIT Section 5311

QISTBIGIWf QJS.TRtCTNANJE?~;;t});~ STIPJf:=:=)? ~)::~;:tFYi~QQQ;~~:;:;:i):;. ::::~:::~::i:::FY:~:~Qo.t:::mi~:i: ::::::::ii}ifYaOO:2.t:it~): :::ffii~::IQ;rAWti:t:f.

1

Gainsville

189004

$728,570

189005

$766,026

189006

$804,324

$2,298,920

2

Tennille

289004

$2,030,264

289005

$2,131,042

289006

$2,232,595

$6,393,901

3

Thomaston

389004

$1,609,630

389005

$1,687,515

389006

$1,753,992

$5,051,137

4

Tifton

489004

$902,810

489005

$968,946

489006

$1,017,389

$2,889,145

5

Jesup

589004

$825,225

589005

$1,015,825

589006

$1,053,800

$2,894,850

6

Cartersville

689004

$1,613,000

689005

$1,661,000

689006

$1,658,300

$4,932,300

7

Atlanta

N/A

$0

N/A

$0

N/A

$0

$0

ALL SUPPLEMENTAL

889004

$300,000

889005

$300,000

889006

$300,000

$900,000

:r.OTA'L;;CO.$.r$iilmnnWnWn:(ttt)ln:~: :ttt~lJmQP.llA.~I;;qlm'~i.lqg.~4 ::;;:m::t~,m~A.9P. .@:r;;,jU~i~~~~~1

FEDERAL COST (50%)

$4,004,7501 $4,265,177

$4,410,200 $12,680,127

LOCAL FUNDS (50%)

4,004,750

4,265,177

4,410,200

12,680,127

., .r- .,

...



)



I

I

STIP Financial Plan

I

I

I

I

I

I

I
h,'r

~

.



'0

STIP Financial Plan

;.'~..i..

The following describes how the STIP Financial Plan (SFP) was developed for State Fiscal 2000-

-~

.2002. The SFP is the spending plan for allocating transportation funding to state and local projects.

It addresses a time period of three years, and, by law, is fmancially constrained by forecasted

c

funding .levels. Forecasted funding levels are based on the historical spending authority provided to

Georgia in 1999 adjusted to projected funding estimates as provided in the current multi-year

transportation bill signed by Congress. Added to the adjusted funding ceiling are the previously

appropriated/allocated Federal funds (carry-over) that are unexpended and available for year 2000.

Projects assigned to these carry-over funds will be developed and can be let to construction, by any

of the following 3 methods:

1. Conditioned on obligation authority appropriated by Congress, 2. The advance construction provision where state or local government funds are used with a
promise of repayment when federal allocations become available. 3. From redistribution of unexpended Obligation Authority from other states.

This funding ceiling determines the estimated available funds that are reasonably expected to be obligated over the upcoming three years of the STIP. Only those projects or an identified phase (preliminary engineering, rights-of way or construction) of a project which have a STIP dedicated public or private funding source are eligible for placement into the three-year program.

The Transportation Improvement Programs (TIP) and their related funding, developed by the 11 Metropolitan Planning Organizations (MPO), are incorporated into the STIP by reference.

The State Fiscal 2000-2002 SFP totals $4.03 billion with a FY 2000 annual program of $1.79 billion. Funding for this three-year program includes $2.90 billion in federal funds, $1.03 billion in state funds, and $97.02 million in local funds. This level of infrastructure investment will support nearly 169,000 jobs in the construction industry. In addition to the construction jobs generated by the program, a well-maintained transportation system fosters a healthy economy by providing the infrastructure needed for efficient movement of goods and people. Efficient transportation is fundamental to productivity.

HIGHWAY PROGRAMS

Interstate Maintenance (1M) - Funds used for resurfacing, restoration, and rehabilitation of the Interstate Highway System These funds cannot be used to provide new capacity to the system, nor
for construct.ion of new facilities such as rest areas, po.rts of entry, etc.

National Highway System (NHS) - A system of highways considered most important to interstate

.travel, national defense, connection with other modes of transportation, and are essential to

international commerce. The system includes the current interstate highways and other routes

designated by the state and Federal Highway Administration (FHWA).

.

.'

1

Surface Transportation Program (STP) - These funds may be spent on any road that is functionally classified as collector or higher. The funds may be used on projects ranging from new construction to resurfacing, and may also be used for transit projects,

Fifty percent of the funds are allocated to urban and rural areas of the state based on population. .

)

Thirty percent can be used in any area of the state at the discretion of the State Transportation Board.

Of the remaining 20 percent of the funds, ten percent must be spent on highway safety projects and

ten percent must be spent on Transportation Enhancement projects. Safety projects include Hazard

Elimination, Railroad Crossing, and Railroad Protective Devices.

~,

.

The Transportation Enhancement Program has been of particular interest to the general public and

users of non-traditional transportation related facilities. The State Transportation Board has ..

.established the Enhancements Advisory Panel The purpose of this panel is to represent statewide

interests with their expertise in the TEA categories of multi-use facilities, historic resources, .

transportation aesthetics and scenic preservation as they advise GDOT management and the State

Transportation Board.

.

Enhancement projects are defined as: "...provisions of facilities for pedestrians and bicycles; provision of safety and educational activities for pedestrians and bicyclists; acquisition of scenic easements...or historic sites; scenic or historic highway programs (including the provision of tourist and welcome center facilities), landscaping and other scenic beautification; historic preservation, . rehabilitation and operation of historic. highway buildings, structures, or' facilities (including railroad . facilities); preservation of abandoned railway corridors (including the conversion and use thereof for pedestrian or bicycle trails); control and removal of outdoor advertising, archaeological planning and research; and environmental mitigation to address water pollution due to highway runoff, or reduce vehicle-.caused wildlife mortality while maintaining habitat connectivity, and establishment of transportation museums." .

Applications for projects are accepted orily from public agencies. Private groups are encouraged to participate by applying through the appropriate public agency. Project sponsors must provide 20% matching funds.

Congestion Management!Air Quality (CMAQ) - These funds are for projects, which can be proven to reduce traffic congestion and/or improve air quality in non-attainment areas. Projects such as park and ride lots, signal coordination, and ride sharing qualify for these funds. Currently, there are thirteen counties in the non-attairiment area: Cherokee, Clayton, Cobb, Coweta, DeKalb, Douglas, Fayette, Forsyth, Fulton, Gwinnett, Henry, Paulding, and Rockdale.

Bridge Replacement (BR) - These funds are for the replacement or rehabilitation of substandard

bridges both on and off the federal system. Bridges must have a span of 20 feet and must be listed

on the Federal Register with a sufficiency rating of 80 or less for rehabilitation and 50 or less for

replacement.

.

Demonstration or High Priority (Demo, HPP) - Congressionally authorized funds designated for construction of specified projects.

2

HIGHWAY FUNDING SOURCES

State Funding Sources - The State makes funds available from several sources for matching

;

federal-aid funding. Sources include motor fuel taxes, special fuel taxes (diesel) and 3% state sales

tax on gasoline. Eighty-five percent of these fees are used for construction and maintenance of

highways. The remaining 15 percent are made available to the cities and counties for local road use

;:~
,j.

in the form of county contracts and state-aid let. Revenues from these sources are expected to grow

at about one percent a year. State funds are utilized for a variety of purposes but in the STIP program

~~m.
.

development, $536 million of these funds are used to match federal-aid highway.

Federal Highway Funding Sources - Revenues to pay for the $2.90 billion federal funds program

I.I~

are based on future estimates of federal revenue available to Georgia through the Highway Trust
Fund. Also added to this estimate is carry-over funding from the Intermodal Surface Transportation Efficiency Act (lSTEA) of 1991 and from Transportation Equity Act for the 21st Century (TEA-21)

of 1998. Georgia's estimated yearly share from the Highway Trust Fund is expected be about 3.51%

ItI.'.

of the estimated $26.47 billion or $927.28 million. The obligation ceiling for Georgia is estimated to be 92.5% of the apportioned amount or about $673.85. The amounts by fund code are calculated and

I

distributed based on 1999 percentages 'received by Georgia under TEA-21. The above estimates are subject to change based on forthcoming yearly appropriation and obligation levels set by Congress.

I

Local Highway Funding Sources - During the three-year program, an estimated $95.63 million in

local funds will be needed to match federal and state aid for local projects and for limited

I

participation in improvements on the state system

FY 2000-2002 HIGHWAY PROGRAM FUNDING

I

The $4.03 billion highway program for FY 2000-2002 includes $2.58 billion for improvements to

d

the state highway system, with the remaining $1.45 billion available for the local roads and projects.

Im..,,.

The primary funding sources of the federal-aid to local governments are the Surface Transportation Program and the Bridge Replacement and Rehabilitation Program Local governments also receive

federal demonstration funds for specific projects and Congestion Mitigation!Air Quality funds based

I.

on project eligibility and selection. Enhancement projects are selected statewide based on the guidance provided through the Georgia Transportation Enhancement Program.

I

The following table summarizes project funding by ownership type for FY 2000-2002:

FY 2000-2002 Highway Project Funds

I

,

($ Millions)

Project Distribution

FY 2000

FY 2001

FY 2002

Total

i

State Hiahway

$

Local Roads and Streets

$

1,173 $ 614 $

711 $ 331 $

691 $ 515 $

.'. 2575
1,460

I

Total

$

1,787 $ 1,042 $ 1,206 $ 4,035

.'

I

The following table summarizes project funding by type of funds for FY 2000-2002:

3

I

FY 2000-2002 Highway Project Funds

($ Millions)

,

'.1'

Category of Funds Federal Aid

State

Local

Total

FY 2000 FY 2001 FY 2002

$ 1,324 $

710 $

865 $

$

400 $

308 $

332 $

$

63 $

24 $

9$

$ 1,787 $ 1,042 $ 1,206 $

Total 2,899 1 040 96 4,035

The following tables summarizes program funding by Category Groupings for FY 2000-2002:

Federal Aid Highway Matched Program Funds' FY 2000-2002
($ Thousands)

category Groupings
Interstate Maintenance National Highway System Congestion Mitioation Brtdoe Placement & Rehab ' Surface Transoortanon Program Tot Matched Apportionment

2000

2001

2002

$ 367,241 $ 211,880, $ ~15,768

$ 704,203 $ 383,457 $ 390,494

$ 76,003 $ 41,903 $ 42,672

$ 207,546' $ 97,867 $ 99,663

$ 572,520 $ 281,340 $ 286,503

$ 1,929,513 $ 1,018,448 $ 1,037,102

Total
$ ,794,889 $1,478,t54
s$ 160,579 404,076 $1 ',140,363 $ 3,978,061

Category Groupings Obligation Ceiling Minimum Allocation Minimum Guarantee Special Proiects Total-Ped Matched Available

2000

2001

2002

$ 673,850 $ 686,458 $ 699,054 $

$ 42,172 $ - $

-$

$ 124,259 $ 42,638 $ 43,421 $

$ 251,508 $ 82,581 $ 84,097 $

$ 1,091,789 $ 811,677 $ 826,572 $

Total 2,059,362
42,172 210,318 418,186 2,730,038

State Highway Program Funds FY 2000-2002
($ Thousands)

Category Groupings EDS STA Total State Available

2000

2001

2002'

$ 176,032 $ 133,000 $ 133,000 $

$ 88,931 $ 35,000 $ 35,000 $ $ 264,963 $ 168,000 $' 168,000 $

Total 442,032 158,931 600,963

4

Total Highway Program Funds FY 2000-2002
($ Thousands)

Category Groupings Federal Plus Match STA Total Available

2000

2001

2002

Total

(

$ 1,091,789 $ 811,677 $ 826,572 $ 2,730,038

$ 1,093,789 $ 813,678 $ 828,574 $ 2,730,038

$ 2,185,578 $1,625,355 $ 1,655,146 $ . 5,460,076

....,.-
c

':'" .
.5

TRANSIT PROGRAMS

The Georgia Department of Transportation in cooperation with the Federal Transit

Administration (FTA) and the state's public transit agencies work together to develop a

)

.program of transit service and facility improvements to enable them to meet their

transportation needs.

FTA Section 5307 Program - This program provides funding for capital, planning and operation assistance (areas with a population less than 200,000). Funds are distributed nationwide on a formula basis.

FTA Section 5309 Program - This program offers capital funding for public transportation systems on a .discretionary basis.

FTA Section 5310 Program - This program provides funding to private non-profit agencies for capital improvements to be used inthe provision of transportation service to elderly and disabled persons.

FTA Section 5311 Program - This program provides funding to enhance the access of

people in non-urbanized areas to healthcare, shopping, education, employment, public

services and recreation. Funds are available for capital equipment, operating and

administrative expenses.

.

TRANSIT FUNDING SOURCES

State Funding Sources - The state primary support for matching federal transit funding . is general sales tax revenues. One-half of the required twenty percent match is provided
by these taxes. State funds are utilized for a variety of purposes but in the STIP program development, $24 million of these funds are used to match federal-aid.

Federal Transit Funding Sources - The $414 million in federal-aid funds is partially based on estimates offederal revenue available to Georgia through the Transit Trust Fund and from earmarked funds in the Transportation Efficiency Act for the 21sl Century (TEA21).

Local Transit Funding Sources - During the three-year program, an estimated $128 million in local funds will be needed to match federal-aid for local projects. These funds are acquired through local sales taxes, special taxing districts, property taxes as well as general revenues.

.I

:. ;,~ 1." ,.

FY 2000 - 2002 Transit Program Funding

($ Millions)

I

Fund Source

FY 2000

Total FY 2000-2002 Annual Average

Section 5307

55

157

52

IIif:. '

Section 5309

88

Section 5310

2

232 5

77 2

Section 5311

8

20

7

Subtotal

153

414

138

State Funds

9

24

8'

Local Funds

46

128

43

Grand Total 207

566

189

.,

~.,...

)'
I
(;
(
...!
,".'.~'
I' ;~. -
I
15
V
:J.. '

'.'
t.
.,,'
,, ,
. .~ . i